Lucila Gonzalez Disaster Financial Planning and...

Post on 09-Oct-2020

2 views 0 download

Transcript of Lucila Gonzalez Disaster Financial Planning and...

Lucila Gonzalez

Disaster Financial Planning and Recovery

• California Department of Transportation (Caltrans)

• Staff Services Manager II

• Lucila.Gonzalez@DOT.CA.GOV

“Seguridad de infraestructura estratégica”

Discussion Topics❑ Caltrans Organizational Structure❑ Disaster Financial Planning – why ?❑ Define Hazards and Risk ❑ Cost of Network Disruption❑ Governance and the Stafford Act❑ Planning Tools and Documents ❑ Caltrans Disaster Recovery Financing❑ Economic Studies used for Disaster Financial Planning and Response

- SAFR- RRAP

❑ Conclusion

Infrastructure

15,000 centerline miles of highway

26,000 state and local bridges

440 Caltrans building facility sites

Organization

19,000 employees

12 Districts

Caltrans Organizational Profile

Disaster Financial Planning – why ?

❑ How will you pay for short or long term recovery?❑ What is the length and impact of the Disruption?❑ Are lifeline assets impacted, such as utilities, because of the disruption?❑ Is this a lifeline route ?❑ What is the Economic cost of the Disruption ? Per hour/per day/per week?❑ Will the lack of financial planning recovery cause the redirection of route/sector

priorities ?❑ Will communities be impacted in an adverse manner economically? Will they ever

recover?

Define Hazards and Risk

Dist 8, I-10Tex Wash EB Bridge Failure 8/19/15

Types of Major Damage

Examples of typical damage to State Highways:

➢ Storms – Landslides, Slipouts, Washouts

➢Wildfires – Trees, Slope Stability, Drainage➢ Earthquakes – Bridge, Pavement, Settlement➢ Bridge hits

Cost of Network Disruption

The Economic Costs of Freight Transportation

Government, control, or authority

Stafford Act Support to States

Planning Tools

Planning Tools and Documents

❑ COOP/COG

❑ Pandemic Plans

❑ Emergency Operations Plans

❑ Winter Operations Plans

❑ Exercises

Alder Crk Slide, Dist 5

Caltrans Disaster Recovery Financing

District Director’s OrderEmergency Contracting Types of Contracts

Field Maintenance is our first responders

Maintenance crews usually arrive first, and begins repair if possible and maintains traffic control.

If repairs are beyond maintenance capacity, a contract is required.

How Caltrans is prepared

We recover in two phases:

1st Emergency Opening (EO) Fix it Fast!

2nd Permanent Restoration (PR) if needed

Emergency Opening Phase

➢ Reopen facilities to essential traffic, minimize or protect from further damage

➢ Complete work within 180 days of incident

How we fix it fast..

➢ The Director’s Order (DO)

▪ We can award an emergency contract within hours..

Dist 1 HUM 101 Slide 2010

What Is A Director’s Order?

What Is A Director’s Order?

Director’s Order is a formal document granting authority to excuse the contract from normal project delivery procedures.

There are two parts to a DO:

1. Funding Allocation (CTC Resolution G-11)

2. Legal Authority to bypass the State Contract Act

Funding Allocation –California Transportation Commission Resolution G-11

Legal Authority

PCC 10122

DO Verbal Approval

Dist 7, LA-110 Apartment Fire

Director’s Order’s do not waive:

• Environmental Approvals• Permits• Right of Way

The Director’s Order is a …

• Time and Materials contract

• No plans. Work is as ‘Directed by the Engineer’ (Resident Engineer - RE)

• Select a qualified and available contractor, no competitive bidding

•Caltrans maintains an Emergency Contractor Registry to let Caltrans know you are

interested in emergency work

Example Director’s Order Document

Permanent Restoration

Getting things back to normal

Permanent Restoration Phase

➢ Same as a normal programmed project delivery ➢ Intent is to restore facilities to their pre-damage condition (in-kind)➢ Betterments or upgrades to current ‘standards’ are generally allowed

Funding Types & Federal Assistance

➢ State-only Funds

➢ Federal Highways Emergency Relief (ER)

➢ FEMA Public Assistance

• Significant, extraordinary damage in one or more counties

• Caltrans makes request through Cal OES based on extraordinary Damage Assessment

• enables FHWA ER program (threshold is $700,000 min.)

! We need to be responsive – decisions need to be made to accelerate response and recovery

Presidential Major Disaster

Massive damage > $52 million

(uninsured loss)

➢ FHWA activates ER program

❖ Damage within R/W eligible

➢ FEMA Public Assistance

❖ Debris removal (MAP-21)

❖ Damage outside R/W eligible

Northridge Earthquake, 1994

Caltrans reserves $250 million for 2016-17for Emergency and Permanent Restoration

Emergency contract expenditures(millions of dollars)

Summary Emergency Contracts last two years

Permanent Restorationcontract expenditures

(millions of dollars)

Economic Studies

Caltrans is working with the U.S. Department of Homeland Security on a Regional Resiliency Assessment Program (RRAP) Project

RRAP focuses on goods movement through high hazard areas from the Port of Long Beach through the

Cajon Pass (I-15) to the State of Nevada - 390 kilometers

Conclusion

Why is Disaster Economic PlanningFor Transportation Infrastructure recovery important?

❑ Effective and efficient Transportation Systems helps drive a nation’s economy

❑ Reduces the Economic Impacts of the Disaster due to disruptions

❑ Pre-Event economic planning helps to accelerate the response and recovery of the Transportation System

❑ Opportunity to build back better, with funding and resources pre-identified

❑ Adds to the overall Resiliency of the transportation System

QUESTIONS?