US 290 PROGRAM OVERVIEW

Footer Text

Table of Contents

2

6

9

11

14

19

2

25

Mission & Goals

Corridor Overview

Interim Solution

Partnerships/Funding

Managed Lanes

Construction

Questions

1

2

3

4

5

6

7

Footer Text

Mission & Goals

MISSION– Working with others to provide safe and reliable transportation solutions for

Texas

GOALS– Maintain a safe system– Address congestion– Connect Texas communities– Best in class state agency

3

Footer Text

100 Most Congested Roadway Segments in Texas

US 290: I-610 to FM 529 - #18 I-610: I-10 to I-45 - #20 US 290: FM 529 to FM 1960 #32

4

Footer Text

US 290 Program Overview

US 290: I-610 to FM 2920– 35 miles ($2.4 billion)

5

Hempstead: I-610 to SH 99– 24 miles ($2.3 billion)

Record of Decision (ROD) approved 2010

Footer Text

Interim Solution

Funding current concept not feasible Interim partnership solution on US 290 ($1.8 billion)

6

Rehabilitate Hempstead Road (Started August 2013) Environmental Re-evaluation Document Public Comment Period ended September 18th, 2013

Footer Text

Partnership

Key Funding Partners– State and Federal Elected Officials – Approval of state and federal funds– Harris County – Judge, Harris County Commissioners Court, Public Infrastructure

Department, Toll Road Authority– Houston Galveston Area Council – Transportation Policy Council

Other Partners– Federal Highway Administration– Metropolitan Transit Authority of Harris County– City of Houston– City of Jersey Village

Community Partners– Cy-Fair Chamber of Commerce– West Houston Association– Near Northwest Management District– Greater Houston Partnership

7

Footer Text

Funding

Original US 290/Hempstead Tollway Program Cost - $4.7 billion

Interim Phased Plan - $1.8 billion– Harris County - $400 million– Rider 42 funds/Prop 12 - $168 million– Other Prop 12 - $440 million– Prop 14 - $123 million– Other State - $84 million– Federal - $646 million

8

Footer Text

Memorandum of Understanding

TxDOT and Harris County Toll Road Authority – executed April 2012– Partnership to leverage resources and maximize interim congestion relief

Interim US 290 from I-610 to SH 99 (Grand Parkway)– 4-general purpose lanes each direction– Reversible 3 to 2 managed lanes in center– Harris County to operate and maintain managed lanes• Revenue stays in the region

– Rehabilitate Hempstead Road

9

Footer Text

US 290 Managed Lanes

10

Footer Text

Accelerating Construction

7 project construction contracts awarded 5 projects and Hempstead Tollway remaining to let for

construction

11

Estimate/ Bid

$83M $104M$41M $91M $135M $58M $110M $153M $143M $107M (Project J-1)$142M (Project J-2)

$151M (Project K)

Footer Text

Construction

Project K (I-610/US 290 Partial Interchange)– Congestion relief on I-10, I-610, US 290– Construction contract awarded May 26, 2011– $151 million contract; $6.79 million incentives– Estimated completion 2015

Project J-1 (I-610/US 290 Partial Interchange)– Construction contract awarded October 25, 2012– $107 million contract; $5.76 million incentives– Estimated completion 2016

12

Footer Text

Construction

Project G (US 290/Beltway 8 Interchange)– Congestion relief on US 290, Beltway 8, Sam Houston Tollway– Significant safety enhancements– Construction contract awarded September 26, 2012– $110 million contract; $5 million incentives– Estimated completion 2016

13

Footer Text

Transportation System Management (TSM) Projects

14

Outbound US 290 at Barker Cypress

Outbound US 290 at Spring Cypress

Footer Text

Public Information Program