In this talk, we present why Sandvik IT chose to use the Kanban method for continuous improvements, how it was packaged and introduced for more than 60 teams and how it is supported. We finish by looking at the results that Sandvik has gotten so far. During the talk, we present some of the tools that we have developed for managing this implementation at scale: the Kanban Kick-start Field Guide and the Kanban assessment.

Transcript of Implementing kanban at scale at sandvik IT

Implementing Kanban at Scale at Sandvik IT

Lotta OlssonManager, Operational Excellence SupportSandvik IT

Christophe AchouiantzLean/Agile Coach @chrisach

The Story• Why the Kanban Method

at Sandvik IT?Why?

• How did we implement Kanban within 60+ teams?How?

• The results so farImpact!

• Our new challengesNext

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

Click icon to add picture

Click icon to add pictureClick icon to add picture

www.sandvik.com

4

World leading products, high-technology and innovative

solutions

What dowe do?

We manufacture advanced special alloys and ceramic

materials, industrial tools and mining equipment. We work in

close cooperation with our customers and we invest heavily

in research and development.

What are we?We are a world-leading

high-technologyengineering group.

Who are we?Our corporate culture is

characterized by our thrive to bring the best and most

innovative solutions to our customers.

Findings from > 25 Dev teams

Why Kanban at Sandvik IT

Same top challenges

Root cause No Flow control

See and manage

the flow of work

Strong focus

on improve

Evolution over

Revolution

The Kanban Method Fits our Context and Goals

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

How to make Kanban implement itself?

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

Engineering the Kanban Implementation

Pull-based• No Push!

Awareness• Get early

adopters

1 Day • Teams are

too busy

Minimal Coaching• Have few

coaches

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

PrepareGather info &

Set expectations

KickCreate Kanban

system based on purpose (1 day)

StabilizeUpdate Kanban system to fit the

team

(week-months)

ImproveChallenge the team to work toward target

condition

(forever)

The ”Kanban Kick-start” Concept

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

Flow Manager

Improvement & coaching Kata

Change footer at: View > Slide Master. Select the first slide master and go to Insert > Header & Footer to change the text. Apply to all.

10

Tavlor!

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

Sharepoint TeamPhoto: Christophe Achouiantz

Change footer at: View > Slide Master. Select the first slide master and go to Insert > Header & Footer to change the text. Apply to all.

11

Tavlor!

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

BI TeamPhoto: Christophe Achouiantz

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

Support TeamPhoto: Christophe Achouiantz

Change footer at: View > Slide Master. Select the first slide master and go to Insert > Header & Footer to change the text. Apply to all.

13

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

Industrial IT TeamPhoto: Christophe Achouiantz

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

HR TeamPhoto: Christophe Achouiantz

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

Mainframe TeamPhoto: Marie S. Nilsson

The Kanban Kick-start Field Guide

Get it at: http://leanagileprojects.blogspot.se/

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

Managing Many TeamsPhoto: Christophe Achouiantz

Kanban Assessment

More info at: http://leanagileprojects.blogspot.se/

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

Source: “The effects of Kanban in software development teams - A study of the implementation at Sandvik” R.Ericsson & A.Granlöf 2011

Result so far<2 m 3-5 m 6 m

Better prio of work X X X

Less task switching X X X

Better team collaboration X X X

Less stress X X X

Better collaboration with customers X X

Customer more involved X

More focus on quality X

Shorter lead times X

Impact of Better Collaboration

Deliver the Right Thing

Better Cohesion

Better

Collaboration

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

Photo: Christophe Achouiantz

Other Notable Impacts

Better Team Survivability

Better Team

Building

Kanban

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

Other Notable Impacts

Install a habit of

transparency and

improvements in the org.

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

• Build on the foundation we have

• Improve

• Next step – scale up

What happens now?

Lotta Olsson & Christophe Achouiantz (@chrisach) – Lean Kanban Nordic 2014

Kanban Kick-start Field Guide & Kanban Assessmenthttp://leanagileprojects.blogspot.se/

Get more info about the Sandvik Journey on InfoQ:http://www.infoq.com/articles/kanban-Sandvik-IT-1http://www.infoq.com/articles/kanban-Sandvik-IT-2