Hurricane Preparations Before and After Sandy · Presentation to the MWRA Wastewater Advisory...

Post on 13-Jul-2020

1 views 0 download

Transcript of Hurricane Preparations Before and After Sandy · Presentation to the MWRA Wastewater Advisory...

Massachusetts Water Resources Authority

Presentation to the

MWRA Wastewater Advisory Committee

Hurricane Preparations Before and After Sandy

January 4, 2013

Michael J. Hornbrook Chief Operating Officer

The Forecast

2

•  MWRA  staff  par-cipated  in  conference  calls  hosted  by  the  Na-onal  Weather  Service  

National Weather Service Briefings

3

•  In  an-cipa-on  of  the  storm,  reservoir  levels  were  lowered  in  order  to  ensure  capacity  

–  Quabbin        stopped  transfer  to  WachuseC    

–  WachuseC        released  700  mg    –  Sudbury    System      released  470  mg    

–  Chestnut  Hill  Reservoir    released  13.7  mg  

Lowered Reservoir Levels

4

Reservoirs During March 2010 Rains

5

Storm Preparations

•  Staff  began  mee-ng  and  making  prepara-ons  early  in  the  week  

–  Generators  tested  

–  Cri-cal  equipment  checked  

–  Chemical  levels  topped  off  

–  Fuel  topped  off  

–  24-­‐hour  staffing  plans  developed  for  EOC,  opera-ons,  maintenance  and  other  essen-al  staff  

•  MWRA  sent  out  weather  advisories  to  its  member  communi-es  throughout  the  storm  beginning  on  Thursday  

Community Notifications

7

•  Updates  were  also  provided  on  MWRA’s  web  page  

Web Updates

8

Web Updates

9

Pre-Positioned Pumps In Critical Locations

•  Portable  pumps  were  pre-­‐posi-oned  –  2  at  Melrose  

–  2  at  IPS  in  Weymouth  for  the  South  Shore  

–  1  at  Somerville  Marginal  

10

Pumping During March 2010 Storms

11

•  Sandbags  were  filled  and  stacked  at  the  Clinton  Treatment  Plant  and  the  Alewife  Pump  Sta-on  

Sandbagging

12

Flooding At The Clinton Treatment Plant March 2010

13

•  Opera-onal  procedures  for  large  storms  reviewed    •  Par-es  no-fied  

•  Tunnel  emp-ed  

South Boston CSO Tunnel

14

Construction Projects Were Shut Down

15

Coordinating With MEMA

•  MWRA  had  a  representa-ve  at  the  MEMA  bunker  in  Framingham  throughout  the  storm  

EOC Activation

•  MWRA’s  emergency  opera-ons  center  (EOC)  in  Chelsea  was  ac-vated  at  7:00am  Monday,  October  29th  un-l  the  storm  had  passed  

17

Deer Island EOC Was Also Opened

18

Monitoring Pumping

19

Monitoring Deer Island Flows

20

Monitoring Rainfall By Location

21

•  EOC  sent  updates  throughout  the  storm  to    a  pre-­‐determined  distribu-on  list  for  “Major  Wet  Weather  Event”  

Hourly Updates Sent To Staff

22

Wastewater System Performance

•  Total  rainfall  measured  at  Chelsea  was  2.23  inches  

•  2  of  3  headworks  reached  capacity  

•  All  CSO  facili-es  ac-vated  

•  No  SSOs  

           Dura-on  

 Peak  Flows  MG  

 Chelsea  Creek:       No       319  Ward  Street:       Yes   2  hr.  5  min.   253  Columbus  Park:       Yes   5  hr.  3  min.   180  

   Volume  

Discharged  Dura-on  of  Ac-va-ons  

            MG      CoCage  Farm         Yes   8.68   2  hr.  24  min.  Prison  Point:       Yes   32.70   11  hr  32  min.  Somerville:       Yes   5.37   7hr.    34  min.  Union  Park:       Yes   3.55   1  hr.  51  min.  

Hourly Flows At Wastewater Facilities

24

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

8.00

9.00

10.00

11.00

12.00

13.00

14.00

15.00

0.00

100.00

200.00

300.00

400.00

500.00

600.00

700.00

800.00

900.00

1000.00

02:00  PM  03:00  PM  04:00  PM  05:00  PM  06:00  PM  07:00  PM  08:00  PM  09:00  PM  10:00  PM  11:00  PM  12:00  AM  01:00  AM   2:00  AM

*  0.63   0.17 0.08 0.04 0.02 0.08 0.26 0.31 0.02 0.01 0.00 0.00 0.00

CSO  FACILITY  FLO

WS  (M

GH)

Avg.  hou

rly  -­‐W

W  FLO

W  (M

GD)

Time  &  Rainfall   (inches)

Storm  Event  October  29-­‐30,  2012

Prison  Point  CSO

Somerville  Marginal  CSO

Union  Park  Detention  Facility

Cottage  Farm  CSO

Ward  St  HD  WK

Columbus  Park  HD  WK

Chelsea  Creek  HD  WK

DEER  ISLAND  TOTAL  Hourly  Flow

–  Ludlow  Monitoring  Sta-on  –  Oakdale  Power  Sta-on  

–  Carroll  Treatment  Plant  

–  Hultman  Shai  4  

–  MetroWest  Shai  L  

–  MetroWest  Shai  E  

–  Norumbega  Covered  Storage  

–  Turkey  Hill  Tank  

–  Oak  Hill  Tank  

–  Spring  Street  Pump  Sta-on  

–  Blue  Hills  Covered  Storage  

–  Loring  Road  

–  Deer  Island  Tank  

–  Chelsea  Facility  

–  Chelsea  Screenhouse  –  Chelsea  Headworks  

–  Columbus  Park  Headworks  

–  Nut  Island  Headworks  

–  Braintree-­‐Weymouth  Pump  Sta-on  

–  Caruso  Pump  Sta-on  

–  Houghs  Neck  Pump  Sta-on  

–  New  Neponset  Pump  Sta-on  

 

Power Outages

25

MWRA experienced power outages at numerous facilities across the service area:

•  At  Deer  Island,  a  sec-on  of  a  gravity  thickener  scum  roof  was  ripped  off  by  the  wind  

Storm Damage

26

Before   A(er  

•  Over  100  trees  and  numerous  limbs  came  down  along  the  aqueducts  in  the  MetroWest  area  

Storm Damage

27

Storm Damage

28

Entrance  to  Southborough  facility  

•  Biggest    poten-al  MWRA  impact  -­‐  wastewater  system  

•  Evalua-ng  various  storm  surge  scenarios  

•  Compare  storm  surges  to  building  eleva-ons/interior  equipment  

 

•  Re-­‐Evalua-ng  current  designs:  

–  Chelsea    Creek  Headworks  –  Alewife  Pump  Sta-on  

   

   

Post Sandy Evaluations

29

30

Water Levels as Recorded by Tidal Gage #8518750, near Manhattan, NY

9’ higher than normal high tide.

11’ above MSL

Impact Evaluations

31

PK scenario

100

Year

Sto

rm

500

Year

Sto

rm

100y

r + 2

.5' o

f SLR

11 ft

abo

ve M

SL

9ft a

bove

hig

h tid

e

100y

r Sto

rm

500y

r Sto

rm

Reference water elevation (*) 115.83 116.63 118.33 117.43 120.33 120.41 121.21

Cottage Farm CSO 112.96 114.00 1.83 2.63 4.33 3.43 6.33 • •Somerville Marginal CSO 115.66 116.00 0.63 2.33 1.43 4.33 • •Commercial Point CSO 121.26 122.50

Fox Point CSO 118.96 120.00 0.33 • •Constitution Beach CSO 117.16 117.50 0.83 2.83 • •Chelsea Creek Headworks 113.16 117.12 1.21 0.31 3.21 • •Chelsea Screen House 113.86 115.00 0.83 1.63 3.33 2.43 5.33 • •Delauri P.S. 118.66 120.00 0.33 • •Alewife Brook P.S. 112.66 114.50 1.33 2.13 3.83 2.93 5.83 • •Caruso P.S. 118.16 120.00 0.33 • •Houghs Neck P.S. 115.36 118.83 1.50 • •Braintree-Weymouth IPS 126.14 127.25

Squantum P.S. 114.66 118.00 0.33 2.33 • •Pelletizing Plant 116.36 119.00 1.33 • •Chelsea Facility 116.30 117.76 0.57 2.57 • •

2100 SLR High Emissions ScenarioCurrent

Gro

und

Elev

atio

n

(LID

AR

-Der

ived

)

Low

est B

uild

ing

Ope

ning

Su

rfac

e El

evat

ion

Sandy with a Boston Landfall

•  Reservoir  Storage/Releases  

•  Turbidity  in  Reservoirs  

•  Equipment  in  manholes  

Drinking Water Infrastructure Impacts

32

•  Selec-on  of  “Storm  Surge”    -­‐  dictates  ability  to  mi-gate        

•  “Survivability”/Level  of  Service    of  cri-cal  facili-es    

•  Priori-za-on  of  facili-es’  modifica-ons  

•  Funding  availability  

Future Key Decisions

33