Kane County (of Illinois) Arterial Operations Center AND atms · kane county (of illinois) arterial...

Post on 19-Mar-2020

0 views 0 download

Transcript of Kane County (of Illinois) Arterial Operations Center AND atms · kane county (of illinois) arterial...

KANE COUNTY (OF ILLINOIS) ARTERIAL OPERATIONS CENTER AND ATMS PRESENTED BY: STEPHEN ZULKOWSKI , TRAFFIC OPERATIONS ENGINEER OF KANE COUNTY

2018 ITS MIDWEST ANNUAL MEETING, SEPTEMBER 13-14TH

ABOUT KANE COUNTY (OF ILLINOIS)

• Roughly 30 miles west of Chicago

• Population of over 500,000

• Employment over 275,000

• Kane County DOT employs 66 Full Time Employees

• KDOT oversees over 311 centerline miles of highways and bridges

• KDOT maintains over 120 traffic signals

• FY2018-2020 Transportation Improvement Program (TIP) estimated to be over 350 Million Dollars over 5 years

City of Chicago

THE PROJECT ARTERIAL OPERATIONS CENTER (AOC) ADVANCED TRAFFIC MANAGEMENT SYSTEM

• BUILDING ADDITION • BUILDING ADDITION FURNITURE • AOC PC DISPLAYS AND TVS

• AOC VIDEOWALL MANAGEMENT SYSTEM

• AOC CONTROL ROOM CONSOLE • TRANSSUITE INTEGRATION • SIGNAL CONTROLLER FIRMWARE

UPDATES

Total Cumulative Cost: ~$ 2,500,000*

Completed 2018

*Fiber Optic / Interconnect Not Included Local funds only

THE PROJECT ARTERIAL OPERATIONS CENTER (AOC) ADVANCED TRAFFIC MANAGEMENT SYSTEM

• 2,500 SQ FEET (PER FLOOR) • 4 NEW OFFICES • 1 NEW CONFERENCE ROOM • ELEVATOR (ADA) ACCESS • 1 NEW CONTROL ROOM • BACKUP GENERATOR • CONSTRUCTION COST:

• 1.7 Million dollars • COMPLETED IN 2016

• BUILDING ADDITION • BUILDING ADDITION FURNITURE • AOC PC DISPLAYS AND TVS

• AOC VIDEOWALL MANAGEMENT SYSTEM

• AOC CONTROL ROOM CONSOLE • TRANSSUITE INTEGRATION • SIGNAL CONTROLLER FIRMWARE

UPDATES

THE PROJECT ARTERIAL OPERATIONS CENTER (AOC) ADVANCED TRAFFIC MANAGEMENT SYSTEM

• BUILDING ADDITION • BUILDING ADDITION FURNITURE • AOC PC DISPLAYS AND TVS

• AOC VIDEOWALL MANAGEMENT SYSTEM

• AOC CONTROL ROOM CONSOLE • TRANSSUITE INTEGRATION • SIGNAL CONTROLLER FIRMWARE

UPDATES

• FURNISHED 5 OFFICES (7 WORK STATIONS)

• FURNISHED 2 CONFERENCE ROOMS

• FURNISHED WAITING AREA • NEEDED SOMEWHERE TO

SIT • CONSTRUCTION COST:

• $43,000 • COMPLETED IN 2016

THE PROJECT ARTERIAL OPERATIONS CENTER (AOC) ADVANCED TRAFFIC MANAGEMENT SYSTEM

• AOC PC DISPLAYS AND TVS

• AOC VIDEOWALL MANAGEMENT SYSTEM

• AOC CONTROL ROOM CONSOLE • TRANSSUITE INTEGRATION • SIGNAL CONTROLLER FIRMWARE

UPDATES

• RFP SELECTED “CHRISTIE DIGITAL PHOENIX” VIDEOWALL MANAGEMENT SOLUTION

• PROCUREMENT OF 10- 50” TVS

• PROCUREMENT OF 12 PC MONITORS • PROCUREMENT OF 1- 70” CONF.

ROOM TV • DISPLAY NETWORK CAMERA

STREAMS, LIVE CABLE TELEVISION, OR ANY CONTENT DISPLAYED ON LOCAL PC (SCREEN COPY) TO WALL

• CONSTRUCTION COST:

• $108,000 Videowall management $18,000 PC and TV displays, & PC Towers

• SUBSTANTIALLY COMPLETED IN 2016 • CLOSED OUT IN 2018

THE PROJECT ARTERIAL OPERATIONS CENTER (AOC) ADVANCED TRAFFIC MANAGEMENT SYSTEM

• AOC CONTROL ROOM CONSOLE • TRANSSUITE INTEGRATION • SIGNAL CONTROLLER FIRMWARE

UPDATES

• 3 WORK STATIONS, 2 ON TRAFFIC NETWORK, 1 ON COUNTY NETWORK

• 2 CPU CARTS WITH INTEGRATED COUNTER TOP.

• WORK STATIONS ELECTRONICALLY ADJUSTABLE HEIGHTS (SIT TO STAND)

• NEEDED SOMEWHERE TO SIT (OR STAND)

• DESIRED AN IMPROVED AESTHETIC TO THE CONTROL ROOM WORK STATIONS.

• CONSTRUCTION COST:

• $21,000 Control Room Desk

• COMPLETED IN 2016

THE PROJECT ARTERIAL OPERATIONS CENTER (AOC) ADVANCED TRAFFIC MANAGEMENT SYSTEM

• TRANSSUITE INTEGRATION • SIGNAL CONTROLLER FIRMWARE

UPDATES

• 113 EXISTING SIEMENS CONTROLLERS UPGRADED FROM SEPAC TO NTCIP (4.08) FIRMWARE

• TRANSSUITE INSTALLED AND CONFIGURED (MORE DETAIL NEXT SLIDE)

• CONSTRUCTION COST:

• $400,000 TransSuite ATMS and Integration

• $75,000 Additional TransSuite Modules

• $113,000 Firmware Updates and database conversion

• SUBSTANTIALLY COMPLETED IN 2016 • CLOSED OUT IN 2018

KEY BENEFITS FROM TRANSSUITE ATMS • FULL FEATURED:

• Signal Controller management

• (Real Time) Time-Space Diagrams, Databases, Split loggers, active status

• Video Control (view and manipulation)

• Dynamic Message Sign (DMS) Interface (view and manipulate)

• Automated, Trigger/sensor based input, programmable DMS sign message outputs. Such as Travel times or weather data.

• Automatic logging of all alarms & events

• Configurable auto-email notification by event code, such as for “Signal in Flash” to Maintenance personnel/ contractors.

• Automatic logging and user prompted reporting of system detectors (V+O, Speed, Classification, Travel time, etc.)

• Mapping interface for configured devices

• TRANSSUITE MODULES INSTALLED:

TRANSSUITE – TIME-SPACE

TRANSSUITE – TIME-SPACE (MODIFICATIONS)

TRIGGER BASED INPUT/OUTPUT FOR DMS (FROM RWIS)

• First bullet point here

• Second bullet point here

• Third bullet point here

PROJECT CHALLENGES

• Broadcast storm / data storm (PTZ cameras)

• Transition to Central TOD through TransSuite

• Firmware Conversions were manual

• Daylight Savings Time + Time Zones + Time downloads

• Local TOD vs Central TOD plan selection

• Cooperation between KDOT staff / Traffic Network & Kane I.T. staff / Kane network

KDOT TRAFFIC PERSONNEL

KANE I.T. PERSONNEL

0 1

1 0

0

0 1

1

1 1

0 0

0 0

0

PROJECT CHALLENGES

Pre-Existing Layer 2 Only

Interim Layer 2 split – 2 way

Post-Proj. Layer 2 split – 3 ways Layer 3 switch – in field

• Inadequate Network Design producing Broadcast Storms / Data Storms

PROJECT CHALLENGES • Inadequate Network Design producing Broadcast Storms / Data Storms

• VLAN & IP addresses improved

PROJECT CHALLENGES • Inadequate Network Design producing Broadcast Storms / Data Storms

• VLAN & IP addresses improved

PROJECT CHALLENGES • Cooperation between KDOT staff/Traffic Network and Kane I.T. staff/Kane

network

• ATMS installed on virtual servers within Kane’s I.T. network, separate from Traffic Network. Network Port Routing through firewall.

• Recommended Hardware specs (for ATMS) vs Declining Performance based merit for upgraded hardware.

• Learning (Surviving) the language

barrier associated with networking and routing.

• Lack direct VPN to traffic network (although a plus for security). Remote access provided exclusively through Remote Desktop Connections to ATMS servers.

WHERE WE GO FROM HERE?

• Expanding the Network, Adding redundant communication links, sharing system data with more agencies.

• Continue to leverage / learn TransSuite ATMS.

• Implement first Kane County Adaptive Signal Control System

• (Potential) future TSP / BRT functionality

• Higher functioning PTZ camera and Detection product features

• Some Closing Thoughts…..

EXPRESSING SPECIAL THANKS AND APPRECIATION

• Thomas Szabo

• Former Kane County Traffic Manager, August 2001-September 2014 (13+ years)

• Now Senior Project Manager at Christopher B. Burke

• Various Consulting Teams, serving as an extension of staff

• Various Public agencies, supporting County inquiries (ongoing)

THANK YOU Stephen Zulkowski Kane County Traffic Operations Engineer Phone: 630-208-3139 Email: Zulkowskistephen@co.kane.il.us

QUESTIONS?