Harlan High School

Facilities Construction

NNOORRTTHHSSIIDDEE IINNDDEEPPEENNDDEENNTT SSCCHHOOOOLL DDIISSTTRRIICCTT

Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS

Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING

Jim Berg DIRECTOR OF FACILITIES CONSTRUCTION

December 2016

2014 BOND PROJECTS

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL)

Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – Jim Berg Contractor – Joeris General Contractor GMP - $110,800,000.00 Construction Period – October 2014 – May 2017 Construction Status: 87% Complete Project Scope – New 2800 Student High School

Site grading, utilities and landscaping in progress. Interior CMU walls, drywall framing, electrical, plumbing, and HVAC installation in progress. Window installation, interior painting, exterior brick veneer and roofing in progress. Concrete drives and parking areas in progress. Punch in progress. Athletic field sodding in progress.

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Aerial (Nov. 22, 2016)

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Front Entrance

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (December 2016)

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (December 2016)

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (December 2016)

KALLISON ELEMENTARY SCHOOL (KALLISON RANCH #2 ELEMENTARY)

Architect – Garza Bomberger Project Architect – Roy Lewis NISD Project Manager – Marilyn Sevedge Contractor – Guido Construction Construction Amount - $24,640,000.00 Construction Period – March 7, 2016 – May 26, 2017 Construction Status: 40% Complete Project Scope – New 800 Student Elementary School

Structural steel erection and masonry ongoing. Floor slabs are 80% complete. Brick, MEP ductwork and roofing are starting. Pedestrian bridge installed.

KALLISON ELEMENTARY SCHOOL Aerial (November 2016)

KALLISON ELEMENTARY SCHOOL Aerial (November 2016)

KALLISON ELEMENTARY SCHOOL Front Entrance

KALLISON ELEMENTARY SCHOOL (December 6, 2016)

KALLISON ELEMENTARY SCHOOL (December 6, 2016)

KALLISON ELEMENTARY SCHOOL (December 6, 2016)

ADDITIONS AND RENOVATIONS

PROJECTS IN PROGRESS

ALLEN ES CLASSROOM - ADDITION/ADA/WINDOW UPGRADES

Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Chris Parker Contractor – Suburban Construction Co. Construction Amount - $4,075,000.00 Construction Period – March 2016 – December 2016 Construction Status: 90% Complete Project Scope – Classroom Addition/ADA/Window Upgrades

Addition structural concrete complete. Masonry in progress. Structural steel/decking complete. MEP, paint and ceramic tile in progress.

ALLEN ES CLASSROOM - (Rendering of Site and Floor Plans)

ALLEN ES CLASSROOM - (Rendering of Floor Plan, Elevation and Perspectives)

ALLEN ES CLASSROOM - ADDITION/ADA/WINDOW UPGRADES (December 1, 2016)

ALLEN ES CLASSROOM - ADDITION/ADA/WINDOW UPGRADES (December 1, 2016)

GLENOAKS ELEMENTARY - Administration Upgrades/Security Lobby

Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – McGoldrick Construction Co. Construction Amount - $3,750,000.00 Construction Period – June 2016 – March 2017 Construction Status: 30% Complete Project Scope – New Administration Building

Forming for Floor Slab.

GLENOAKS ELEMENTARY (Rendering of Front Elevation)

GLENOAKS ELEMENTARY Administration Upgrades (November 15, 2016)

GLENOAKS ELEMENTARY Administration Upgrades (November 22, 2016)

GLENOAKS ELEMENTARY Administration Upgrades (December 1, 2016)

2014 BOND PROJECTS

IN

BID/DESIGN PHASE

SUMMER 2016

HOLMES HS FINE ARTS UPGRADE

Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Jim Berg Contractor – Bartlett Cocke Construction Budget - $27,900,000.00 Tentative Construction Period – June 2017 – December 2018 Project Scope – Fine Arts Building Replacement

Schematic design approved by Board on September 27, 2016. Site and Demolition Construction Documents in progress.

NORTHSIDE ACTIVITY CENTER RENOVATIONS

Architect – Richard Sanchez Architects, Inc. Project Architect – Richard Sanchez NISD Project Manager – Thomas Curiel Contractor – TBD Construction Budget - $4,000,000.00 Tentative Construction Period – January 2017 – January 2018 Project Scope – Addition

Construction Documents issued for proposals.

PAUL TAYLOR FIELD HOUSE RENOVATIONS

Architect – Garza Bomberger Architects Project Architect – Roy Lewis NISD Project Manager – Thomas Curiel Contractor – TBD Construction Budget - $4,600,000.00 Tentative Construction Period – February 2017 – August 2017 Project Scope – ADA Interior/Exterior Renovations

Construction Documents issued for proposals.

2014 BOND PROJECTS

IN

BID/DESIGN PHASE

SUMMER 2017

GROSENBACHER AREA ELEMENTARY (Prototype of Boldt ES and Cole ES)

Architect – Noonan Rittiman Project Architect – John Rittiman NISD Project Manager – Tom Curiel Contractor – TBD Construction Budget - $24,000,000 Tentative Construction Period – March 2017 – May 2018 Project Scope – New 800 Student Elementary School (Prototype of Boldt ES and Coles ES)

95% Construction Documents review scheduled for December 7, 2016.

2017 SECURITY LOBBIES at (9) ELEMENTARY SCHOOLS

Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $1,260,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – New Security Lobby for (9) Elementary Schools:

Adams Hill ES, Allen ES, Beard ES, Braun Station ES, Forester ES, Hoffmann ES, Knowlton ES, Timberwilde ES, and Villarreal ES

Construction Documents issued for proposals.

BOONE ELEMENTARY - Administration Upgrades, Bus/Student Canopy & Security Lobby

Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Jim Berg Contractor – TBD Construction Budget - $4,040,000.00 Tentative Construction Period – June 2017 – May 2018 Project Scope – Administration Upgrades, Bus/Student Walkway Canopy

Modifications Schematic Design approved by Board on October 25, 2016. Construction Documents in progress.

COLONIES NORTH ELEMENTARY Window Upgrades / ADA Work

Architect – Huckabee Architects Project Architect – Jeff Rodriquez NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $2,000,000.00 Tentative Construction Period – June 2017 – October 2017 Project Scope – Window Upgrades and ADA Work Construction Documents in Progress.

GLASS ELEMENTARY Window Upgrades / ADA Work

Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $1,500,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Window Upgrades and ADA Work Schematic Design meeting scheduled for December 15, 2016.

GLENOAKS ELEMENTARY - Window Upgrades / ADA Work

Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $1,100,000.00 Tentative Construction Period – June 2017 – December 2017 Project Scope – Window Upgrades and ADA Work

Schematic Design Phase pending Board Approval.

GLENN ELEMENTARY School Building Replacements / Security Lobby

Architect – LPA Project Architect – Mark Oppelt NISD Project Manager – Jim Berg Contractor – TBD Construction Budget - $4,800,000.00 Tentative Construction Period – June 2017 – August 2018 Project Scope – Replacement of Buildings

Schematic Design scheduled for Building Committee review October 25, 2016. Construction Documents in progress.

KNOWLTON ELEMENTARY Cafeteria / Kitchen Renovations / Library Addition

Architect – Pfluger Project Architect – Carr Hornbuckle NISD Project Manager – Jim Berg Contractor – TBD Construction Budget – $2,200,000.00 Tentative Construction Period – June 2017 – November 2017 Project Scope – Renovations and Additions

Schematic Design approved by Board on October 25, 2016. Construction Documents in progress.

TIMBERWILDE ELEMENTARY Cafeteria/Kitchen Renovations/Library Addition

Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $2,200,000.00 Tentative Construction Period – June 2017 – November 2017 Project Scope – Renovations and Additions

Schematic Design approved by Board on October 25, 2016. Construction Documents in progress.

MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovations

Architect – Garza Bomberger Architects Project Architect – Roy Lewis NISD Project Manager – Tom Curiel Contractor – TBD Construction Budget – $4,400,000.00 Tentative Construction Period – June 2017 – March 2018 Project Scope – Renovations and Additions

Schematic Design in progress.

2017 DOOR HARDWARE Glass ES, Westwood Terrace ES and Holmes HS

Architect – Chesney Morales Project Architect – Richard Morales NISD Project Manager – Jim Berg Contractor – TBD Construction Budget – $117,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Door Hardware

Construction Documents in progress.

2017 FLOORING REPLACEMENTS Elrod, Glenn, Glenoaks, & Michael Elementary

Architect – CWS Architect Project Architect – Robert Watts NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $230,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Flooring

Construction Documents in progress.

2017 FLOORING REPLACEMENTS Carson ES, Neff MS, & Warren HS

Architect – Huckabee Architects Project Architect – Jeff Rodriguez NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $325,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Flooring

Construction Documents in progress.

NEFF MS COMPETITION GYM FLOORING AND BLEACHERS

Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $ TBD Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Flooring and Bleachers

Construction Documents in progress.

2016 GROWTH & IMPROVEMENT

2016 ATHLETIC AREA UPGRADES JAY HS, CLARK HS, JONES MS & ROSS MS

Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Chris Parker Contractor – STI-GC Contract Amount - $1,500,000.00 Construction Period – May 2016 – August 2016 Construction Status: 96% Complete Project Scope – Installation of Athletic Storage Units and Interior

Renovations. Locker and millwork replacement complete. Athletic storage

unit installation complete. Wire mesh partitions installation in progress. Closeout in progress.

CHILD NUTRITION WAREHOUSE Warehouse Renovation

Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Henry Acosta Contractor – Workman Commercial Contract Amount - $5,726,500.00 Construction Period – July 2016 – January 2017 Construction Status: 29% Complete Project Scope – Warehouse Renovation

Contract in progress. Renovation funded from Child Nutrition 2016 Growth & Improvement funds and 2010 Bond Savings.

Demo complete, rough-ins in progress. Walk in cooler/freezer floor in progress.

CHILD NUTRITION WAREHOUSE - Warehouse Renovation (Aerial View)

CHILD NUTRITION WAREHOUSE Warehouse Renovation (Nov. 18, 2016)

CHILD NUTRITION WAREHOUSE Warehouse Renovation (Nov. 18, 2016)

CHILD NUTRITION WAREHOUSE Warehouse Renovation (Nov. 18, 2016)

2017 GROWTH & IMPROVEMENT

2017 ATHLETIC AREAS UPGRADES Hobby MS, Pease MS, and Taft HS

Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Chris Parker Contractor – TBD Contract Amount – TBD Construction Period – June 2017 – August 2017 Construction Status: 0% Complete Project Scope – Installation of Athletic Storage Units and Interior

Renovations. Schematic Design in progress.

ROOFING PROJECTS

BOONE ELEMENTARY SCHOOL ROOFING PROJECT

Roofing Consultant – Raba Kistner Contractor – Samuel Dean Sheet Metal Inc. Contract Amount – $336,973.00 Construction Period – June – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing

Project Closeout in Progress.

CABLE ELEMENTARY SCHOOL ROOFING PROJECT

Roofing Consultant – Austech Engineering Contractor – Cram Roofing Contract Amount – $199,550.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repairs & Waterproofing

Project Closeout in Progress.

HOWSMAN ELEMENTARY SCHOOL ROOFING PROJECT

Roofing Consultant – Raba Kistner Contractor – Beldon Contract Amount – $692,986.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing

Project Closeout in Progress.

ANSON JONES MIDDLE SCHOOL ROOFING PROJECT

Roofing Consultant – Hollon + Cannon Contractor – Cram Roofing Contract Amount – $165,000.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing

Project Closeout in Progress.

LEWIS ELEMENTARY SCHOOL ROOFING PROJECT

Roofing Consultant – Austech Contractor – Empire Roofing Contract Amount – $190,151.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing

Project Closeout in Progress.

LINTON ELEMENTARY SCHOOL ROOFING PROJECT

Roofing Consultant – Raba Kistner Contractor – ATC Contractors, Inc. Contract Amount – $208,500.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing

Project Closeout in Progress.

MARY HULL ELEMENTARY SCHOOL ROOFING PROJECT

Roofing Consultant – Hollon + Cannon Contractor – Cram Roofing Contract Amount – $317,385.00 Construction Period – June 2016 – August 2016 Construction Status: 100% Complete Project Scope – Roof Replacement & Waterproofing

Project Closeout in Progress.

MAY ELEMENTARY SCHOOL ROOFING PROJECT

Roofing Consultant – Hollon + Cannon Contractor – Port Enterprise Contract Amount – $1,678,997.00 Construction Period – June 2016 – October 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing

Project closeout in progress.

TAFT HIGH SCHOOL ROOFING PROJECT

Roofing Consultant – Hollon + Cannon Contractor – Port Enterprise Contract Amount – $1,632,113.00 Construction Period – June 2016 – December 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing

Project closeout in progress.

VILLARREAL ELEMENTARY SCHOOL ROOFING PROJECT

Roofing Consultant – Austech Contractor – Samuel Dean Sheet Metal Inc. Construction Budget – $97,090.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing

Project Closeout in Progress.

2016 HAIL DAMAGE

ROOFING PROJECTS

BEARD ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT

Roofing Consultant – Hollon & Cannon Contractor – TBD Contract Amount – $566,480.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement & Restoration

Project in Design.

CARNAHAN ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT

Roofing Consultant – Hollon & Cannon Contractor – TBD Contract Amount – $2,125,200.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement

Project in Design.

CLARK HIGH SCHOOL HAIL DAMAGE ROOFING PROJECT

Roofing Consultant – Hollon & Cannon Contractor – TBD Contract Amount – $2,490,800.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement

Project in Design.

SOUTH TRANSPORTATION HAIL DAMAGE ROOFING PROJECT

Roofing Consultant – Raba Kistner Contractor – TBD Contract Amount – $261,920.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement

Project in Design.

STEVENSON MIDDLE SCHOOL HAIL DAMAGE ROOFING PROJECT

Roofing Consultant – Raba Kistner Contractor – TBD Contract Amount – $1,904,450.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement & Restoration

Project in Design.

CARLOS COON ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT

Roofing Consultant – Austech Contractor – TBD Contract Amount – $1,409,870.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement & Restoration

Project in Design.

ELROD ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT

Roofing Consultant – Austech Contractor – TBD Contract Amount – $784,880.00 Construction Period – June 2017– December 2017 Project Scope – Roof Restoration

Project in Design.

FERNANDEZ ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT

Roofing Consultant – Austech Contractor – TBD Contract Amount – $1,102,400.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement & Restoration

Project in Design.