Presentation to the Town of Haverhill. October 23, 2008

Transcript of Hcms Sdm

Haverhill Cooperative School District Special School District Meeting

October 23, 20086 pm

Dr. John A. Bagonzi Woodsville Community Building

HCMS Roof Project:Armory Photos

October 16, 2008

View from Roof – No Students

View from Roof – Grade 5 Classroom

View from Roof – Grade 6 Classroom

View from Roof – Grade Four Classroom

View from Roof – Grade 4 Classroom

View from Roof – Grade 4 Classroom

View from Roof – Grade 4 Classroom

View from Roof – Grade 5 Classroom

View from Roof – Grade 7 Classroom

View from Roof – Grade 7 Classroom

View from Roof – Grade 7 Classroom

Grade 7 Life Skills Class

Grade 7 Art Class

Art Supply Cart

East Hallway

West Hallway

Indoor Eating Area and South Hallway

Outdoor Eating Area

Staff Room with Band Room Next Door

Staff Room

Band Room

Title 1 Room

Physical Education Class – Under Cover due to Rain

Physical Education Class – Under Cover due to Rain

Only Girls Bathroom – One Toilet and One Sink

Only Girls Bathroom – One Toilet and One Sink

Main Entrance Hallway, Cafeteria POS Computer, Staff Photocopier

Janitor’s Closet and Computer Network Closet

RSA 508: 4-b – Damages from Construction

I Except as otherwise provided in this section, all actions to recover damages for injury to property, injury to the person, wrongful death or economic loss arising out of any deficiency in the creation of an improvement to real property, including without limitation the design, labor, materials, engineering, planning, surveying, construction, observation, supervision or inspection of that improvement, shall be brought within 8 years from the date of substantial completion of the improvement, and not thereafter.

II The term "substantial completion'' means that construction is sufficiently complete

so that an improvement may be utilized by its owner or lawful possessor for the purposes intended. In the case of a phased project with more than one substantial completion date, the 8-year period of limitations for actions involving systems designed to serve the entire project shall not begin until all phases of the project are substantially complete.

III If an improvement to real property is expressly warranted or guaranteed in writing

for a period longer than 8 years, the period of limitation set out in paragraph I shall extend to equal the longer period of warranty or guarantee.

RSA 508: 4-b – Damages from Construction

IV In all actions for negligence in design or construction described in paragraph I, the standard of care used to determine negligence shall be the standard of care applicable to the activity giving rise to the cause of action at the time the activity was performed, rather than a standard applicable to a later time.

V (a) The limitation set out in paragraph I shall not apply to actions involving fraudulent misrepresentations, or to actions involving the fraudulent concealment of material facts upon which a claim might be based. Such actions shall be brought within 8 years after the date on which all relevant facts are, or with due care ought to be, discovered by the person bringing the action.

(b) The 8-year limitation period in paragraph I shall not apply to actions arising out of any deficiency in the design, labor, materials, planning, engineering, surveying, observation, supervision, inspection or construction of improvements which are for nuclear power generation, nuclear waste storage, or the long-term storage of hazardous materials.

VI Nothing in this section shall affect the liabilities of a person having actual possession or control of an improvement to real property as owner or lawful possessor thereof, and nothing contained in this section shall alter or amend the time within which an action in tort may be brought for damages arising out of negligence in the repair, maintenance or upkeep of an improvement to real property.

Winnisquam Regional School District versus Daniel J. Levine

and Winnisquam Regional School District versus

Butler Manufacturing Company

• http://www.courts.state.nh.us/supreme/opinions/2005/winni096.htm

Project Scope• Adding Roof Trusses• Upgrade Electrical to Current Code• Ventilate Entire Roof • Removing mold under expert supervision• Bringing Insulation from R-38 to R-50• Replacing Sheetrock Ceilings• Upgrading the existing sprinkler system• Upgrading Fire Alarm Panel

Project Partners

• Architect – Mac Rood• Structural Engineer – Bruce Stewart• Contractor – Fenn-Way Builders• District Clerk of the Works – George Bagocius• School District Attorney – Gordon Graham• Fire Engineer – Nick Cricenti Jr. (SFC)• Electrical Engineer – Lee Carroll

Project Cost(as of 10/23/2008)

Total Project Estimate $2,471,394

Funds Already Budgeted - $239,532

Building Trust Fund Used - $80,392

Loan Required – amount to be raised

$2,151,470

How are we going to Fund the Project

Loan Required $2,151,470

Quality Zone Academy Bonds $1,498,000

Loan for Balance $ 653,470

QZAB BondsQZAB Bonds Available $1,498,000

About 1% Interest Earned over 15 years

- $104,860

Building Aid to be received over 15 years

- $898,800

QZAB Net Cost to Tax Payers $494,340

Loan for Balance of FundsPrincipal & fees $653,720

Plus Interest (5%) estimate $179,863

Less Building Aid to be received over 10 years

- $392,232

Loan Net Cost to Tax Payers $441,351

Net Cost to the TaxpayerQZAB Net Cost to Tax Payers $494,340

Loan Net Cost to Tax Payers $441,351

Building Aid to be Received on Funds already Budgeted

- $167,012

Net Project Cost to the Taxpayer over 15 years

$768,679

Impact on Our Taxes• No tax impact this school year (08-09)

• 2009 - 2010 Estimated Tax Rate Impact for this Project is $.12 per $1,000.00. The result is $12.00 for a $100,000 property

• Total debt payments for district will decline every year thereafter because the current bonds for 1991 District Building Project are paid off at the end of 2011

A “YES” vote means:

• Building repairs begin tomorrow

• Building will be structurally sound and compliant with current codes

• Students will be back in the building in January

A “NO” Vote means:

• Students stay in the Armory and other locations until at least the end of the school year

• All work on the building will end immediately

• Cannot petition the court for another special school district meeting on this issue this school year

“NO” Vote• Building repairs begin

tomorrow

• Building will be structurally sound and compliant with current codes

• Students will be back in the building in January

• Students stay in the Armory and other locations until at least the end of the school year

• All work on the building will end immediately

• Cannot petition the court for another special school district meeting on this issue this school year

“YES” Vote