Federal AviationAdministrationAirport 20 to 1

Approach Surface &

Restoring Night Minimums

Georgia Airports Association (GAA) 2015 Annual Workshop

Cindy M Hintz Eastern Flight Procedures Team

February 27, 2015

Federal AviationAdministration

2

20:1 Penetrations Background

• Late 1990’s: Criteria developed by Flight Standards (AFS).

• Oct 2012: AFS required immediate NOTAM action to restrict night operations when 20:1 penetrations identified.

• Jan 2014: Refined policy considered “Risk” factors based on the amount of obstacle penetration, allowed the airport manager a 30 day validation period, and allowed for Category A/B and C/D surface areas to be restricted independently. (NOTAMs could restrict the C/D area only if the A/B area was clear of penetrations).

Federal AviationAdministration

3

• AFS has implemented a change to FAA Order 8260.3B, United States Standards for TERPS, Straight-in Visual Area Beginning Width.

Recent Change to 20:1 Dimensions

Federal AviationAdministration

4

Dimension Changes Outlined

Federal AviationAdministration

5

New vs Old 20:1 (Width)• Original 20:1: CAT C/D beginning width 800FT • Revised (20:1 & 34:1): CAT A/B/C/D beginning width 400FT

Federal AviationAdministration

6

TERPS

Offset Evaluation

Federal AviationAdministration

7

How are 20:1 Approach PenetrationsIdentified ?????

•Biennial Review: Terminal instrument procedures reviewed every two years against current criteria. During this review 20:1 penetrations may be identified.

•Routine Amendments: While amending procedures to support airport improvement projects or Air Traffic change requests, current criteria is applied and 20:1 penetrations may be identified.

Federal AviationAdministration

8

When 20:1 Penetrations Identified Notification Process

• Initial Notification: Within 3 business days, a file is forwarded to the airport sponsor requiring validation of each penetration ASAP, but not more than 30 days. The Airport District Office (ADO) is info copied.

• Action required by sponsor: Airport owner/sponsor must provide written validation report to FPT and info copy ADO.

• No Response: If no response received from sponsor within 30 days, the penetrations will be treated as existing and the instrument Approach Procedures (IAPs) will be restricted at night by NOTAM.

Federal AviationAdministration

9

Obstacle Verification• Verification: Airport owner/sponsor must verify the

validity of each penetration as soon as possible but notification must not exceed 30 calendar days.

• 20:1 Determined Invalid: Sponsor determines the obstacle does not exist or it has been removed or reduced in height that no longer penetrates the 20:1 surface. (Documentation Required).

• 20:1 Determined Valid: Sponsor determines the obstacle does exist at the reported location/height.

Federal AviationAdministration

10

Airport Owner/Sponsor Required Response

• If 20:1 penetrations determined INVALID: FPT will notify applicable offices to update airport’s data file(s). NOTAM action will not be taken to restrict or modify Instrument Approach Procedure (IAP).

• If 20 to 1 penetrations determined VALID: – Airport owner/sponsor submits written compliance plan.– Airport owner/sponsor mitigates the penetration through

removal, lighting, reduction in height, or VGSI waiver.– FAA action taken per Risk Assessment Criteria

Federal AviationAdministration

11

Federal AviationAdministration

12

Federal AviationAdministration

13

Alternate Mitigation Option using Visual Glide Slope Indicator (VGSI):

• Temporary waiver good for 30 days while obtaining Flight Standards Approval.

• VGSI Mitigation Requirements: –Equipment Unrestricted & Clear OCS–Angle of VGSI equal to or less than IAP angle–TCH not more than 15 FT higher than IAP TCH–Visual Descent Point (VDP) not published–Visibility not lower than 1 SM.

Federal AviationAdministration

14

Alternative Mitigation Option using Full-Scale Deflection of ILS/LOC/LPV/LP

Federal AviationAdministration

15

AeroNav Products Automatically Evaluates for this

Federal AviationAdministration

16

Obstacles Mitigated – NOW WHAT???• Trees Removed: Notify FPT of tree removal. Include

Obstacle Identification (ID).

• Trees Trimmed: Notify FPT of completed tree trimming. A stamped and signed survey must be provided to support a new obstacle height. – Obstacle ID with Coordinates– Site Elevation with Accuracy Code (AC)– Revised Tree MSL and AGL Height

• Structures Lighted: Notify FPT if the structure has been lighted (Include the obstacle ID).

Federal AviationAdministration

17

Re-Evaluation of Night Restrictions • Existing Night Restrictions: Contact FPT and ask for a

re-evaluation of your airport to determine if the new surface area provides any relief to your airport.

• NOTAMs: – If there are existing NOTAMs and it’s determined the

20:1 penetrations are no longer applicable or have been removed, the NOTAM can be cancelled

– If restrictions are already charted (NA at Night) and it’s determined the restriction is no longer applicable, it’s possible to regain night operations through a temporary NOTAM followed by a chart amendment.

Federal AviationAdministration

18

Thank you

Questions?