SR A1A (Highway A1A) US 192 to SR 404 (Pineda Causeway), Brevard County, Florida

Financial Project Number: 428753-1-32-01

February 11, 2016

TPO Board Presentation

Presenter
Presentation Notes
Welcome to the Public Hearing for the SR A1A safety improvement project. Brevard County, Florida

Begin Project

End Project

Project Limits (MP 17.552 to MP 26.226) Begin 200 feet north of US 192 (5th Avenue) End 600 feet north of SR 404 (Pineda Causeway) Approximately 8.7 miles.

Project Limits – US 192 to SR 404 (428753-1)

Municipalities Indiatlantic Melbourne Indian Harbour Beach Satellite Beach Brevard County

Initial Project Elements (2012) 1. Milling and Resurfacing 2. Pedestrian Signal Improvements 3. Curb Ramp Improvements (ADA) 4. Roadside Drainage Improvements 5. Improve Transit Access 6. Minor Sidewalk Improvements

Project Improvements

Added Project Elements (2014-2015) 1. Mast Arm Upgrades 2. 7 New Mid-block Crossings 3. New Sidewalk Construction 4. Median Improvements 5. New Cross Walk Locations 6. Improved Transit Stops 7. Marked Bike Lanes 8. Eliminate Auxiliary Lanes 9. Extend Turn Lane

Initial Project Elements (2012) 1. Milling and Resurfacing 2. Pedestrian Signal Improvements 3. Curb Ramp Improvements (ADA) 4. Roadside Drainage Improvements 5. Improve Transit Access 6. Minor Sidewalk Improvements

Project Improvements

HIGHWAY A1A

Initial Project Elements (2012) 1. Milling and Resurfacing 2. Pedestrian Signal Improvements 3. Curb Ramp Improvements (ADA) 4. Roadside Drainage Improvements 5. Improve Transit Access 6. Minor Sidewalk Improvements

Intersections 1. Grosse Point Avenue 2. Paradise Boulevard 3. Holy Name Way 4. Eau Gallie Boulevard 5. Palm Springs Boulevard 6. Pine Tree Drive 7. DeSoto Parkway 8. Cassia Boulevard 9. Jackson Avenue 10. Scorpion Court 11. Shearwater Parkway 12. Berkley Street 13. Ocean Boulevard

Project Improvements

Initial Project Elements (2012) 1. Milling and Resurfacing 2. Pedestrian Signal Improvements 3. Curb Ramp Improvements (ADA) 4. Roadside Drainage Improvements 5. Improve Transit Access 6. Minor Sidewalk Improvements

Project Wide 1. Improve Curb Ramp (signalized intersections) 2. Add Directional Warning Devices

Project Improvements

Initial Project Elements (2012) 1. Milling and Resurfacing 2. Pedestrian Signal Improvements 3. Curb Ramp Improvements (ADA) 4. Roadside Drainage Improvements 5. Improve Transit Access 6. Minor Sidewalk Improvements

Project Wide 1. Replace Ditches with Pipe 2. Upgrade Inlet Grates to meet ADA Standards 3. Replace Deteriorated Structures 4. Install Railings

Project Improvements

Initial Project Elements (2012) 1. Milling and Resurfacing 2. Pedestrian Signal Improvements 3. Curb Ramp Improvements (ADA) 4. Roadside Drainage Improvements 5. Improve Transit Access 6. Minor Sidewalk Improvements

Project Wide 1. Construct Bus Pads (43 Locations)

Project Improvements

Initial Project Elements (2012) 1. Milling and Resurfacing 2. Pedestrian Signal Improvements 3. Curb Ramp Improvements (ADA) 4. Roadside Drainage Improvements 5. Improve Transit Access 6. Minor Sidewalk Improvements

Project Wide Connect Isolated Transit Stops

Project Improvements

Intersections 1. Grosse Point Avenue 2. Paradise Boulevard* 3. Holy Name Way 4. Eau Gallie Boulevard 5. Palm Springs Boulevard* 6. Pine Tree Drive* 7. DeSoto Parkway* 8. Cassia Boulevard* 9. Jackson Avenue* 10. Scorpion Court* 11. Shearwater Parkway* 12. Berkley Street 13. Ocean Boulevard

Added Project Elements (2014-2015) 1. Mast Arm Upgrades 2. 7 New Mid-block Crossings 3. New Sidewalk Construction 4. Median Improvements 5. New Cross Walk Locations 6. Improved Transit Stops 7. Marked Bike Lanes 8. Remove Auxiliary Lanes 9. Extend Turn Lane

Project Improvements

*Upgrade to Mast Arm

Project Improvements

*Upgrade to Mast Arm

Nearest Intersection

1. Wallace Avenue* 2. Satellite Avenue 3. Sunrise Avenue 4. Magellan Avenue 5. Royal Palm Boulevard 6. Ellwood Avenue 7. Grant Avenue**

Added Project Elements (2014-2015) 1. Mast Arm Upgrades 2. 7 New Mid-block Crossings (Beach Access) 3. New Sidewalk Construction 4. Median Improvements 5. New Cross Walk Locations 6. Improved Transit Stops 7. Marked Bike Lanes 8. Remove Auxiliary Lanes 9. Extend Turn Lane

Project Improvements

*Subject to Approval

**Access Change

Typical Mid-Block Crossing

SR A1A

COQUINA POINT GOODWILL COMMERCIAL SHOPS

BUCCANEER BUCCANEER

Sidewalk Limits

1. Transit Stop Connectivity 2. Glenwood Avenue to Ellwood Avenue 3. Grant Avenue to Jackson Street 4. Jackson Street to Scorpion Court (west side) 5. Scorpion Court to Shearwater Parkway (west side) 6. Ocean Boulevard to Beach Park (east side)

Added Project Elements (2014-2015) 1. Mast Arm Upgrades 2. 7 New Mid-block Crossings 3. New Sidewalk Construction 4. Median Improvements 5. New Cross Walk Locations 6. Improved Transit Stops 7. Marked Bike Lanes 8. Remove Auxiliary Lanes 9. Extend Turn Lane

Project Improvements

Sodding and Curbing 1. Mid-block Crossing Locations 2. Convert Existing Traffic Separators

DeSoto Parkway Intersection Scorpion Court Intersection Shearwater Parkway Intersection

3. Shearwater Parkway to Satellite Beach City Limits

Added Project Elements (2014-2015) 1. Mast Arm Upgrades 2. 7 New Mid-block Crossings 3. New Sidewalk Construction 4. Median Improvements 5. New Cross Walk Locations 6. Improved Transit Stops 7. Marked Bike Lanes 8. Remove Auxiliary Lanes 9. Extend Turn Lane

Project Improvements

Intersections 1. Grosse Point Avenue 2. Paradise Boulevard 3. Holy Name Way 4. Eau Gallie Boulevard 5. Palm Springs Boulevard 6. Pine Tree Drive 7. DeSoto Parkway 8. Cassia Boulevard 9. Jackson Avenue 10. Scorpion Court 11. Shearwater Parkway 12. Berkley Street 13. Ocean Boulevard

Added Project Elements (2014-2015) 1. Mast Arm Upgrades 2. 7 New Mid-block Crossings 3. New Sidewalk Construction 4. Median Improvements 5. New Cross Walk Locations 6. Improved Transit Stops 7. Marked Bike Lanes 8. Remove Auxiliary Lanes 9. Extend Turn Lane

Project Improvements

*Add Northside Crossing to Intersection

Project Improvements

SR A1A

Convert Concrete Traffic Separator to Grassed Median

Transit Stop: Construct Bus Pad

Construct Sidewalk To Connect Transit Stop

Transit Stop: Construct Bus Pad

Convert Concrete Traffic Separator to Grassed Median

Add New Crosswalk Leg

Improve Curb Ramps

Improve Curb Ramps

Presenter
Presentation Notes

Boarding and Alighting Areas

1. SE 1st 2. Seaview Plaza (Ocean Blvd)

Added Project Elements (2014-2015) 1. Mast Arm Upgrades 2. 7 New Mid-block Crossings 3. New Sidewalk Construction 4. Median Improvements 5. New Cross Walk Locations 6. Improved Transit Stops 7. Marked Bike Lanes 8. Remove Auxiliary Lanes 9. Extend Turn Lane

Project Improvements

Bicycle Markings

Added Project Elements (2014-2015) 1. Mast Arm Upgrades 2. 7 New Mid-block Crossings 3. New Sidewalk Construction 4. Median Improvements 5. New Cross Walk Locations 6. Improved Transit Stops 7. Marked Bike Lanes 8. Remove Auxiliary Lanes 9. Extend Turn Lane

Project Improvements

Added Project Elements (2014-2015) 1. Mast Arm Upgrades 2. 7 New Mid-block Crossings 3. New Sidewalk Construction 4. Median Improvements 5. New Cross Walk Locations 6. Improved Transit Stops 7. Marked Bike Lanes 8. Remove Auxiliary Lanes 9. Extend Turn Lane

Project Improvements Locations

1. Southbound from Sunrise Avenue

2. Southbound from Jackson Street

3. Northbound at Sandpiper Condominiums

4. Northbound Continuous Green at Pineda Causeway

Added Project Elements (2014-2015) 1. Mast Arm Upgrades 2. 7 New Mid-block Crossings 3. New Sidewalk Construction 4. Median Improvements 5. New Cross Walk Locations 6. Improved Transit Stops 7. Marked Bike Lanes 8. Remove Auxiliary Lanes 9. Extend Turn Lane

Project Improvements

Locations

Southbound Right Turn Lane to Scorpion Court

SR A1A (Highway A1A) US 192 to SR 404 (Pineda Causeway), Brevard County, Florida

Financial Project Number: 428753-1-32-01

Schedule & Estimated Construction Cost Plans Complete – March 2016

Construction Begin – Fall 2016

2016 Construction Cost Estimate – $10.6M*