International News US increasing its visible support Operating under financial constraints but...

Post on 14-Jan-2016

214 views 0 download

Tags:

Transcript of International News US increasing its visible support Operating under financial constraints but...

Inte

rnatio

nal N

ew

sUS increasing its visible support

Operating under financial constraints but

slowing down other parts of the MUCOOL programme to provide resources to iMICE.

Sole

noid

& R

efrig

era

ting

Solenoid

Expected mid October - time scale slipped by two months but no panic (yet)

Refrigeration

A problem with the discontinuation of the system which had been the basis of the original plans.

The replacement system is more expensive – however the process of drawing down contingency funds has been exercised.

Expecting to order replacement this week.

RF P

ow

er S

yste

m fro

m

Berkle

yArrived at Daresbury and the renovation is building momentum.

RF C

avity

The RF cavity under construction at Berkeley has been electro-polished and is being prepared for power at the Fermilab MTA

TRD SEPT04 Layout

TOF0 TOF1

Ckov1

IronShield

TOF2Ckov2

Cal

ISISBeam

DiffuserProtonAbsorber

IronShield Tracker

Target

Particle identification PID

Ch

kov1

CKOV1 University of MississippiSummary Frascati meeting

Ray tracing optimization of Mirror and PMT in progress

Test Beam this autumn

Final design by January 06

Aerogel box

Front mirror

Particle entrance window

Particle exit window

Reflecting pyramid

Back mirror

Optical windows, Winston cones, PM’s

+ various small elements (clamping pieces for windows)

8

Ckov2 : University of Louvain

Simulation of ckov2

3 detectors hit ! Some ring imaging clearly visible on the screen display .

28

No scattering

Aim of TOF stations : Milan

• TOF0 experiment trigger

•TOF0/TOF1 PID on incoming muons

•TOF1/TOF2 PID on particle traversing the cooling channel

•Requirements:

oSingle detector resolution ~60 ps

oHigh rate capability

oSustain nearby B fringe fields

The environmentThe beamline design puts harder and

harder requests on TOF stations

• Higher and higher particle rates ( now 2.3-2.8 MHz for TOF0, it was ~1 MHz at beginning)

• Request for thinner and thinner scintillators (to reduce multiple scattering)

• TOF stations in the fringe field of magnets: quadrupoles for TOF0 (B ~ 50-100 gauss), solenoids for TOF1/TOF2 (B~.2 T)

TOF0 support structure

TOF Detector Layout

• TOF X/Y planes with PMTs at both ends:• TOF0 is placed after Q6.

• TOF1 is placed after Q9.• TOF2 downstream

– Transverse sizes:• TOF0,1,2 are all 4848 cm.

– Segmentation:• All stations are 2 planes arranged orthogonal

to each other.• TOF0 has 12 slabs in each plane. NO

OVERLAP (to cope with higher rates)• TOF1,2 have 8 slabs per plane. NO OVERLAP

• TOF0 environment:– Low field: 100-200 g; High rate: 2.5 MHz.

• TOF1,2 environment:– High field: 1-2 Kg; Medium rate 0.5 MHz

Comparison of laser with cosmics calibration data

The two calibration methods provide similar accuracy on the equalization constants

The shifts of equalization constants () measured with the two methods are well correlated (within 100ps)

70ps

laserco

smic

s

Shifts of calibration constants from 2001 to 2002 data taking

M Bonesini – IEEE 2002

TOF : Conclusions

design for TOF stations well understood only some points to be defined connected with

choice of size of TOF1/TOF2 PMTs (1.5” vs 2”) and divider for TOF0 PMTs (booster vs active divider)

define electronics chain (TDC for high incoming rate): probable choice CAEN V1290

define the high-demanding calibration system (mainly laser based)

test a prototype asap at LNF BTF, together with EMCAL

Test B

eam

sUK :

Focus on two test beams

KEK : late September – testing the tracker

ISIS : Early January – testing the production target

Tracker Prototype

• Fourth station completed and new tracker assembled with 4 stations at Imperial.

• New waveguides manufactured in Japan. Optical connector at Station end much easier to use!

• Tracker was made light-tight at Imperial and shipped to Fermilab for cosmic-ray testing.

• Now in Japan being setup for test-beam.

ACC and TOF Performance

VLPC with MICE Cryostat

• We have two D0 VLPC cassettes (1024 channels each).

• MICE cryostat, using Sumitomo cryocoolers has been operating at Fermilab since May.

• Now operating well at KEK.• LED calibration data taken at Fermilab as

well as 3606 cosmic ray triggers.

FNAL Cosmic Ray Setup

High Gain Cassette - More Light

Made with G4MICE

Test B

eam

s : IsisBackgroundIsis beam – 50 Hz rep rate.

Injection every 20ms. Acceleration 10ms. Fast extraction.

MICE target dips into the beam during the last ~2ms by upto 35 millimetres

Must be out by the next injection 10ms later.

Targ

et q

uestio

ns

Satisfy ISIS that we can create a system which

1. Will not compromise the vacuum

2. Whose reliability does not compromise ISIS operation

3. Removes a maximum amount of ISIS beam

Determine whether what muon flux we can produce within these constraints.

Aims of the tests

1. Run a prototype target

2. Characterise the beam

Hall Switches

(Control)

Position Sensor

(Monitor)

Targ

et q

uestio

ns

A target has been created

and put through bench tests

It works with some provisos

continuous oscillation

one shot operation needed for synchronisation with ISIS

not made of vacuum safe materials

Targ

et a

nsw

ers : i

Plans

Necessary improvements

Creation of a version in vacuum safe materials

Improvement of the electronics to allow one shot operation

Desirable improvements

Upgrade the electronics to increase the power and hence the acceleration.

At present the acceleration is not sufficient to get the target in and out in the required time.

Targ

et a

nsw

ers : ii

Desirable improvements

Upgrade the electronics to increase the power and hence the acceleration.

At present the acceleration is not sufficient to get the target in and out in the required time.

January running

50/128 Hz – means that the target does not have to be out in 10ms

Start of insertion can be moved back in time to allow sufficient target insertion.

Timetable:

• Design review end September

• Test mechanical assembly late October.

• Vacuum & reliability tests November.

• Decision on readiness end November.

• Install in ISIS from early January

• ISIS closes 20th January.

• Test run from 23rd January (~100 pulses? Over a few days).

• Remove by 31st January.

Particle flux measurements : Glasgow

• Prepare for system test end 2005 inside ISIS at 10 m, 20

m. – Set-up test station at Glasgow with UNIDAQ and read-out electronics:

in progress, some technical problems with DAQ (talking to Makoto)– Test all PMTs and validate performance– Purchase Bicron BC-404 scintillator + light-guides.– Full system fully tested by November 2005– Purchase polyethylene absorbers– Install equipment in ISIS during December-January (ISIS shutdown)– Set-up triggering electronics and gated scalers for target monitoring

• In parallel, perform more accurate simulations: in progress– Calculate particle momenta coming out of target– Run test-beam set-up at 10 m and 20 m using different absorbers– Determine rate per scintillator slab for different configurations – Write proposal to ISIS: target November 2005

Con

clusio

ns

Work is building momentum.

Progress is happening in all the components

Problems are arising and (thus far) being solved

Advert

• CCLRC/PPARC seeks to position UK strategically w.r.t.:– International Linear Collider

– Neutrino Factory

– Other accelerator-based scientific facilities

• Key component – high-gradient cavities:– Develop manufacturing capability

– Neutrino Factory application:• Proton driver:

– Front-end: ~234 MHz, RFQ, buncher cavities, chopper

– Could be SC linac; SPL (352 MHz), FNAL (1.3 GHz), …

– Synergy with ILC

• Phase rotation, buncher and cooling channel

– Require large aperture low frequency

– Transport: solenoidal channel cavities operate in strong B field

Use warm cavities at low (200 MHz – 300 MHz) frequencies

Collaboration:

• So far:– US: LBNL (some advice/contact from/with JLab)– UK: IC Phys/Mech.Eng., advice and contact from CCLRC, RAL and DL

• Proposal:– Cavity:

• US: LBNL, FNAL (MuCool, MTA), JLab?• UK: IC, CCLRC, HPRF Faraday (E2V, Shakespeare) Cockroft

– Note: Industrial CASE application ICL/HPRF Faraday submitted– Coupling coil:

• GVA

• Timescale:– Submit October/November

Proposal

Design, manufacture and commission 201MHz cavity

Design from Imperial Mech. Eng.

Contact Ken Long