INVESTOR PROGRESS UPDATE JANUARY 2021

Post on 02-Feb-2022

4 views 0 download

Transcript of INVESTOR PROGRESS UPDATE JANUARY 2021

INVESTOR PROGRESS UPDATE

JANUARY 2021

MILESTONESOF THE MONTH

01

02

Awali Estate Complete

Construction of 1255-Palm Ridge ongoing

03

04

Vipingo development Sea water Desalination Plant InstallationComplete.

Testing Ongoing

Construction ofVipingo LeisureCentre ongoing

YOUR FAMILYHOME AWAITS

AWALI ESTATECompleted Project

No of units

Construction duration

Construction duration to date

Progress status

Show Houses

74

Complete

Complete

Complete

Complete

AWALI ESTATE PROJECT PROGRESS FACT SHEET

AMENITIES AND UTILITIES PROGRESS

INFRASTRUCTURERoads

Permanent power connection

Gate house

ICT

Complete

Complete

Complete

Complete

Complete

Complete

Complete

Complete

Children’s play area

Perimeter fence

CCTV

Complete

Complete

Complete

Complete

Complete

Complete

COMPONENT STATUS TARGET COMPLETION DATE

LANDSCAPING

Grassing

Trees and Flowers

Complete

Complete

Complete

Complete

PROJECTFACT SHEET

No of units

Construction duration

Construction duration to date

Progress status

Show Houses

74

Complete

Complete

Complete

Complete

AWALI ESTATE PROJECT PROGRESS FACT SHEET

AMENITIES AND UTILITIES PROGRESS

INFRASTRUCTURERoads

Permanent power connection

Gate house

ICT

Complete

Complete

Complete

Complete

Complete

Complete

Complete

Complete

Children’s play area

Perimeter fence

CCTV

Complete

Complete

Complete

Complete

Complete

Complete

COMPONENT STATUS TARGET COMPLETION DATE

LANDSCAPING

Grassing

Trees and Flowers

Complete

Complete

Complete

Complete

Move In...

AWALISITE OVERVIEW

1255 PALMRIDGE

PROJECTFACT SHEET

1255-PALM RIDGEPROJECT PROGRESS FACT SHEET

AMENITIES AND UTILITIES PROGRESS

INFRASTRUCTURERoads

Permanent power connection

Gate house

CCTV

Ongoing

Complete

Ongoing

Scheduled

March 2021

Complete

January 2021

March 2021

Swimming pool

Children’s play area

Parks

Perimeter fence

Scheduled

Scheduled

Ongoing

Complete

March 2021

March 2021

March 2021

Complete

COMPONENT STATUS TARGET COMPLETION DATE

LANDSCAPING

Grassing

Trees and Flowers

Ongoing

Ongoing

February 2021

February 2021

No of units

Construction duration

Construction duration to date

Construction duration to completion

Progress status

Show Houses

330 (Phase 1)

90 Weeks

90 Weeks

12 Weeks

Complete

JANUARY ACTIVITIES

Block A1

Block B1

Block C1

Block A2

Block B2

Block C2

Block A3

Block B3

Block C3

Block D1

Block D2

Block D3

Internal Finishes Ongoing

Internal Finishes Ongoing

Internal Finishes Ongoing

Internal Finishes Ongoing

Internal Finishes Ongoing

Internal Finishes Ongoing

Internal Finishes Ongoing

Internal Finishes Ongoing

Internal Finishes Ongoing

Fourth floor walling ongoing

Fourth floor walling ongoing

Fourth floor walling 90% complete

PHASE 1

PHASE 2

CONSTRUCTIONPROGRESS

A1

A3A2

B1

B2 B3

C1 C2

C3

D1 D2

D3

INTERNAL FINISHES ONGOING

INFRASTRUCTURE & AMENITIES

Infrastructure

Landscaping

Landscaping

Parking

Perimeter Fence

Swimming Pool

KINGSWOODPARK

Build your dream home within the serene Vipingo Development’s Kingswood Park. The controlled gated estate offers four unique typologies to choose from.

Your coastal home is now within reach.

KINGSWOOD MIRABELLAExcellent design for 1/4 acre plot

KINGSWOOD MAISONETTE

KINGSWOOD BUNGALOW

KINGSWOOD RIVIERA

Excellent design for 1/8 acre plot

Excellent design for 1/8 acre plot

Excellent design for 1/8 acre plot

PROGRESS STATUSSite roads clearance complete.

PLANT

VIPINGO DEVELOPMENTSEA WATER DESALINATION

Testing of the 3 million litre capacity sea water desalination plant is ongoing following the successful installation of the plant. We look forward to supplying you with clean and reliable water.

UTILITIES

PROGRESS STATUS

VIPINGO INVESTMENTPARK

Vipingo Investment Park offers serviced plots for light to medium industries in a controlled development with unrivalled amenities and infrastructure.

The park which is conveniently located along the Mombasa Malindi highway is:

35KM from Mombasa CBD

45KM from Moi International Airport & the Port of Mombasa

PROGRESS STATUSConstruction of industries is ongoing.

VIPINGOLEISURE CENTRE

Shop and Work in Style

Contact Jane via leasing@vipingoleisurecentre.com

Your shopping experience will never be the same again. Vipingo Leisure Centre mall is set to host a wide variety of brands to meet all your needs. Looking to set up shop within Kenya’s most exquisite mall?

PROGRESS STATUS

VIPINGO DEVELOPMENT LIMITED

1st Floor, Vipingo Ridge Conference CentreP. O. Box 117 – 80119 Vipingo Website: www.vipingodevelopment.com Email: info@vipingodevelopment.com Mobile: +254 740 400 215 Tel: +254 4400 215

WE ARE ON SOCIAL MEDIA

Vipingo Development LTD

@VipingoLTD

Vipingodevelopmentlimited

Vipingo Development