2Texas Nodal Program UpdateJuly 21, 2008 2
Agenda: Market Readiness Metrics Update
• Status Update
• ERCOT Staff Readiness
• Market Participant Readiness
– Cycle 4 Survey Update
• EDS Readiness
• Appendix: Metrics Update 7.16.2008 (see separate file)
• Metrics Review: For Vote (see separate file)
3Texas Nodal Program UpdateJuly 21, 2008 3
Status Update
All status levels for overall readiness remain the same
4Texas Nodal Program UpdateJuly 21, 2008 4
ERCOT Readiness
• Engagement (green)• new survey results came out at the end of
June - ERCOT remains fully engaged
• Training (amber)• training efforts are on-going
• Process (green)• all departments are meeting target
performance levels
• Staffing (amber)• ERCOT is currently ~95% staffed
(98% required for green status)• recruitment is on-going
• Testing (green)• no recent developments
ERCOT Staff Readiness status is AMBER
5Texas Nodal Program UpdateJuly 21, 2008 5
Market Participant Readiness
Market Participant Readiness status is AMBER
• Engagement (amber)• limited survey response from QSEs and LSEs
drives amber status
• Connectivity (green)• several new entrants to the market have been
successfully tested
• Registration and Qualification (amber)• MP10 (resource mapping) has, again,
improved steadily since the last meeting• MP11 (RARF data) – same 5 RARFs have not
been received (RARFs representing more than 99.5% of MWs have been submitted) – not including new entrants to the market
• Telemetry (green)• no change
• Training (amber)• limited survey response from QSEs drives
amber status
• Trials Participation (green)• consistently solid performance for MP15
(EDS 3 trials participation)
6Texas Nodal Program UpdateJuly 21, 2008 6
Cycle 4 Survey Update
• There were varying degrees of response to the Cycle 4 Survey
– QSEs with Resources and TDSPs had 100% response to the Cycle 4 Survey
– 84% of QSEs have responded to the survey (up from 72% initially)
– 73% of LSEs have responded to the survey (up from 67% initially)
• This limited response is driving several metrics to red
– QSEs without Resources are red for MP1, MP12, and MP13
– LSEs are red for MP19
• ERCOT Account Managers will continue their outreach efforts to MPs who were non-responsive to the Cycle 4 Survey or who reported negative answers
• The survey will remain open through August 15th
• Updates to the Cycle 4 Survey can be submitted using the excel form found on the metrics website (same process as previous surveys)
Cycle 4 Survey Data was reported on the scorecards on June 12th
7Texas Nodal Program UpdateJuly 21, 2008 7
Status Update: EDS
• EDS 1 (green) no changes
• EDS 2 (red) state estimator convergence values for the past week were all above 75% 9 reports and 1 extract were published for June
E3 (Validate Telemetry/SE EDW/MIS Access & Data Accuracy)
• EDS 3 (amber) Maintained amber status
• EDS 4 (red) waiting on EMS 5 delivery to proceed with EMO3 (Verify Outage Evaluation System Functionality)
scheduled to leave FAT on July 18th site fail-over test was conducted and passed on 7/15 – N2.2 is now GREEN
EDS status remains unchanged since the last meeting