Where we are
Disk 9 is finished and dispatched to Liverpool (April 04) Disk 8 is finished and dispatched to Liverpool (Aug 04) Disk 7 is almost finished, and will be dispatched this month Disk 6 and 5 are in progress,
» Disk 6 is 60% complete
» Disk 5 is 10% complete Disk 4 is due to begin this week. As of this week we have 3 full time technicians building disks.
NIKHEF has all services for disk 9A and 8A. They have started both. NIKHEF is soon to receive services for 7A
CCLRC 3I Wilmut
CCLRC 4I Wilmut
CCLRC 5I Wilmut
Cooling circuit production
We go through lows and highs with circuit production! Circuit production rate is sufficient…. Just. Problems encountered and resolved include:-
» Incorrect pipes delivered» Huge difficulty bending pipe from UTI (new pipe due soon)» Block supply complicated and intermittent.» Block reaming proved very problematic» Various cleaning problems.
Presently we have 3 contactors, 1 DL lab tech, making circuits and circuit components. We also have money for 1 more contractor if we start to fall behind schedule.
CCLRC 6I Wilmut
Grounding and Shielding
Everything on disk is grounded accept opto harness wrap, these will be grounded once opto harnesses have passed testing.
Pipe to foil joints will be finally made after precise placement. This is proved to work on top of pipe sleeves.
Grounding finger makes disk assembly more difficult, but not impossible.
Patch panels grounded with foil fingers. Disk grounded to support cylinder via foil
tabs. Foil plating varies in quality, Foils are
only used if they can be easily tinned.
CCLRC 7I Wilmut
Tapes and Opto
Oxford and Glasgow are ahead in tape supply. Recent problem with w2 tapes, looks like it has been
solved NIKHEF is having problems with tape failiures (new
cover layer) this is yet to be resolved. Opto harness supply looks very good. RAL has
harness ready down to disk 3C. Tapes for spare disks ordered No real worries with tapes any more.
CCLRC 8I Wilmut
Bottom line
We are quite close to meeting the sheadule laid down by SH in May this year.
The final stages of disk assembly take longer than the schedules suggest.
Very few new problems are presenting them selves.
CCLRC 9I Wilmut