MICROSOFT: PROJECT ALLUVION
PROJECT ALLUVION
Incentives & Infrastructure
Estimated incentives and Infrastructure cost: $87,000,000
We will have a Development Agreement with Microsoft that will also have a minimum assessment agreement requiring a minimum property valuation of $255,000,000 at the end of Phase IV
Project Description
Four phase data center Area: 154 acres Total investment: $1,126,218,000 Total building size: 1,165,364 square
feet Total employment: 84
Potential Infrastructure Improvements
South 8th Street (old Army Post Rd to County Line Rd)
Pine Avenue to new Army Post Road
Potential Infrastructure Improvements Continued
Pine Avenue upgrades (eastern Corporate Limits to South 8th Street)
Maffitt Road/County Line Road connection (South Veterans’ Parkway to County Line Road)
County Line Road connector to MaffittRoad extension
Water & Sewer
Water line distribution/storage upgrades
Sanitary sewer line upgrades
Services
Relocation of MidAmerican power line
Fiber optic conduit/fiber line installation
Public Safety Facility (to be constructed/equipped as part of TIF District at a date to be determined)
Schedule
Review plans (Phase I only) Grading Construction of Phase 1 Open Phase 1 Future Phases