Federal Energy Regulatory Commission The FERC Regulatory Process Dennis H. Melvin, Esq. Director –...

Post on 16-Jan-2016

220 views 0 download

Transcript of Federal Energy Regulatory Commission The FERC Regulatory Process Dennis H. Melvin, Esq. Director –...

Federal Energy Regulatory Commission

The FERC Regulatory Process

Dennis H. Melvin, Esq.

Director – Legal Division (OAL)

Federal Energy Regulatory Commission

Washington, DC

August 9, 2005 FERC Regulatory Process 2

Federal Energy Regulatory Commission

Question

•How does FERC decide what a utility can charge and what goes into a tariff?

August 9, 2005 FERC Regulatory Process 3

Federal Energy Regulatory Commission

How Does FERC Regulate?

• Industry-wide Decisions– Notice of Inquiry (NOI)– Notice of Proposed Rulemaking (NOPR)– Final Rule or Policy Statement

• Company Specific Decisions– Applications (rate increase, change in a term or

condition of a contract, etc.) or complaints filed by utilities, customers, interested parties or state commissions

August 9, 2005 FERC Regulatory Process 4

Federal Energy Regulatory Commission

Company Specific Decisions

• Application or complaint filed

• Filing is publicly noticed

• Staff analysis and recommendation to the Commission (tight deadlines)

August 9, 2005 FERC Regulatory Process 5

Federal Energy Regulatory Commission

• Commission action– Decide merits of case without further

procedures

– Hold a technical conference or call for more written information

– Hold trial-type hearing before an Administrative Law Judge

Company Specific Decisions (con’t)

August 9, 2005 FERC Regulatory Process 6

Federal Energy Regulatory Commission

OAL• Represents the public interest• Only unbiased party• The results we seek:

– Lowest rates consistent with a well-run utility

– Non-discriminatory treatment for all customers

– Opportunity for utility to earn a fair return and compete

August 9, 2005 FERC Regulatory Process 7

Federal Energy Regulatory Commission

Settlements Are Important

• Prevents the legal system from being overloaded

• Settlement allows for faster resolution of disputes

• Parties are usually happier with a settlement

August 9, 2005 FERC Regulatory Process 8

Federal Energy Regulatory Commission

Adjudication Milestones

• 1. Judge assigned and Procedural Track set• 2. Prehearing/Discovery• 3. Prepared Testimony• 4. Pre Trial Brief• 5. Hearing• 6. Initial and Reply Briefs• 7. Initial Decision • 8. Exceptions Briefs• 9. Commission Order & Rehearing

August 9, 2005 FERC Regulatory Process 9

Federal Energy Regulatory Commission

Milestone One

• The Chief Judge will:– Assign an Administrative Law Judge to the

case– May indicate a deadline for decision

August 9, 2005 FERC Regulatory Process 10

Federal Energy Regulatory Commission

Milestone Two• Prehearing Conference

– Conducted by Presiding Judge assigned– Scope and timetable to be determined– Settlement urged, Trial Staff available

• Discovery– Discovery concerns raised with ALJ– Procedures established– Wide range of options

August 9, 2005 FERC Regulatory Process 11

Federal Energy Regulatory Commission

Discovery

• Information regularly filed with the agency

• Written questions and answers

• Subpoenas available– Necessary if non-party data required– Nationwide reach

• Depositions, Inspections, Audits

August 9, 2005 FERC Regulatory Process 12

Federal Energy Regulatory Commission

Protective Orders

• Intent is to safeguard confidential information

• Order describes how confidential data is to be handled

• Issued by the Judge

• Everyone must sign and agree to its terms

August 9, 2005 FERC Regulatory Process 13

Federal Energy Regulatory Commission

Milestone Three

• Prepared Testimony– Prefiled before the hearing– May contain confidential information and

need special handling– May be electronically filed– Several rounds

August 9, 2005 FERC Regulatory Process 14

Federal Energy Regulatory Commission

August 9, 2005 FERC Regulatory Process 15

Federal Energy Regulatory Commission

August 9, 2005 FERC Regulatory Process 16

Federal Energy Regulatory Commission

Milestone Four

• Pre Trial Brief– Includes the theory of the case– Evidence to be presented– Summary of witnesses’ testimony – Description of exhibits– Legal foundation and precedent– Weaknesses in presentations of others

August 9, 2005 FERC Regulatory Process 17

Federal Energy Regulatory Commission

Milestone Five• Hearing

– Can last one day to many months– Witnesses sworn, direct testimony and

exhibits admitted, then cross-examination– Confidential testimony requires special

procedures– Written transcript made – Judge ultimately decides admissibility of

evidence

August 9, 2005 FERC Regulatory Process 18

Federal Energy Regulatory Commission

A Hearing Room at the FERC

August 9, 2005 FERC Regulatory Process 19

Federal Energy Regulatory Commission

Another Hearing Room

August 9, 2005 FERC Regulatory Process 20

Federal Energy Regulatory Commission

Milestone Six

• Initial and Reply Briefs– Dates set by Presiding ALJ– Simultaneous unless ordered otherwise– Must not discuss evidence outside of the

record

August 9, 2005 FERC Regulatory Process 21

Federal Energy Regulatory Commission

Milestone Seven

• Initial Decision – Usually summarizes evidence and

arguments– Published in FERC Reports– Certified to Commission with the record– Always subject to Commission review

August 9, 2005 FERC Regulatory Process 22

Federal Energy Regulatory Commission

Milestone Eight

• Briefs On and Opposing Exceptions– 30 days after ID, 20 days thereafter– Must be less than 100 pages

August 9, 2005 FERC Regulatory Process 23

Federal Energy Regulatory Commission

Milestone Nine• Commission Order & Rehearing

– No deadlines on Commission action on Judge’s ruling

– Published in FERC Reports– Rehearing request must be filed within 30

days– Further appeals can be made to the court

system

August 9, 2005 FERC Regulatory Process 24

Federal Energy Regulatory Commission

Thank you for your attention !

• Dennis H. Melvin, Esq.» Director, Legal Division» Office of Administrative Litigation» Federal Energy Regulatory Commission» 888 First Street, NE» Washington, DC 20426» (202) 502-8042 : Phone» (202) 208-0188 : FAX» dennis.melvin@ferc.gov