Post on 06-Apr-2018
8/3/2019 Great Small Foundation Project
1/60
Concrete Retaining WallJonathan Fuller, Angela Hughey, Bryan Lunsford, Alan Stevenson, Chad Wise
Auburn UniversityWomens Softball Complex
8/3/2019 Great Small Foundation Project
2/60
Table of Contents
Client Information
Project Details
Research
Preconstruction Photos
Model
Drawings
Takeoff & Estimate
Donated Material
Member Responsibility
Group Four
Schedule
Safety Plan
Photos
Final Costs
Conclusions
Member Statements
8/3/2019 Great Small Foundation Project
3/60
Client InformationOrganization: Auburn University (Womens Softball)
Contact: Jan Swaim, Pete Dunnaway
Project DetailsThe structure needed was a concrete retaining wall to preventfurther mud damage to the batting cages in the womens softballcomplex. The wall will connect to an existing series of retaining
walls and stand about waist high.
8/3/2019 Great Small Foundation Project
4/60
Researchhttp://www.concretenetwork.com/concrete/poured_concrete_retai
ning_walls/provisions.htm
Provisions for Joints in the Construction of Walls
This online article details the use ofjoints in concrete construction. Wereferenced it in designing ourexpansion joint. The article alsoshows key and roughened surfacejoints.
8/3/2019 Great Small Foundation Project
5/60
Preconstruction Photo
8/3/2019 Great Small Foundation Project
6/60
Preconstruction Photo
8/3/2019 Great Small Foundation Project
7/60
Design Sketches
8/3/2019 Great Small Foundation Project
8/60
Design Sketches
8/3/2019 Great Small Foundation Project
9/60
3D Modeling
8/3/2019 Great Small Foundation Project
10/60
3D Modeling
8/3/2019 Great Small Foundation Project
11/60
3D Modeling
8/3/2019 Great Small Foundation Project
12/60
Detail Documentation
8/3/2019 Great Small Foundation Project
13/60
Detail Documentation
8/3/2019 Great Small Foundation Project
14/60
Original Take off & Estimate
4x8x1/2 Plywood (15)
-1 Drill bit
Concrete: 9.77cu. yds. =about 10cu. yds.
#4 Rebar=524 linear feet
Spray form release
Screws (2 and 3)
Spray expansion foam
gravel (.67 x 48 x 1 = 33 cu. Ft.)
Drain pipe= 75 linear ft.
Vapor barrier= 1
2x4x16
2x4x8
($18 ea.)$270
Na
($56ea.)$560
786
$5
$10
$5
free
36
36
240
230
About $2168.00
8/3/2019 Great Small Foundation Project
15/60
Donated Material & Services
Tiebacks
Pigs feet
Fence moved 50ft
Bobcat / backhoe rental
Shovels AU and us
Tools us
Edger
Trowel
Rebar cutter
Gutter moved
8/3/2019 Great Small Foundation Project
16/60
Group member responsibilities
Jonathan Fuller: Rebar delivery and placementJonathan Fuller: Rebar delivery and placement
AngelaAngela HugheyHughey: On site organization: On site organization
Bryan Lunsford: Client communicatorBryan Lunsford: Client communicator
Alan Stevenson: Project drawing, FormsAlan Stevenson: Project drawing, Forms
Chad Wise: Concrete delivery and placement/ Safety ManagerChad Wise: Concrete delivery and placement/ Safety Manager
8/3/2019 Great Small Foundation Project
17/60
Project Schedule
8/3/2019 Great Small Foundation Project
18/60
Job Specific Project Safety Program
All exposed footings must be roped off
with caution tape and flagged.
All power equipment must be used bya competent person.
Safety glasses must be worn at alltimes.
In cases of accident all personal must
see Chad Wise Safety Manager.
Cell Phone must be present at all timesincase of emergency.
8/3/2019 Great Small Foundation Project
19/60
8/3/2019 Great Small Foundation Project
20/60
8/3/2019 Great Small Foundation Project
21/60
8/3/2019 Great Small Foundation Project
22/60
8/3/2019 Great Small Foundation Project
23/60
8/3/2019 Great Small Foundation Project
24/60
8/3/2019 Great Small Foundation Project
25/60
8/3/2019 Great Small Foundation Project
26/60
8/3/2019 Great Small Foundation Project
27/60
8/3/2019 Great Small Foundation Project
28/60
8/3/2019 Great Small Foundation Project
29/60
8/3/2019 Great Small Foundation Project
30/60
8/3/2019 Great Small Foundation Project
31/60
8/3/2019 Great Small Foundation Project
32/60
8/3/2019 Great Small Foundation Project
33/60
8/3/2019 Great Small Foundation Project
34/60
8/3/2019 Great Small Foundation Project
35/60
8/3/2019 Great Small Foundation Project
36/60
8/3/2019 Great Small Foundation Project
37/60
8/3/2019 Great Small Foundation Project
38/60
8/3/2019 Great Small Foundation Project
39/60
8/3/2019 Great Small Foundation Project
40/60
8/3/2019 Great Small Foundation Project
41/60
8/3/2019 Great Small Foundation Project
42/60
8/3/2019 Great Small Foundation Project
43/60
8/3/2019 Great Small Foundation Project
44/60
8/3/2019 Great Small Foundation Project
45/60
8/3/2019 Great Small Foundation Project
46/60
8/3/2019 Great Small Foundation Project
47/60
8/3/2019 Great Small Foundation Project
48/60
8/3/2019 Great Small Foundation Project
49/60
8/3/2019 Great Small Foundation Project
50/60
8/3/2019 Great Small Foundation Project
51/60
8/3/2019 Great Small Foundation Project
52/60
8/3/2019 Great Small Foundation Project
53/60
8/3/2019 Great Small Foundation Project
54/60
8/3/2019 Great Small Foundation Project
55/60
8/3/2019 Great Small Foundation Project
56/60
8/3/2019 Great Small Foundation Project
57/60
8/3/2019 Great Small Foundation Project
58/60
Final Costs
4x8x1/2 Plywood (14)
2x4x16 Pine
2x4x8 Pine
Concrete: 15.5 cubic yards
#4 Rebar= 28-20 pieces
Chamfer strips
Powder Actuated Nail Gun with 2 Pin and
27 Cal Strip Load Green
Turnbuckle, form
Silicon
1/2x4x8 Blue Board
Cast Off (5Gal) Release Form
Snap Tie
Screws (2 and 3)
gravel
Drain pipe= 75 linear ft.
$529.76
$184.50
$185.46
($56ea.)$868.00
87.36
$36.00
$46.00
$46.00
$221.85
$21.88
$8.28
$29.79
$69.99
$Free
$Free
$36.00
Total $2370.87 Estimated $2168.00
8/3/2019 Great Small Foundation Project
59/60
Conclusions | Things we might have changed
Vibration should be systematic and even throughout the wallVibration should be systematic and even throughout the wall
Use more caution during pour (chamfer strips)Use more caution during pour (chamfer strips)
DonDont assume anything.t assume anything. --Jan Swan (footing below)Jan Swan (footing below)
We could have drawn more detailed drawings beforeWe could have drawn more detailed drawings before
construction instead of fastconstruction instead of fast--trackingtracking
Pay attention to the politics in any jobPay attention to the politics in any job
Have clear communication with everyone involvedHave clear communication with everyone involved
8/3/2019 Great Small Foundation Project
60/60
Jonathan Fuller:Jonathan Fuller: HandsHands--on is the best way to learn.on is the best way to learn.
AngelaAngela HugheyHughey:: Building always takes longer than you think.Building always takes longer than you think.
Bryan Lunsford:Bryan Lunsford: Working with personnel is difficult.Working with personnel is difficult.
Alan Stevenson:Alan Stevenson: Working in a group can be rewarding andWorking in a group can be rewarding and
challenging.challenging.
Chad Wise:Chad Wise: Prof. Hein is the greatest.Prof. Hein is the greatest.
Group Member Statements