H4-VLE commissioning Status Report · 7 GeV/c beam down to the NP -04 cryostat Last timing)...

Post on 14-Jul-2020

0 views 0 download

Transcript of H4-VLE commissioning Status Report · 7 GeV/c beam down to the NP -04 cryostat Last timing)...

H4-VLE commissioningStatus Report

M. Rosenthal, A. Booth, N. Charitonidis, Y. Karyotakis, I. Ortega, P. Sala

and many many others.

NP-04 Detector Activation Status

The H4-VLE tertiary branch

The H4-VLE extension

1189 ± 2

1047 ± 7

958 ± 6

843 ± 6

278 ± 3

208 ± 2

156 ± 1

Momentum Scan

B19 current

MeasurementSimulation (100% efficiency)Simulation (92% efficiency)

Collimator – Momentum selection

Very preliminary !

Simulation: For H2 !

Threshold Cherenkov – Preliminary results

Thanks to everybody for the effortsduring the first week of

H4-VLE commissiong & operation!