I N T R O D U C T I O N SM A S O N D I S T R I C T

SSPA Task Force Meeting March 5, 2020

I N T R O D U C T I O N S

Meeting Purpose

1 Offer an overview of the Fairfax County Site Specific Plan Amendment Process.

What is it, and how does this work?

Meeting Purpose

22 Kickoff the Mason District SSPA Task Force and discuss their role within the process

Meeting Purpose

33 Offer an introduction to Comprehensive Planning in Fairfax County

Meeting Purpose

44 Provide a summary of the nominations or ideas submitted for consideration

2020 SITE SPECIFIC PLAN AMENDMENT PROCESS

What is the Comprehensive Plan? a guide for decision-making in the county about the built and natural environment

Site-Specific Plan Amendments (2 yr. Cycle)

Comprehensive Plan Amendment Work Program

Countywide/Policy Plan Amendments

Areawide Planning Studies

Site-Specific Plan Amendments (2 yr. Cycle)

Additional Board-authorized Amendments

Comprehensive Plan Amendment Work Program

The South County SSPA Guidebook is published on the SSPA Website and contains detailed

information about the process.

~ www.fairfaxcounty.gov/planning-development/plan-amendments/sspa

10

The Screening Process

The Screening Process Nomination screening is a phase in the SSPA process where the task force will consider whether nominations or proposals should be considered further by staff and undergo a period of additional analysis.

The Question Which nominations should be added to the county’s

2020 Plan Amendment Work Program?

The Screening Criteria Is the idea being proposed contrary to County policies?

Is any additional analysis necessary?

BEGIN IMPACT ANALYSIS NOMINATION PERIOD

& DETAILED REVIEW September – December 2019 August 2020

South County SSPA Timetable

SCREENING PERIOD January – July 2020

ONGOING

15

COMPLETED PENDING

NOMINATION PERIOD Septe

ANALYSIS

mber – December 2019

BEGIN IMPACT

& DETAILED REVIEWAugust 2020

COMPLETED PENDING

16

South County SSPA Timetable

SCREENING PERIOD January – July 2020

January 2020: Supervisors select Task Forces

March - April 2020: Task Force review of nominations for screening

Friday before each Task Force Meeting (2nd and subsequent meetings):

Staff provides a summary report with preliminary staff’s recommendation distribution

May 8, 2020: Final Staff Reports published prior to public hearings

UPDATED June 17 and 18, 2020: Planning Commission public hearings

July 28, 2020: Board of Supervisors adoption of new Comprehensive Plan Work Program

NOMINATION PERIOD Septe

ANALYSIS

mber – December 2019

BEGIN IMPACT

& DETAILED REVIEWAugust 2020

COMPLETED PENDING

17

South County SSPA Timetable

SCREENING PERIOD January – July 2020

1st Meeting

- Planning staff provides a brief overview of the SSPA process.

- Task Force adopts discussion and voting procedures, appoints

vice chair and secretary, and discusses meeting schedule.

- Planning staff provides Introduction to Comprehensive

Planning presentation

- Planning Staff provides overview of nominations.

NOMINATION PERIOD Septe

ANALYSIS

mber – December 2019

BEGIN IMPACT

& DETAILED REVIEWAugust 2020

COMPLETED PENDING

18

South County SSPA Timetable

SCREENING PERIOD January – July 2020

2nd and 3rd Meetings

- Staff provides brief overviews of each nominations and provides Preliminary

Staff Reports to the Task Force.

- Nominators may present their nominations and justification to the Task Force.

- Task Force discusses whether to recommend the nominations for the Plan

Amendment Work Program.

- Task Force votes on all nominations

- Secretary records the votes and recommendation.

NOMINATION PERIOD Septe

ANALYSIS

mber – December 2019

BEGIN IMPACT

& DETAILED REVIEWAugust 2020

COMPLETED PENDING

19

SCREENING PERIOD January – July 2020

UPDATED June 17 and 18, 2020: Planning Commission public hearings

June 24, 2020 Planning Commission mark-up

July 28, 2020: Board of Supervisors adoption of new

Comprehensive Plan Work Program

South County SSPA Timetable

Sample Task Force Vote / Recommendation

The task force will offer their recommendation by voting whether each nomination should be

added to the County’s Work Program.

20

What happens after the task force vote?

S U B M I S S I O N S S C R E E N I N G A N A L Y S I S

PLANNING PROCESS

S C R E E N I N G W O R K P R O G R A M R E Z O N I N G P R O C E S S

(Timeframe can vary)

TASK FORCE

CONCLUDES

PUBLIC PUBLIC PUBLIC HEARINGS HEARINGS HEARINGS (for each nomination)

Inclusion on the county’s Plan Amendment work program will lead to additional analysis but does not guarantee a recommendation of approval.

Task Force Administrative Items

Introduction to the Comprehensive Plan

The Comprehensive Plan • A GUIDE for decision-making about the County’s land use

• Statutory mandate: required by the Code of Virginia to shape the orderly development of the county

25

Fairfax County Comprehensive Plan

Policy Plan Volume Four Area Plan Volumes Comprehensive Plan Maps

(County-wide Policies)

Policy Plan

Functional Elements

• Land Use

• Transportation

• Housing

• Environment

• Economic

Development

• Heritage Resources

• Public Facilities

• Human Services

• Parks and Recreation

• Revitalization

• Visual & Performing Arts • Chesapeake Bay

Supplement

Concept For Future Development

Area Plan Geographies

Community Planning Districts

Community Planning Sectors

How is the amount of development measured?

Density, Intensity, and F.A.R.

Terms used to talk about “how much” development.

Residential Dwelling units pe

3-4 du/ac (single family detached)

Residential Dwelling units pe

se Densityr acre (du/ac)

se Density r acre (du/ac)

5-8 du/ac (townhouses)

U

16-20 du/ac (garden apartments) 30-40 du/ac (mid-rise apartments)

U

Intensity = Floor Area Ratio (FAR)

EXAMPLE:

FLOOR AREA (sq. ft.) 100,000 sq. ft. of building = 1.0 FAR

100,000 sq. ft. of land LAND AREA (sq. ft.)

Intensity in Different Forms

Planning & Zoning

Comprehensive Plan Zoning Ordinance

▪Body of Regulations • Guide – Recommendations

▪Implements the Plan • Supplies general policies

▪Sets requirements for setbacks, • Type of Land uses and

height and open space amount of development

▪Zoning Districts (ex. R-1, C-2, and PDC)

• Proposals to rezone property are evaluated for conformance with the Comprehensive Plan

• Special Exception applications are evaluated for harmony with the Comprehensive Plan

Where can I find a copy of

the Comprehensive Plan?

Department of Planning & Development Website

www.fairfaxcounty.gov/planning-development/fairfax-county-comprehen www.fairfaxcounty.gov/planning-

development/fairfax-county-comprehensive-plan

Additional Resources

• COMPREHENSIVE PLAN

www.fairfaxcounty.gov/dpd/comprehensiveplan/

• LINK TO COMP PLAN GLOSSARY

www.fairfaxcounty.gov/dpd/comprehensiveplan/glossary/planglossary.pdf

• LINK TO COMP PLAN FAQ

www.fairfaxcounty.gov/dpd/comprehensiveplan/planfaq.htm

• LINK TO COUNTY EMAIL SUBSCRIPTIONS

www.fairfaxcounty.gov/email/lists/

(view the land use & development section for selections)

• LINK TO FB LAND USE PAGE

www.facebook.com/fairfaxlanduse/

• EDUCATION & FAQS

www.fairfaxcounty.gov/planning-development/plan-amendments/sspa/faqs

Questions

Overview of Nominations

26 Total Nominations Submitted

6

23*

Accepted For Screening

6 In Mason District

9 Lee District 8 Mount Vernon

Nominations can currently be reviewed via the Fairfax County SSPA website at: https://www.fairfaxcounty.gov/planning-development/plan-amendments/sspa/south/track-nomination

T H A N K Y O U F O R Y O U R T I M E

JENNIFER

GARCIA Jennifer.Garcia@fairfaxcounty.gov

First Christian Church + PC19-MA-001

6420-6443 Arlington Blvd. + PC19-MA-003

ADDITIONAL

RESOURCES SSPA WEBPAGE

www.fairfaxcounty.gov/planning-development/plan-amendments/sspa/south/track-nomination

BRYAN MICHAEL BOTELLO BURTON Bryan.Botello@fairfaxcounty.gov Michael.Burton@fairfaxcounty.gov

+ Public Storage

PC19-MA-004 + 6152 Leesburg Pike (Gibson)

PC19-MA-002

+ 7616 Little River Turnpike

PC19-MA-005 + Dar Al-Hijrah Islamic Center

PC19-MA-006

DEPARTMENT OF PLANNING & DEVELOPMENT WWW.FAIRFAXCOUNTY.GOV/PLANNING-DEVELOPMENT