MICE-UK, May 2005, pd 1
MICE Muon Beam
• Optics Design Work– Pion-Muon-Matching
• Engineering– Target– Conventional Magnets– Muon Solenoid
• MoU Signed• Delivery mid summer
– Diffuser– Hall (shielding)
MICE-UK, May 2005, pd 2
MICE-UK, May 2005, pd 3
Optics Design Work (KT)
• Since RAL collaboration meeting– Aimed to include material effects
• Scattering • Energy loss E)
– Calculations with G4Beamline (KW)– Fudge in Transport/Turtle
Match to E
~30%
MICE-UK, May 2005, pd 4
Q4
Q5
Q6
Q7
Q8
Q9
AI30
AI21
AI22
AI23
AI10
TOF0
ATC1
CKV1
AC20
D1
AC31
AC32
AC33
AC40
TOF1
AT1D
ε_source
Air filled
Muonsfrom decaysolenoid
H
V
TOF0 CHKV TOF1
Dipole
MICE-UK, May 2005, pd 5
Q4
Q5
Q6
Q7
Q8
Q9
AI30
AI21
AI22
AI23
AI10
TOF0
ATC1
CKV1
AC20
D1
AC31
AC32
AC33
AC40
TOF1
AT1D
ε_source / 10,000
Air filled
Muonsfrom decaysolenoid
H
V
TOF0 CHKV TOF1
Dipole
MICE-UK, May 2005, pd 6
Ways forward
• These effects have been included in the rate calculations– Materials, apertures
• The issue is to improve the design of the beam line to give a better through-put…
• Positions of TOF…• Positions of Qts and drift spaces• Blind optimisation of parameters (TR)
MICE-UK, May 2005, pd 7
Beam Line Engineering 1• Synchrotron
– Redesign of S7 (parts already manufactured)– Install in August– Trial build, clean and vac test
• Target & Benchmark– Opportunity to test a target in December
shutdown benchmark– Few pulse at start up – dispose of target!
MICE-UK, May 2005, pd 8
Beam Line Engineering 2
• Beam pipes
• Stands
• Vacuum
• Power supplies
• Controls
• Water
• Test beam elements (HV, Water)
MICE-UK, May 2005, pd 9
Diffuser• Issues:
– Engineering solution– Integration around front of tracker
• Tracker access for installation• Diffuser installation• Access to ToF, Cherenkov• Large shield plate
MICE-UK, May 2005, pd 10
250mm
980 mm
“wrong end” for diffuser- space is the same
MICE-UK, May 2005, pd 11
Stephanie Yang/Wing Lau Ring fixed to tracker
diffuser
Rings pushed togetherTo open levers… and install diffuser atcorrect place
http://www.isis.rl.ac.uk/accelerator/mice/beamline/diffuserassmby2.avi
MICE-UK, May 2005, pd 12
Progress & Risks• Progress against plan:
– About 6 months slack in programme– S7 – completed procurement– Vacuum & Beam pipes
• design in progress
– Need to move on • Controls• Cooling/Infrastructure (hope to reuse)• Power supplies
• Risks:– Shielding (cost)– Issue with quadrupoles (Q35s) (cost)