Post on 19-Jan-2015
description
1
I-74 Bettendorf Local Roads Meeting
November 7, 2012Bettendorf City Hall1609 State StreetBettendorf, Iowa
2
Funding Update
Bettendorf, Iowa
Moline, Illinois
Davenport, Iowa
3
Funding Update
•Projected Funding▫Federal Transportation Bill passed on 7/7/12
4
Funding Update
•Projected Funding▫Iowa DOT 2013 -2017 Program
DRAFT 2013 - 2017 IOWA HIGHWAY PROGRAM
RTE ADT LOCATION MILES TYPE OF WORK 2013 2014 2015 2016 2017
74 20300 53RD ST INTERCHANGE IN DAVENPORT
EROSION CONTROL
250
74 34800 IN BETTENDORF AND DAVENPORT
2.5 RIGHT OF WAY 4208 4715 4201 3734
GRADE AND PAVE
13700
▫Illinois DOT 2013 -2018 Program
▫$73 Million
5
Funding Update
6
Funding Update
7
Funding Update
8
Bettendorf Local Roads – Advance Work
Bettendorf, Iowa
Moline, Illinois
Davenport, Iowa
9
•The letting date is September 16, 2014.
•Potential changes were possible due to the advancement of the local roads.
Bettendorf Local Roads – Advance Work
10
Bettendorf Local Roads – Advance Work
11
•Eliminate the State Street to Gilbert Street Diagonal Connection▫Original design closed State Street for the new I-74
piers
▫New piers not constructed, so State Street can stay open
▫Diagonal connection is no longer needed for staging
▫Land occupied by the connection could become developable
▫State Street will need patching and/or resurfacing
▫Ownership of State Street will transfer to the City
Bettendorf Local Roads – Advance Work
12
Bettendorf Local Roads – Advance Work
13
•Geometry Existing State Street & Proposed US 67 ▫Sharp skew angle was not desirable
▫Eliminate the connection
Access to the area between 11th and 12th Streets would be via new US 67, south on 12th Street and west on State Street - Rejected
▫Modify the connection
State Street one way between 11th and 12th Street
QCA Spas and Adel would have right-in/right-out entrances as they do today.
Bettendorf Local Roads – Advance Work
14
Bettendorf Local Roads – Advance Work
15
Bettendorf Local Roads – Initial
16
Bettendorf Local Roads – Current
17
•WB I-74 Exit Ramp to State Street/US 67
▫To be maintained at all times▫Temporary connection in the interim condition
•Intersection of State Street and 12th Street▫May experience capacity issues in the interim
condition
▫Kimberly and State Street accessing the EB entrance ramp
▫Intersection often experiences delays now
Bettendorf Local Roads – Key Issues
18
Bettendorf Local Roads – Current
19
•Calvert Drive to Remain Open Until I-74 Built▫ If closed, traffic exiting businesses north of
Mississippi Blvd on 14th Street would need to detour north to Central then back on 15th Street to access the downtown
▫Existing traffic on Calvert Drive is light, however a detour may cause confusion for drivers
•Parking
▫Some parking lot spaces will be lost
▫There is the potential to gain some spaces along State Street.
Bettendorf Local Roads – Key Issues
20
Bettendorf Local Roads – Parking
21
Bettendorf Local Roads – Properties
22
•Total Acquistion (Blue Shaded Lots)▫Largely, existing building have been removed
▫Contract to remove six buildings (320, 327, 335, 359, 361, 368)
▫Purchased but not possesed (341, BP Station 402 State St)
•Parcel 365▫412 -16th St should be marked with red cross
hashes. This is a parcel that is possibly a total acquisition
Bettendorf Local Roads – Properties
23
Bettendorf Local Roads – Properties
24
•Properties Acquisition▫ The goal is to acquire all properties by the end of
2013
▫All of the properties will need to be cleared prior to the September 2014 letting
Bettendorf Local Roads – Properties
25
Bettendorf Local Roads – Properties
26
•Potential Excess Property
▫Property outside the red dashed “need line”
▫Proposed ROW lines not finalized until after the local road project is fully designed
▫Not likely dispose of any excess property along the I-74 mainline and ramps until this work is completed
▫Lots needed for mainline construction are all lots between 13th Street and 15th Street
Bettendorf Local Roads – Properties
27
Bettendorf Local Roads – Properties
28
Plan Development Update
Bettendorf, Iowa
Moline, Illinois
Davenport, Iowa
29
Iowa Plans - 100% Unapproved Plans
•Roadway Plans▫Contract A (161) – Completed▫Contract B (205) – Completed▫Contract C (206) – Completed▫Contract D (207) – Completed▫Contract E (226) – Will be Completed in
December•Signing Plans
▫Being prepared by the Iowa DOT•ROW plans and plats (partial takes)
▫Work to begin in March 2013• Iowa Utility Process
▫Utilities to owners in December 2012
30
Iowa Plans - 100% Unapproved Plans
•Bridge Plans▫Iowa Ramps A, B, C and D – Completed▫WB Iowa Viaduct – Completed▫EB Iowa Viaduct – Completed▫WB North Approach – Completed▫WB South Approach – Completed▫EB North Approach – Completed▫EB South Approach – Completed▫100% Arch Substructure Plans – Completed▫100% Arch Superstructure Plans – Completed
•Bridge Demolition Plans ▫Suspension Spans – Completed▫Truss Spans – Completed
31
Illinois Plans•Roadway Plans: 90% Complete Submittal
▫Contract A – Completed▫Contract B – Completed▫Contract C – Completed▫Contract D – Will be Completed in January
•Structure Plans▫Pre-Final Plans Completed by February 15 2012
•ROW plans and plats (partial takes)▫Work began in March 2012
•Illinois Utility Process▫90% Plans sent to utilities/agencies in late August▫Utility owners response due December 31st
Typology E – Landscape Design – Bettendorf, Iowa
32
04/10/2023
Typology E- Typical Landscape Design
33
04/10/2023
I-74 Corridor Landscape
•Assume mow edge along roadway entire mainline at interchange/ramps
•Plans show plant material areas with idea that some earthwork can occur to enhance character and conditions (i.e. aesthetics, slopes & drainage)
•Possibility of Right of Way fence enhancement
•Possibility of selective thinning of existing tree species/understory plant material
34
04/10/2023
35
I-74 Bettendorf Local Roads Meeting
THANK YOU!