Post on 19-Nov-2020
Working together builds better results
Major works framework
WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK 03
Introducing LCP
LCP aims to explore and deliver any
benefits that might be realised through
collaborative working between public
sector clients in the 33 boroughs
across London and other public sector
organisations within London. LCP’s
strategic aim is for London’s public sector
commissioning authorities and buying
organisations to work collectively to
achieve higher benchmarks using their
respective strengths and combined
resources.
The LCP partnership goal is to
avoid duplication and inefficiency in
construction procurement and maximise
value for money from construction
projects by aligning and harmonising
the supply market offer available to
public sector organisations in London.
The London Construction Programme (LCP) was
established in 2012 by Haringey Council, encouraged and
supported by London Councils, to develop a pan-London
strategy to improve construction procurement.
LCP is a virtual partnership of various buying organisations offering procurement solutions to deliver construction projects more efficiently and effectively. The various buying organisations who comprise the LCP board are currently:
-- Haringey Council
-- LHC
-- Crown Commercial Service (CCS)
-- Hampshire County Council (Southern Construction Framework)
LCP offers framework agreements, contracts and category management
support to deliver construction projects more efficiently and effectively
across the capital.
Televiv Harry, LCP Framework Manager
02 WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK
WWW.LCP.G2B.INFO 0504 WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK
Framework highlights:
-- Coverage of all types of construction projects including offices, schools, leisure, housing refurbishment anddesign and build etc
-- Pre-selected and performance managed class-leading contractors
-- Standardised yet flexible contracts
-- A range of key performance indicators and tracking tools
-- Expert 2nd line support from industry and sector specialists
-- Flexibility in procurement routes (although 2 stage open book tendering is recommended for higher value bands)
-- Value for money, risk and cost control
-- Government initiatives (e.g. fair payment, apprenticeships, localism)
-- Improved procurement efficiency The framework is designed for use exclusively for public sector organisations in London to procure all types of construction works efficiently, quickly and compliantly
-- Best practice procedures and support A key feature of the framework is the provision of a full suite of documentation, best practice procedures and related knowledge to guide the user to achieve the best outcome
-- Quality assured construction contractors The framework has been created by London Authorities for London Authorities and provides access to the leading construction contractors in London, selected through a robust quality evaluation process for their excellence in delivery of public sector building works
About this framework
This comprehensive framework is
relevant for all major construction works
and associated services.
All types of construction projects are included from schools and leisure buildings to offices
and housing refurbishment
The LCP Major Works framework offers:
WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK 05
-- Disposal of existing and development projects
-- Ability to raise development finance
-- Infrastructure including design, sales, marketing, aftercare and maintenance
Development covers both work areas including but not limited to:
-- Demolition
-- New build development
-- Infill development
-- Mixed use developments
-- Repair, maintenance and upgrading of the structure, external fabric of individual buildings and communal areas
-- Planned maintenance – capital and revenue projects
-- Internal works including kitchens and bathrooms
-- Mechanical and electrical works
-- Replacement of roofs, doors and windows and associated works
-- Fire prevention works (including fire doors)
-- Planned maintenance either capital and revenue projects
-- Adaptations
-- Refurbishments
-- Regeneration works
-- Structural works
-- Extensions
-- Remodelling
-- Mechanical and electrical
-- Energy efficiency measures
-- Retrofit
-- Redecoration of the outsides of buildings and communal areas
-- Works to estate areas, such as landscaping, replacement of paths, provision of fencing etc
-- New build housing and development
-- Conversion of existing buildings for residential or other use including heritage buildings
-- Design elements where applicable
-- Installation works and services
-- Energy efficiency measures
-- Retrofit
-- Fit out
-- Demolition
-- Development and mixed use development
-- Design elements where applicable
Building works delivered
Housing covers refurbishments,
extensions, new build including:
Education, and other areas including leisure, care,
health, industrial, commercial and administrative
(inclusive of fit out) including:
0706 WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK
08 WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK
Framework eligibility
The London centric framework
is exclusively designed for:
-- The London Boroughs and the City of London
-- Greater London Authority Group including, but not limited to: Transport for London, LondonFire and Emergency Planning Association, (London Fire Brigade), Mayor’s Office for Policing andCrime &Royal Parks
-- Police and Emergency Services in Greater London – fire authorities, fire and rescue authorities, police authorities, and the Metropolitan Police Authority/Service and Ambulance Authority/Service
-- Educational Establishments in Greater London– schools, school governing bodies; voluntary aided schools; foundation schools; any faith educational establishments including the Roman Catholic Dioceses and Anglican Dioceses, associated with the named Local Authorities including diocesan authorities; academies; free schools, city technology colleges; foundation partnerships; education authorities, publicly funded schools, universities, colleges, further education establishments; higher education establishments and other educational establishments
-- House of Commons and the House of Lords but excluding Government Departments
-- All Providers of Social Housing in London – Registered Providers of Social Housing (as defined in the Housing and Regeneration Act 2008), and as registered with the Home and Communities Agency (or its successor body), Tenant Management Organisations(TMOs) and their agents, all Arms Length Management Organisations (or any successor bodies) established by Local Authorities within Greater London
-- NHS Establishments in Greater London – Primary Care Trusts successor groups (Clinical Commissioning Groups), NHS Authorities, NHS Trusts (including Foundation Trusts), healthcare organisations associated with the Local Authorities within the Greater London Area
-- Trusts, Charities, Social Enterprises, Mutuals, and Community Interest Companies – organisations that have been established by the public bodies within the scope of this advertisement and/or where the contracting public bodies are trustees or partners of the Trusts, Social Enterprises, Mutuals and Community Interest Companies or any similar organisation and the Royal Botanic Gardens, Kew
-- Other Public Sector Organisations, Waste Authorities, Local Government Association, The Electoral Commission and Lee Valley Park Authority
Our frameworks benefit public sector organisations serving London; including the NHS, emergency services, social housing providers,
schools, social enterprises and many more.
WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK 09
10 WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK
LCP Major Works framework process
Contact LCP to sign an access agreement in
order to receive a framework
information pack
Meet with LCP Framework
Manager to discuss requirements
including pipeline of works
Client to contactConsultants (if needed)
Using the Project Notification
document, send project details
to LCP to obtain project number
Carry out softmarket testing
Agree the formof procurementfor the project
Using the EOI document, send out the project
details to all framework suppliers
on relevant lot
Framework suppliersreturn EOI document
to client
Mandatory requirements
Using the Capability Assessment
document, evaluate EOIs and shortlist to 3/4 (or as required)
Notify successful/unsuccessful,
providing feedback where applicable
Using the EOI Feedback document,
notify LCP of the results
Using the Outline Call-Off document,
send out tender information to
suppliers (two or single stage)
Using the Evaluation templates,
recommend a supplier
Notify tenderers via templated Outcome
Leters. Feedback and standstill
recommended
Notify LCP of successful supplier
using Project Award Form
Using the contract form
of your choice, appoint
Supplier-Single Stage or
Pre-construction
– 2 Stage (Set up a
project team workshop)
Issue Stage 2 tender at end of Pre-construction
(2 Stage only)
Continue with project using
recognised Gateway Approval process
Report as required under Access Agreement
Completion followed by
LCP feedback collection
Recommended action
WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK 11
12 WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK
Award weighting criteria
Each framework supplier has been assessed
on the below criteria. The Major Works Framework
includes the flexibility for clients to adjust the weighting
to meet their and/or project needs.
Quality -- 55% Qualitative Assessment
and the ability to service LHC
framework requirements
-- 5 Memberships including NFRC,
CHAS, Considerate Contractor
or equivalent
60%Price -- Schedule of Rates:
Three scenarios were included
which were automatically formatted
from the completed Schedule of Rates.
The scenarios aided companies in
agreeing the approved maximum
prices (AMPs)
40%
Approved framework suppliers
£100,000-£999,999 Lot 1 NH1 £1,000,000–£4,999,999 Lot 2 NH2 £5,000,000 plus Lot 3 NH3
Architectural Decorators Ltd Cosmur Construction (London) Ltd Durkan Ltd
Cityline Construction Ltd Durkan Ltd Geoffrey Osborne Ltd
Cosmur Construction (London) Ltd Geoffrey Osborne Ltd Higgins Construction PLC
Cuttle Construction Ltd Keepmoat Regeneration Ltd Keepmoat Regeneration Ltd
Keepmoat Regeneration Ltd Kind Diamond Build Consortium Kind Diamond Build Consortium
Kind Diamond Build Consortium Lakehouse Contracts Ltd Lakehouse Contracts Ltd
Lakehouse Contracts Ltd Mulalley and Company Ltd Mulalley and Company Ltd
Lengard Ltd Wates Construction Ltd Wates Construction Ltd
Mulalley and Company Ltd
Sandwood Design and Build Ltd
£100,000-£999,999 Lot 4 NE1 £1,000,000–£4,999,999 Lot 5 NE2 £5,000,000 plus Lot 6 NE3
Beardwell Construction Ltd Barnes Construction Geoffrey Osborne Ltd
Cosmur Construction (London) Ltd Geoffrey Osborne Ltd Higgins Construction PLC
Cuttle Construction Limited Keepmoat Regeneration Ltd Keepmoat Regeneration Ltd
Keepmoat Regeneration Ltd Kind Diamond Build Consortium Kier Construction Ltd
Kind Diamond Build Consortium Lakehouse Contracts Ltd Lakehouse Contracts Ltd
Lakehouse Contracts Ltd Mulalley and Company Ltd Mace Ltd
Mulalley and Company Ltd T&B (Contractors) Ltd Wates Construction Ltd
Shaylor Group PLC Wates Construction Ltd Willmott Dixon Holdings Ltd
T&B (Contractors) Ltd
VINCI Construction UK Ltd
North London (Barnet, Camden, Enfield, Hackney, Haringey, Islington)
Housing
A list of all the companies approved
by LCP to work on our frameworks.
WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK 13
14 WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK
£100,000-£999,999 Lot 13 SEH1 £1,000,000–£4,999,999 Lot 14 SEH2 £5,000,000 plus Lot 15 SEH3
Cityline Construction Ltd Cosmur Construction (London) Ltd Durkan Ltd
Cosmur Construction (London) Ltd Durkan Ltd Geoffrey Osborne Ltd
Cuttle Construction Ltd Geoffrey Osborne Ltd Higgins Construction PLC
Keepmoat Regeneration Ltd Keepmoat Regeneration Ltd Keepmoat Regeneration Ltd
Kind Diamond Build Consortium Kind Diamond Build Consortium Kind Diamond Build Consortium
Lakehouse Contracts Ltd Lakehouse Contracts Ltd Lakehouse Contracts Ltd
Lengard Ltd Mulalley and Company Ltd Mulalley and Company Ltd
Mulalley and Company Ltd Wates Construction Ltd Wates Construction Ltd
Standage & Company Ltd
£100,000-£999,999 Lot 19 SWH1 £1,000,000–£4,999,999 Lot 20 SWH2 £5,000,000 plus Lot 21 SWH3
Cityline Construction Ltd Cosmur Construction (London) Ltd Durkan Ltd
Cosmur Construction (London) Ltd Durkan Ltd Geoffrey Osborne Ltd
Cuttle Construction Ltd Geoffrey Osborne Ltd Higgins Construction PLC
K & A Construction Keepmoat Regeneration Ltd Keepmoat Regeneration Ltd
Keepmoat Regeneration Ltd Kind Diamond Build Consortium Kind Diamond Build Consortium
Kind Diamond Build Consortium Lakehouse Contracts Ltd Lakehouse Contracts Ltd
Lakehouse Contracts Ltd Mulalley and Company Ltd Mulalley and Company Ltd
Lengard Ltd Wates Construction Ltd Wates Construction Ltd
Mulalley and Company Ltd
£100,000-£999,999 Lot 16 SEE1 £1,000,000–£4,999,999 Lot 17 SEE2 £5,000,000 plus Lot 18 SEE3
Beardwell Construction Ltd Geoffrey Osborne Ltd Geoffrey Osborne Ltd
Cosmur Construction (London) Ltd Interserve Construction Ltd Higgins Construction PLC
Cuttle Construction Ltd Keepmoat Regeneration Ltd Keepmoat Regeneration Ltd
Keepmoat Regeneration Ltd Kind Diamond Build Consortium Kier Construction Ltd
Kind Diamond Build Consortium Lakehouse Contracts Ltd Lakehouse Contracts Ltd
Mulalley and Company Ltd Mulalley and Company Ltd Mace Ltd
Shaylor Group PLC T&B (Contractors) Ltd Wates Construction Ltd
T&B (Contractors) Ltd Wates Construction Ltd Willmott Dixon Holdings Ltd
VINCI Construction UK Ltd Willmott Dixon Holdings Ltd
£100,000-£999,999 Lot 22 SWE1 £1,000,000–£4,999,999 Lot 23 SWE2 £5,000,000 plus Lot 24 SWE3
Beardwell Construction Ltd Geoffrey Osborne Ltd Geoffrey Osborne Ltd
Cosmur Construction (London) Ltd Interserve Construction Ltd Higgins Construction PLC
Cuttle Construction Ltd Keepmoat Regeneration Ltd Keepmoat Regeneration Ltd
Keepmoat Regeneration Ltd Kind Diamond Build Consortium Kier Construction Ltd
Kind Diamond Build Consortium Lakehouse Contracts Ltd Lakehouse Contracts Ltd
Lakehouse Contracts Ltd Mulalley and Company Ltd Mace Ltd
Mulalley and Company Ltd T&B (Contractors) Ltd Wates Construction Ltd
Shaylor Group PLC Wates Construction Ltd Willmott Dixon Holdings Ltd
T&B (Contractors) Ltd Willmott Dixon Holdings Ltd
VINCI Construction UK Ltd
Education and other
Education and other
South East London (Bexley, Bromley, Croydon, Greenwich, Lambeth, Lewisham, Southwark)
Housing
South West London (Kingston, Merton, Richmond, Sutton, Wandsworth)
Housing
£100,000-£999,999 Lot 25 WH1 £1,000,000–£4,999,999 Lot 26 WH2 £5,000,000 plus Lot 27 WH3
Cityline Construction Ltd Cosmur Construction (London) Ltd Durkan Ltd
Cosmur Construction (London) Ltd Durkan Ltd Geoffrey Osborne Ltd
Cuttle Construction Ltd Geoffrey Osborne Ltd Higgins Construction PLC
K & A Construction Keepmoat Regeneration Ltd Keepmoat Regeneration Ltd
Keepmoat Regeneration Ltd Kind Diamond Build Consortium Kind Diamond Build Consortium
Kind Diamond Build Consortium Lakehouse Contracts Ltd Lakehouse Contracts Ltd
Lakehouse Contracts Ltd Mulalley and Company Ltd Mulalley and Company Ltd
Lengard Ltd Wates Construction Ltd Wates Construction Ltd
Mulalley and Company Ltd
£100,000-£999,999 Lot 28 WE1 £1,000,000–£4,999,999 Lot 29 WE2 £5,000,000 plus Lot 30 WE3
Beardwell Construction Ltd Geoffrey Osborne Ltd Geoffrey Osborne Ltd
Cosmur Construction (London) Ltd Interserve Construction Ltd Higgins Construction PLC
Cuttle Construction Ltd Keepmoat Regeneration Ltd Keepmoat Regeneration Ltd
Keepmoat Regeneration Ltd Kind Diamond Build Consortium Kier Construction Ltd
Kind Diamond Build Consortium Lakehouse Contracts Ltd Lakehouse Contracts Ltd
Lakehouse Contracts Ltd Mulalley and Company Ltd Mace Ltd
Mulalley and Company Ltd T&B (Contractors) Ltd Wates Construction Ltd
Shaylor Group PLC Wates Construction Ltd Willmott Dixon Holdings Ltd
T&B (Contractors) Ltd Willmott Dixon Holdings Ltd
VINCI Construction UK Ltd
Education and other
West London (Brent, City of London, Ealing, Harrow, Hammersmith and Fulham, Hillingdon, Hounslow, Kensington and Chelsea, Westminster)
Housing
Greater London is defined as the area covered by all the London Local Authorities and all the following postcode areas AL, WD, EN, CR, DA, BR, SM, KT, TW, UB, HA, IG & RM
Approved framework suppliers continued
Approved framework suppliers continued
WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK 15
In association with:
WWW.LONDONCONSTRUCTIONPROGRAMME.CO.UK 0208 489 5303