Kévin Pepitone 1CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF Drive Beam...

Post on 29-Jan-2016

215 views 0 download

Tags:

Transcript of Kévin Pepitone 1CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF Drive Beam...

1

Kévin Pepitone

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

Drive Beam Injector Gun

2

Drive Beam Injector Gun

Kévin Pepitone

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

Low Energy Electron sourcefrom Thermionic Cathode

at High Intensity

Low Energy Electron sourcefrom Thermionic Cathode

at High Intensity

LEETCHI

3

Status of LEETCHI for CLIC

Kévin Pepitone

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

4

Outline

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

• Introduction and electron beam parameters

• Integration: experimental area, HV deck and control room

• Components: HV components and PLC system

• Diagnostics: electrical and optical diagnostics

• Simulations

• Perspectives

• Conclusions

5

Introduction

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

Conceptual design report (EDMS 1234244)

LEETCHI

Parameters Baseline

Beam energy 140 keV

Beam current 5 to 7 A

Pulse length 140 µs

Emittance (RMS) < 20 mm mrad

Repetition rate 50 Hz

Beam power 4,9 to 6,9 kW

Shot to shot charge variation 0.1 %

Flat top charge variation 0.1 % after correction

6

Electron beam parameters

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

Parameters Baseline

Beam energy 140 keV

Beam current 5 to 7 A

Pulse length 140 µs

Emittance (RMS) < 20 mm mrad

Repetition rate 50 Hz

Beam power 4,9 to 6,9 kW

Shot to shot charge variation 0.1 %

Flat top charge variation 0.1 % after correction

From a thermionic cathode

7

Integration

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

162/R-002

6330

2750

CLINFTLA0100

High voltage

Relay Ross150 kV

Insulating transformer to produce 220 Vac

8

Integration – Experimental area

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

HV deck connected to the -140 kV

High voltage DC power supply-200 kV/10 mA

Capacitor10 nF / 150 kV

9

Integration – HV deck

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

Pulser power supply-1000 V at repetition rates up to 1 kHz

Bias power supply300 V / 450 mA

Heater power supply15 V / 10 A

PLC

10

Cathode and connector

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

Ground

+

- 140 kV

Anode

Cathode

Electron beam

Grid

HV pulser-1000 V

Heater PS15 V, 10 A

Bias PS+300 V, 0.45 A

220 VInsulating transformer

220 V

++

+

Cont

rol i

nter

face

PL

COptical fibre

PLC in the control room

HV deck

CathodeCPI YU156

11

Cathode and connector

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

+220 VInsulating transformer

-140 kV

Heater +

Pulser +

Pulser -

Heater -Bias -

Bias +

Vadim Soldatov

12

Integration – Control room

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

Danish Ali Nawaz

PLC

Media converterVacuum gauges

PLC touch screen

HVPS remote

Ion pumps PS

Solenoids PS

Contactors

Delay generator

13

Dump and Diagnostics

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

3D drawing (CATIA)

Graphite dump (diameter at the beginning : 40 mm, total

length : 390 mm)Copper holder with

water-cooling channels

Water

Alex Vamvakas

Energy deposition calculated with Geant4 for 140 keV, 5A, 140 µs electron beam

3D thermal analysis (ANSYS)

Energy deposition

0 20 40 60 80 100 120 140 1600

200

400

600

800

1000

Ede

p (

J/g)

r (µm)0 50 100 150 200 250 300 350 400

0.0

0.2

0.4

0.6

0.8

Ede

p (

J)

z (mm)

Integrated energy deposition as a function

of length

Cedric Delory

Northstar VD-150230 kV, 20 MHz

BergozACCT-S-C8

OTR with silicon carbide target 50 mm diameter

14

Simulations

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

Current dependence of the emittance for the 8

mm cathode (EGUN)

MAGIC simulation example of the electron gun

Focusing coilBucking coil

Cathode r = 8 mm

r-z at 10 ns

Electrical field simulations in the cathode region to check

possible breakdown locations (Flux2D).

Maximum surface field 14 kV/cm

Jacques Gardelle, CEABruno Cassany, CEARomain Pecquois, CEASteffen Doebert

15

Perspectives

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

Parameters Baseline

Beam energy 140 keV

Beam current 5 to 7 A

Pulse length 140 µs

Emittance (RMS) < 20 mm mrad

Repetition rate 50 Hz

Beam power 4,9 to 6,9 kW

Shot to shot charge variation 0.1 %

Flat top charge variation 0.1 % after correction

40 kV prototype of the modulatorDuring HV tests

Modular 7.5 kV board

-150µ -100µ -50µ 0 50µ 100µ 150µ 200µ 250µ 300µ 350µ

-40k

-30k

-20k

-10k

0

Tens

ion

(V)

Temps (s)

Voltage waveform on 4.5 kΩ resistive load

Ve

ETAGE N

ETAGE 2

ETAGE 1

S1

Sr1

Sn

Srn

S2

Sr2

Dch

Dch

Dch

Dch

Dch

Dch

Dbp

Dbp

Dbp

C

C

C

Vs

Ve

ETAGE N

ETAGE 2

ETAGE 1

S1

Sr1

Sn

Srn

S2

Sr2

Dch

Dch

Dch

Dch

Dch

Dch

Dbp

Dbp

Dbp

C

C

C

Vs

Ve

ETAGE N

ETAGE 2

ETAGE 1

S1

Sr1

Sn

Srn

S2

Sr2

Dch

Dch

Dch

Dch

Dch

Dch

Dbp

Dbp

Dbp

C

C

C

Vs

Schematic of the modulator during Charging and Discharging

Bruno Cassany, CEABaptiste Cadilhon, CEARomain Pecquois, CEA

16

Conclusions

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF

• Integration and installation of the gun in the area are completed• Vacuum is good• New components are expected:

Optical diagnosticDumpConnector

• The first tests with short pulses beams will be performed in 2016• The tests with long pulses at 50 Hz should be performed in 2016

17

Thank you for your attention

CLIC project meeting, CERN, December 1st, 2015 Kevin PEPITONE, BE-RF