Post on 07-Aug-2018
8/20/2019 Exe Summ Aryan Coal Eng
1/28
Rapid EIA Study for Proposed 1200 MW TPS Chapter 10
EXECUTIVE SUMMARY
FOR
PROPOSED 1200 MW (4 X 300 MW) THERMALPOWER PLANT
(SUBMITTED FOR PUBLIC HEARING)
AT VILLAGE: BHUMKA - MUSAMUDHI
TEHSIL: MAJHAULI, DISTRICT: SIDHI
STATE: MADHYA PRADESH
PROPOSED BY
ARYAN COAL BENEFICATIONS PVT. LTD.
June 2009
8/20/2019 Exe Summ Aryan Coal Eng
2/28
Rapid EIA Study for Proposed 1200 MW TPS Chapter 10
CHAPTER-10
EXECUTIVE SUMMARY
INTRODUCTION
Aryan Coal Benefications (P) Ltd who are the leader in the business of Coal
Washing and mining in India is planning to install 1200 MW (4 x 300 MW)
power generation units in Sidhi district, Madhya Pradesh state.
The proposal is covered under category A of the Environmental Impact
Assessment Notification 2006 and requires an Environmental Clearance from
Ministry of Environment and Forest.
The purpose of this Environmental Impact Assessment (EIA) study is to
provide information on the surroundings and the extent of environmental
impact likely to arise on account of the proposed power project program for
4 X 300 MW.
PROJECT LOCATION
The proposed power plant site is located at village Bhumka- Musamudhi,
Tehsil: Majhauli, District: Sidhi, Madhya Pradesh. The project site is accessible
by Kamchar – Musamuri – Parsi road. The nearest town Sidhi is located at 35
km away from project site in north direction. Latitude and Longitudes of four
corners of sites are given below
Corners of project site Latitude Longitude
S-E Corner 24O 7
’ 52' N 81
O 52
’ 7” E
S-W Corner 24O 8
’ 23' N 81
O 51
’ 7” E
N-W Corner- 24O 9’ 16' N 81O 51’ 30” E
N-E Corner 24O 8
’ 25' N 81
O 52
’ 34”E
The project will be developed on 950 acres of land. The proposed project
falls in Survey of India Topo Sheet No. 63 H/16.
PROJECT DESCRIPTION
The project involves Installation of stream of machinery and equipments to
generate 4X300 MW of power. During the establishment of the power plant
four numbers of boilers of 1008 TPH capacity will be installed with four
numbers of turbines of 300 MW capacity. Salient features of project are
given below:
8/20/2019 Exe Summ Aryan Coal Eng
3/28
Rapid EIA Study for Proposed 1200 MW TPS Chapter 10
SALIENT FEATURES FOR PROPOSED POWER PROJECT
Sr. No Particulars For Proposed Power Project
1. Production Capacity 4 X 300 MW
2. Coal Consumption 706 TPH
3. Water Consumption 4400 m3/hr
4. Waste water generation 920 m3/hr
5. Capacity of Boilers 1008 TPH x 4
6. Stack height 275 meters (2 Nos. Twin Flue)
7. Stack diameter at top 3.50 m (approx)
8. Stack emissions (SPM) 150 mg/Nm3
9. Total ash generation 318 TPH
10. Fly ash generation 254 TPH
11. Bottom ash generation 64 TPH
12. Project Cost 5045 crores
DETAILS OF THE PROCESSCoal from the gantry is crushed in a crusher and conveyed to coal storage
bunkers through a system of conveyor belts, crusher and vibrating screens
and is fed to the furnace. The coal burns inside the furnace so as to
maintain a furnace temperature of 880-900°C.
De-mineralised water from the storage tank is pumped to the boiler with the
aid of boiler feed pump. The boiler feed water through an economizer
enters the steam drum, mud drum and water walls where it is heated and
converted to saturated steam. The saturated steam is then heated to a
temperature of 540°C in the super heaters and carried to common steamheader. Hot air from the boiler furnace is drawn by an induced draft fan
through economizer, air heater and ESP and vented out through a chimney
of 275 meters height.
The steam from the main steam header at 150 Kg/cm2 and 540°C
temperature is taken to the turbo–generators. After rotating the turbine the
exhaust steam is condensed in the condensers and the condensed water is
pumped to the de-aerator and fed back to the boilers.
Project Cost: The total cost of project is 5045 Crores
RESOURCE REQUIREMENT
Water: The source of cooling water will be from the Banas which is about 40
km from the proposed site. The irrigation department of MP government has
granted permission for withdrawing of water for the proposed unit. A
8/20/2019 Exe Summ Aryan Coal Eng
4/28
Rapid EIA Study for Proposed 1200 MW TPS Chapter 10
dedicated intake system and pipeline shall be laid for this purpose. Water
requirement for 4 x 300 MW units is 4400 m3/hr.
Fuel: Indian coal of E / F Grade has been considered as main fuel. Coal shall
be transported from Northern Coalfields which are approximately 90 km
through rail –N- road mode of transportation.
Coal requirement for 4 x 300 MW units considering GCV of 3600 kcal/kg & 85
% PLF is as follows.
? Coal requirement per hour: 706 Tonnes
Start-up Fuel
The annual requirement of secondary fuel - LDO/HFO used for cold start up
with initial warm up is estimated to be around 12000 KL/annum. It shall be
stored in 2 tanks of 500 KL with considering 30 days storage.
Land Requirement
The land requirement for the project is as follows
Sr. No. Details Area inAcres
1 Land for power plant excluding ash disposal area. 125
2 Land for Green belt development at plant site. 300
3Land for coal storage yard, Handling and Marshalling Yard and
RoW for transport of materials/water200
4 Land for water reservoir 50
5 Land for Colony & Township and Roads 75
6 Land for Ash Dyke 200
7 Total land required for power plant 950
Infrastructure
At present no rail link is existing for the transportation of coal from mines to
site. The nearest railway siding is at Bhadhura, which is 4 km away.
Company is in the process of obtaining necessary clearance for laying a rail
line to site. Hence infrastructure requirement for transportation for initial
period is limited to roads. Apart from this, facilities for unloading, weighing
and storage will be established at plant site.
BASELINE ENVIRONMENTAL QUALITY
Methodology of the Study
Keeping in view the nature of activities, the process of power plant and
various environmental guidelines, the area covering a radial distance of 10
Km from the centre of the plant site was selected as study area for the
8/20/2019 Exe Summ Aryan Coal Eng
5/28
Rapid EIA Study for Proposed 1200 MW TPS Chapter 10
purpose of EIA study. To establish baseline status of air, water, noise, land,
biological and socio-economic environment in the study area, extensive field
studies were undertaken in and around power plant during the winter season
(December 2008 to February 2009)
Climate
The climate of the area is tropical monsoon type with three distinct seasons
as hot and dry summer/premonsoon (March-May), monsoon (June-October),
and winter (November - February). The climate of the area is dry during the
period of November to the beginning of June while during rainy season the
atmosphere is very humid. The average annual rainfall varies from 1000-
1200 mm, peaks in the months of July and August. May is the hottest month
with the mean daily maximum temperature being about 41°C. January is
generally the coolest month with mean daily maximum temperature at
about 9°C.
Air quality was monitored at eleven numbers of air-quality stations and it
was observed that the levels of SPM, RSPM, SO2 and NOx are well within the
standards prescribed by CPCB. Average values of pollutants concentrations
are given below
Sr. No. Sampling Location Name Average Concentrations of Pollutant in µg/m3
SPM RSPM SO2 NOx
1 Project Site 124 50 6 9
2 Amakholi 118 45 7 12
3 Parasi 123 48 7 104 Ser 134 55 8 11
5 Khajuriha 129 49 7 13
6 Nidhpuri 147 60 9 13
7 Bhumka 135 52 7 11
8 Nigri 137 53 10 14
9 Katai 133 50 6 9
10 Chhamrachh 131 47 8 12
11 Bajbal 113 35 8 12
Noise levels were monitored at ten locations within the study area. The day
time noise levels at all the sampling locations were observed in the range of
47 to 55 dB(A) except at Parasi (63 dB(A)). The night time noise levels werein the range of 40 to 49 dB(A). The levels were well within the permissible
limits for residential areas
Water samples of both surface (5Locations) and ground water (6Locations)
sources, were analyzed and compared with IS: 10500 limits. The water from
surface water source is found to be fit for drinking purposes.
8/20/2019 Exe Summ Aryan Coal Eng
6/28
Rapid EIA Study for Proposed 1200 MW TPS Chapter 10
Biological Environment: The study area mostly comprises of rural area. The
area includes few villages comprising of agricultural and barren land where
most of the vegetation is aggregated on agricultural bunds and forest area.
Common flora and faunal species are found in the study area. No national
park, Sanctuary, elephant/tiger reserve, migratory routes falls within the
study area
Socio Economic Environment: The study area comprises of 45 villages.
Total population of study area is 48,778 approximately. The nearest human
settlement is the village Kamchar, Musmuri and Bhumka. Literacy rate of
study area is 48.8%. The percentage of male and female population is
64.93% and 32.68% respectively. The scheduled Caste and Scheduled tribe
population is 9.30% and 33.36% of the total population respectively.
Economic conditions of people are moderate to poor. Most of the families
are living in kachha house. Toilet facilities are not available in most of the
houses in near by villages of project site.
Waste Water Disposal In the Power Plant: The waste water collected from
cooling tower, boilers, ash handling, domestic waste and D.M. plant to the
tune of 920 m3/hr is collected in neutralization-cum-settling tank and then
to the collection-cum-storage tank from where it is further used for fly ash
wetting, dust suppression in coal yard, as fire hydrant and for gardening.
Land Use Pattern: Location around the project sites studied is scarcely
populated except in some clusters and a part of the terrain is agricultural
land. Scattered villages like, Musamudi, Bhumka are located within the
project area. The land use pattern around 10 Km radial distance of the
power plant is given below
Sr. No. Land UseArea
(Hectares)Area in %
1. Forest 9425 30.0
2. Irrigated Land 5771 18.37
3. Un- irrigated land 8681 27.63
4. Cultivable waste land 2513 8.0
5. Not available for cultivation 5026 16.0
6 Total 31416 100
Soil Quality: The pH of soils was in the range of 6.7 to 7.5. The EC of soils
were in the range of 146 to 348 µS/cm. The CEC analysis of the soil samples
8/20/2019 Exe Summ Aryan Coal Eng
7/28
Rapid EIA Study for Proposed 1200 MW TPS Chapter 10
were in the range of 10.43 to 15.5 meq/100gm. N, P, K values at all the
locations shows that soils are moderate fertile.
Impact Assessment: "Environmental Impact" can be defined as any
alteration of environmental conditions or creation of a new set of
environmental conditions, adverse or beneficial, caused or induced by theaction or set of actions under consideration.
IDENTIFICATION OF IMPACTS
Air Environment:
The prediction of impact of stationary sources on the ambient air quality
has been calculated using Oak Ridge Air Quality Index (ORAQI). For
calculating the index, baseline data collected were analyzed and maximum
concentration was determined for three pollutants viz. SPM, SO2 and NOx.
The results on evaluation of Oak Ridge Air Quality Index (ORAQI) show thatthere is no impact on surrounding area.
Air quality modeling has been done to assess the air quality after project
implementation using ISCST3 model. GLC are predicted for SO2 and SPM.
Predicted concentrations at all AAQMS for SO2 and SPM are within the
stipulated AAQMS set by MOEF. Hence, ambient air quality will not be
degraded after the execution of proposed ultra mega power plant
Water Environment: The total water requirement of the Power Plant with
associated facilities will be 4400 m3/hr. The proposed power plant will meet
its process water requirement from Banas river. There will not be any
impact on surface or ground water characteristics due to power plant. The
surface and ground water characteristics of the samples monitored within
the study area are well within the permissible limits.
The treated effluents for discharge would meet the MINAS standards. The
quality of the treated wastewater will be suitable for horticulture/irrigation
Land Use: The proposed Power plant is not expected to change the land
use, soil characteristics and landscape in the region out side the powerplant area.
Noise Environment: The impact of noise generated from the proposed
project on its workers is expected to be insignificant except for the
employees working near compressors, FD fans, PA fans, ID fan, turbines and
Blower. For these sources the workers can be protected using earplugs and
8/20/2019 Exe Summ Aryan Coal Eng
8/28
Rapid EIA Study for Proposed 1200 MW TPS Chapter 10
arranging their duties in cycles. The impact of noise generated due to
proposed project is insignificant on the human settlements in the area.
Biological Environment: The impact on terrestrials and aquatic ecology due
to the proposed the power plant is insignificant. With the green belt
development around the plant as suggested in EMP the terrestrialenvironment of the region will be having positive improvement and will
further mitigate fugitive emissions as well as attenuated noise impact.
Ecology: As the study area does not provide habitation to any rare and
endangered species of flora and fauna, impact on ecology will be mainly due
to removal of green cover. This will be compensated, by the tree plantation
programs being implemented by the management of the Power plant.
Socio-Economics: The impact of the project on socio-economic status of the
region would be predominantly positive, if proper implementations of the
measures suggested in the EMP are made.
Resettlements and Rehabilitation: Musamudi and Bhumka village are comes
under project area of 950 acres. Approximately 66 families will be affected
due to proposed project. Detailed rehabilitation and resettlement plan for
the same has been prepared. Affected peoples will get adequate
compensation as per the RR policy and central government guidelines
Overall Impact: The overall impact of the power plant project is beneficialas the impact on the air, noise, water, land and biological environments are
not very significant and the socio-economic benefits are predominantly
positive.
ENVIRONMENTAL MONITORING PROGRAM
Sr. No.Environmental
attributeLocations Parameters Period and Frequency
1. Ambient AirQuality
plant field
• One at centre
• One Upwind &
• One downwind
Location
Criteria Pollutants:
SO 2, NOx, SPM, PM,
CO
24-hr aver age
sampli ng except for
CO, which wi ll be 8-hr
sampling. (Twice a
week)
2. Stack emission
monitoring
Stacks of operating
plant. SO 2, NOx, SPM, CO
Dail y duri ng
funct i onal phase
3. Drinking water
(potablity
? Dug well wells
core zone
Drinking water
parameters as per
Tw ice in a year dur ing
Functi onal pha se
8/20/2019 Exe Summ Aryan Coal Eng
9/28
Rapid EIA Study for Proposed 1200 MW TPS Chapter 10
Sr. No.Environmental
attributeLocations Parameters Period and Frequency
testing) ? Drinking water
tank, plant
IS 10500.
4. Ambient NoiseMain gate of Site
Nearest village
dB(A) levels
? SPL (dBA)
? Leq (Night +Day)
Leq (day) and Leq (Night) should be
monitor ed once in a
mont h.
5.Treated Effluent
qualityETP of Power Plant
Parameters for
horticulture use -
BOD, pH, S.S,
pathogens
Every month duri ng
funct ional Phase
6. Soil quality Greenbelt area
Organic matter, C,
H, N, Alkalinity,
Acidity, heavy
metals and tracemetal.
Pre -monsoon and
po st-monsoon dur ing
funct ional phase.
7.Ground water
quality4 wells
Drinking water
parameters as per
IS 10500
Once every y ear i n
Apr i l
8
Occuptional
exposure
monitoring
Coal handling
plant, feed cycle
plant, main plant
area
Lung test,
Audiometer test.Once in a six mont h
9 Meteorology
Plant site at
suitable location
Wind speed,
direction, Solar
radiation, relative
humidity,
Cont i nuous on hourly
basis
RISK ASSESSMENT & DISASTER MANAGEMENT PLAN: The risk assessment
helps one in taking care of probable hazards on account of faulty /
defective operations of various plants, machinery, equipment, etc. Such risk
assessment proves helpful in foreseeing the risks involved in various
operations to prevent the likely accidents.
As far as the power plant is concerned, it involves risk both in constructional
phase and operational phase of the project Hazardous Fuel oils and
Chemical Storage Facilities: The power plant operation involves extensive
use of various lubricants and limited use of fuel oils. The fuel oils usually
used are light diesel oil (LDO), furnace oil (FO), low sulphur heavy stock oil
(LSHS) etc. Necessary risk analysis shall very well be done and the storage
facilities shall be suitably developed. Storages of acids and alkalies viz.
hydrochloric acid, sulphuric acid, caustic soda, etc. should be designed
8/20/2019 Exe Summ Aryan Coal Eng
10/28
Rapid EIA Study for Proposed 1200 MW TPS Chapter 10
properly. Various gases used in power plant should be stored in the suitably
designed cylinders and the cylinders are placed in the proper positions.
Occupational Safety: Since the process do not call for release of any
inflammable or toxic substances, it is considered desirable to provide a safe
working environment to the operational staff. Suitable casings to all the
moving parts will be provided and perfect encasing to the electrical
installation will be made to prevent any electrical accident.
Fire protection System: The power plants which are operating on various
kinds of fossil-fuels such as coal, oil, gas, etc. are prone to fires. The fires
are of various kinds and these need to be quenched by way of resorting to
various protection systems. The plant area shall be provided with smoke
detection system which could detect any kind of smoke likely to arise on
account of fires.
Protective equipments for working personnel: In order to take care of the
working personnel, they would be provided with various protective devices,
which shall broadly comprise respirators (face pieces, walls, sweat traps,
head bands, filters, etc.), goggles, rubber gloves, gum shoes, etc
DISASTER MANAGEMENT PLAN: Disaster is an undesirable occurrence of
events of such magnitude and nature, which adversely affects production
and/or causes damage to environment. Risk assessment forms an integral
part of disaster management and any realistic “Disaster Management Plan”
could only occur through a scientific risk assessment studies and involves 1)Requirement of fire extinguisher at all the fire prone sides. 2) Mock drill
should be carried out periodically for emergency preparedness. 3) Effective
communication systems at all the parts of the plant should be maintained.
Risk Analysis: Risk analysis consists of two parts viz. i) Risk identification
and ii) Risk assessment.
Risk Assessment: Risk assessment techniques are:
1) Hazard and Operatability Study (HAZOP) 2) Fault Tree Analysis (FTA) 3)Monte Carlo Simulation 4) Safety Audits 5) Safety Indices 6) Above risk
assessment techniques are discussed in the subsequent paragraphs.
Hazard and Operatability Study (HAZOP) study involves identification of
Hazards or operatability problem of the process and envisages possible
deviations from normal operating conditions.
8/20/2019 Exe Summ Aryan Coal Eng
11/28
Rapid EIA Study for Proposed 1200 MW TPS Chapter 10
PROCEDURE FOR FIRE / GAS LEAKAGE CONTROL: When fire on account of
gas leakage is noticed, it is desirable to take following measures:
a) Break the nearest fire-glass.
b) Immediately inform to concerned plant control room.
c) Follow the instructions of control room.
d) Act to control the incident as per the instructions.
e) Reach to the assembly point, located at right angle to be wind
direction.
ENVIRONMENTAL MANAGEMENT PLAN: The proposed power plant shall
have two significant phases. The first phase shall be the constructional
phase, and the second phase i.e. operational phase,
EMP for Constructional phase: The constructional phase comprises various
activities which are rather transient in nature and prevail for shorter
duration. The following measures are considered desirable:-
Necessary facilities such as sanitation, water supply, rest rooms, etc. shall
be provided for the construction staff.
The site excavation, blasting, movement of earthen materials, etc. shall be
planned and executed properly to avoid any nuisance / hazard.
The site shall be provided with suitable trenches for draining of the rain
water and construction water effectively. The electrical equipments and
instruments shall be properly and carefully handled. The fuels such as
petrol, diesel, the lubricating oils, various gases, paints, varnishes, etc.
shall be properly stored as per the standard practices.
EMP for Operational phase: Various standard practices have been evolved
to manage the power plant operations efficiently to cause least possible
concern to the environment.
Coal Handling Scheme: In a typical coal based power plant, the stack
emissions are obviously expected to comprise SPM, SO2, NOX. Similarly, the
fugitive emissions on account of coal dust and ash particles are verycommon and rather unavoidable. However, in present power plant
practices, the coal dust emissions are taken care of by way of providing dust
suppressing equipments and sprinkling of water everyday.
Ash handling system: The percentage of ash in coal has a bearing on the
quantum of ash produced. Fly ash is collected in the closed hoppers; the
total quantity of fly ash generated will be about 318 TPH. Fly ash will be
8/20/2019 Exe Summ Aryan Coal Eng
12/28
Rapid EIA Study for Proposed 1200 MW TPS Chapter 10
used for the manufacture of cement and will be transported with the help
of bulkers.
Flue gases: The plant shall be provided with electrostatic precipitators
having high efficiency (above 99.98%) for collection of the fly ash that would
be produced from the process of coal combustion in boiler furnace.
Water Pollution: During operational phase, the likely sources of waterpollution and the measures to be taken for their managements are describedhereunder
Effluents from water treatment plant: The effluents from cation/anion
resins are combined with the filter back wash in the neutralizing pit and by
way of giving additional treatment as may be necessary, the effluents are
treated to make them hazard free.
Various drains in the plant area: The storm water (rain water) collectedfrom the open areas is let through the open channels and conveyed to the
storm water drain which in turn lets out the water into a suitable low lying
area. For this purpose, suitable slope shall be provided to avoid any type of
flooding in the power plant. The roof top rainwater harvesting will be done
to recharge the underground water.
Noise Pollution: The power plant process involves various machineries and
equipments and while in operation, these machineries tend to produce
noise, which is rather unavoidable. Efforts are always made to maintain
minimal possible noise levels on all these accounts. The endeavours would
be aimed at maintaining the noise levels below 85-90 dB(A) or even lesser at
a distance of about 1.5 meters from the equipment, using stable foundation
for machines and appropriate noise absorbing sheets in control cabins.
Sewage disposal: The disposal of the domestic sewage from the plant would
be through the closed drainage system sewage treatment plant.
Biological Environmental Management Plan: Efforts shall be made to avert
any adverse impact on flora and fauna in the area of proposed plant or at
least to minimise the impact to the possible extent. To this effect, Greenbelts (30 meter width) shall be suitably developed around the boundary of
the power plant with selected locally grown plant species.
Socio-economic Environment: In order to provide employment to the local
people, efforts shall be made to employ the work force from the
surrounding area. Various social activities to be undertaken by the project
shall be confirming to the local needs and these activities shall be planned
8/20/2019 Exe Summ Aryan Coal Eng
13/28
Rapid EIA Study for Proposed 1200 MW TPS Chapter 10
in coordination with local representatives of the public, government
officials.
IMPACTS ON LAND ENVIRONMENT: To minimize disruption of soil and for
conservation of topsoil, the topsoil should be taken out and stacked
separately and stockpile it. Topsoil should be utilized for landscapingactivity. Other measures, which would be followed to prevent soil erosion
and contamination include: 1) Maximize use of organic fertilizer for
landscaping and green belt development. 2) Selection of the plant species
should be on the basis of their adaptability to the existing geographical
conditions and the vegetation composition of the region. 3) The species
should be fast growing and providing optimum penetrability. 4) The species
should form a dense canopy. 5) Trees with high foliage density, leaves with
larger leaf area and hairy on both the surfaces.
8/20/2019 Exe Summ Aryan Coal Eng
14/28
Rapid EIA Study for Proposed 1200 MW TPS Annexures
ANNEXURE I: COAL HANDLING SCHEME
8/20/2019 Exe Summ Aryan Coal Eng
15/28
Rapid EIA Study for Proposed 1200 MW TPS Annexures
ANNEXURE II: BOTTOM ASH HANDLING
8/20/2019 Exe Summ Aryan Coal Eng
16/28
Rapid EIA Study for Proposed 1200 MW TPS Annexures
ANNEXURE III: FLY ASH HANDLING
8/20/2019 Exe Summ Aryan Coal Eng
17/28
Rapid EIA Study for Proposed 1200 MW TPS Annexures
ANNEXURE IV: DM PLANT
8/20/2019 Exe Summ Aryan Coal Eng
18/28
Rapid EIA Study for proposed 1200 MW TPS Annexures
ANNEXURE V: AMBIENT AIR QUALITY MONITORING RESULTS [TOR POINTNO. 12]
Location: Project Site
Date SPM (µg/m3) RPM(µg/m 3)
SO2(µg/m 3)
NOx (µg/m3)
Hg(µg/m3)
Ozone(µg/m3)
24 hrs. Concentrations
1.12.2008 97 36 5 5 BDL BDL
2.12.2008 120 43 6 11 BDL BDL
8.12.2008 105 46 4 9 BDL BDL
9.12.2008 119 55 5 7 BDL BDL
15.12.2008 123 52 4 9 BDL BDL
16.12.2008 133 58 6 7 BDL BDL
22.12.2008 119 61 5 10 BDL BDL
23.12.2008 128 63 6 8 BDL BDL
29.12.2008 131 66 5 6 BDL BDL
30.12.2008 137 46 6 9 BDL BDL
5.1.2009 138 48 6 7 BDL BDL
6.1.2009 120 51 4 6 BDL BDL
12.1.2009 135 55 6 11 BDL BDL
13.1.2009 124 48 4 8 BDL BDL
19.1.2009 116 40 6 12 BDL BDL
20.1.2009 131 49 8 11 BDL BDL
26.1.2009 135 51 6 8 BDL BDL
27.1.2009 123 57 5 10 BDL BDL
3.2.2009 119 57 6 5 BDL BDL
4.2.2009 104 43 7 11 BDL BDL
10.2.2009 136 50 6 8 BDL BDL
11.2.2009 137 45 7 10 BDL BDL
17.2.2009 117 54 5 8 BDL BDL
18.2.2009 122 42 6 8 BDL BDL
24.2.2009 126 42 5 8 BDL BDL
25.2.2009 132 43 5 9 BDL BDL
Maximum 138 66 8 12
Minimum 97 36 4 5
Average 124 50 6 9
98
th
Percentile 138 65 8 12
8/20/2019 Exe Summ Aryan Coal Eng
19/28
Rapid EIA Study for proposed 1200 MW TPS Annexures
ANNEXURE II (CONTD…)
Location: Amakholi (A2)
Date SPM (µg/m3) RPM(µg/m 3)
SO2(µg/m 3)
NOx (µg/m3)
Hg(µg/m3)
Ozone(µg/m3)
24 hrs. Concentrations
1.12.2008 120 39 7 10 BDL BDL
2.12.2008 127 46 6 12 BDL BDL
8.12.2008 124 57 8 11 BDL BDL
9.12.2008 102 56 9 12 BDL BDL
15.12.2008 130 54 7 8 BDL BDL
16.12.2008 106 55 6 13 BDL BDL
22.12.2008 140 60 7 13 BDL BDL
23.12.2008 113 60 10 9 BDL BDL
29.12.2008 105 59 7 13 BDL BDL
30.12.2008 116 53 8 13 BDL BDL
5.1.2009 115 47 5 14 BDL BDL
6.1.2009 122 48 6 14 BDL BDL
12.1.2009 125 39 8 12 BDL BDL
13.1.2009 102 48 10 14 BDL BDL
19.1.2009 133 56 8 15 BDL BDL
20.1.2009 112 45 6 13 BDL BDL
26.1.2009 115 47 5 10 BDL BDL
27.1.2009 126 33 5 7 BDL BDL
3.2.2009 126 28 6 12 BDL BDL
4.2.2009 106 42 7 13 BDL BDL
10.2.2009131 39 6 9
BDL BDL
11.2.2009 115 29 8 12 BDL BDL
17.2.2009 106 28 6 13 BDL BDL
18.2.2009 109 34 6 14 BDL BDL
24.2.2009 126 38 7 12 BDL BDL
25.2.2009 122 34 6 10 BDL BDL
Maximum 140 60 10 15
Minimum 102 28 5 7
Average 118 45 7 12
98th Percentile 137 60 10 15
8/20/2019 Exe Summ Aryan Coal Eng
20/28
Rapid EIA Study for proposed 1200 MW TPS Annexures
Location: Parasi (A3)
Date SPM (µg/m3) RPM(µg/m 3)
SO2(µg/m 3)
NOx (µg/m3)
Hg(µg/m3)
Ozone(µg/m3)
24 hrs. Concentrations
1.12.2008 123 35 5 10 BDL BDL
2.12.2008 116 43 7 9 BDL BDL8.12.2008 101 46 7 12 BDL BDL
9.12.2008 139 55 8 8 BDL BDL
15.12.2008 134 52 4 7 BDL BDL
16.12.2008 114 57 5 13 BDL BDL
22.12.2008 119 60 5 11 BDL BDL
23.12.2008 123 49 5 12 BDL BDL
29.12.2008 129 54 6 10 BDL BDL
30.12.2008 105 46 6 8 BDL BDL
5.1.2009 132 47 8 9 BDL BDL
6.1.2009 123 50 4 6 BDL BDL
12.1.2009 134 55 6 6 BDL BDL13.1.2009 143 48 9 5 BDL BDL
19.1.2009 110 40 8 10 BDL BDL
20.1.2009 143 49 6 13 BDL BDL
26.1.2009 108 51 9 12 BDL BDL
27.1.2009 118 57 10 10 BDL BDL
3.2.2009 118 57 7 9 BDL BDL
4.2.2009 104 43 5 10 BDL BDL
10.2.2009 136 30 8 9 BDL BDL
11.2.2009 137 45 8 8 BDL BDL
17.2.2009 132 45 6 9 BDL BDL
18.2.2009 121 42 5 11 BDL BDL
24.2.2009 126 41 7 11 BDL BDL
25.2.2009 124 42 5 12 BDL BDL
Maximum 143 60 10 13
Minimum 101 30 4 5
Average 123 48 7 10
98th Percentile 143 59 10 13
8/20/2019 Exe Summ Aryan Coal Eng
21/28
Rapid EIA Study for proposed 1200 MW TPS Annexures
Location: Ser (A4)
Date SPM (µg/m3) RPM(µg/m 3)
SO2(µg/m 3)
NOx (µg/m3)
Hg(µg/m3)
Ozone(µg/m3)
24 hrs. Concentrations
1.12.2008 139 46 8 9 BDL BDL
2.12.2008 132 51 6 12 BDL BDL8.12.2008 141 57 8 11 BDL BDL
9.12.2008 144 60 9 11 BDL BDL
15.12.2008 132 61 6 10 BDL BDL
16.12.2008 147 65 5 15 BDL BDL
22.12.2008 121 67 8 13 BDL BDL
23.12.2008 114 65 9 9 BDL BDL
29.12.2008 94 72 10 7 BDL BDL
30.12.2008 110 57 9 7 BDL BDL
5.1.2009 133 64 8 13 BDL BDL
6.1.2009 141 57 7 6 BDL BDL
12.1.2009 147 60 10 13 BDL BDL13.1.2009 148 58 5 8 BDL BDL
19.1.2009 148 69 6 14 BDL BDL
20.1.2009 152 58 10 9 BDL BDL
26.1.2009 110 63 10 11 BDL BDL
27.1.2009 151 59 9 12 BDL BDL
3.2.2009 141 54 8 12 BDL BDL
4.2.2009 145 41 9 16 BDL BDL
10.2.2009 130 46 11 15 BDL BDL
11.2.2009 139 42 9 14 BDL BDL
17.2.2009 125 38 9 14 BDL BDL
18.2.2009 138 39 8 10 BDL BDL
24.2.2009 130 38 8 13 BDL BDL
25.2.2009 139 43 8 12 BDL BDL
Maximum 152 72 11 16
Minimum 94 38 5 6
Average 134 55 8 11
98th Percentile 152 71 10 15
8/20/2019 Exe Summ Aryan Coal Eng
22/28
Rapid EIA Study for proposed 1200 MW TPS Annexures
Location: Khajuriha (A5)
Date SPM (µg/m3) RPM(µg/m 3)
SO2(µg/m 3)
NOx (µg/m3)
Hg(µg/m3)
Ozone(µg/m3)
24 hrs.Concentrations
1.12.2008 131 42 7 11 BDL BDL
2.12.2008 139 50 6 13 BDL BDL8.12.2008 136 63 8 12 BDL BDL
9.12.2008 112 61 9 14 BDL BDL
15.12.2008 142 59 8 9 BDL BDL
16.12.2008 116 60 6 14 BDL BDL
22.12.2008 147 65 8 14 BDL BDL
23.12.2008 123 66 9 10 BDL BDL
29.12.2008 115 64 8 14 BDL BDL
30.12.2008 127 58 9 14 BDL BDL
5.1.2009 126 52 6 15 BDL BDL
6.1.2009 134 53 7 15 BDL BDL
12.1.2009 136 42 9 13 BDL BDL13.1.2009 111 53 9 16 BDL BDL
19.1.2009 145 61 8 16 BDL BDL
20.1.2009 122 49 6 14 BDL BDL
26.1.2009 125 52 5 11 BDL BDL
27.1.2009 137 37 5 8 BDL BDL
3.2.2009 138 31 6 14 BDL BDL
4.2.2009 116 46 8 14 BDL BDL
10.2.2009 144 43 7 10 BDL BDL
11.2.2009 126 31 9 13 BDL BDL
17.2.2009 116 31 7 14 BDL BDL
18.2.2009 119 37 6 15 BDL BDL
24.2.2009 138 41 8 13 BDL BDL
25.2.2009 134 37 6 11 BDL BDL
Maximum 147 66 9 16
Minimum 111 31 5 8
Average 129 49 7 13
98th Percentile 146 65 9 16
8/20/2019 Exe Summ Aryan Coal Eng
23/28
Rapid EIA Study for proposed 1200 MW TPS Annexures
Location: Nidhpuri (A6)
Date SPM (µg/m3) RPM(µg/m 3)
SO2(µg/m 3)
NOx (µg/m3)
Hg(µg/m3)
Ozone(µg/m3)
24 hrs. Concentrations
1.12.2008 152 50 9 10 BDL BDL
2.12.2008 144 56 9 13 BDL BDL8.12.2008 154 62 9 12 BDL BDL
9.12.2008 157 66 10 13 BDL BDL
15.12.2008 144 66 7 11 BDL BDL
16.12.2008 160 71 6 16 BDL BDL
22.12.2008 133 74 9 14 BDL BDL
23.12.2008 125 71 10 10 BDL BDL
29.12.2008 103 79 7 8 BDL BDL
30.12.2008 120 62 10 8 BDL BDL
5.1.2009 145 70 9 14 BDL BDL
6.1.2009 154 62 8 7 BDL BDL
12.1.2009 161 66 10 15 BDL BDL13.1.2009 162 63 6 9 BDL BDL
19.1.2009 162 75 7 15 BDL BDL
20.1.2009 166 63 9 10 BDL BDL
26.1.2009 120 68 8 12 BDL BDL
27.1.2009 165 64 9 14 BDL BDL
3.2.2009 154 59 8 13 BDL BDL
4.2.2009 158 45 10 17 BDL BDL
10.2.2009 142 50 10 16 BDL BDL
11.2.2009 152 45 9 16 BDL BDL
17.2.2009 136 42 10 15 BDL BDL
18.2.2009 151 43 9 11 BDL BDL
24.2.2009 142 41 8 14 BDL BDL
25.2.2009 152 48 9 13 BDL BDL
Maximum 166 79 10 17
Minimum 103 41 6 7
Average 147 60 9 13
98th Percentile 166 77 10 17
8/20/2019 Exe Summ Aryan Coal Eng
24/28
Rapid EIA Study for proposed 1200 MW TPS Annexures
Location: Bhumka (A7)
Date SPM (µg/m3) RPM(µg/m 3)
SO2(µg/m 3)
NOx (µg/m3)
Hg(µg/m3)
Ozone(µg/m3)
24 hrs. Concentrations
1.12.2008 132 39 5 11 BDL BDL
2.12.2008 126 47 8 10 BDL BDL8.12.2008 110 50 8 13 BDL BDL
9.12.2008 152 60 9 9 BDL BDL
15.12.2008 147 57 4 8 BDL BDL
16.12.2008 125 63 6 14 BDL BDL
22.12.2008 130 66 5 12 BDL BDL
23.12.2008 135 54 6 13 BDL BDL
29.12.2008 141 59 7 11 BDL BDL
30.12.2008 115 50 7 9 BDL BDL
5.1.2009 144 52 9 10 BDL BDL
6.1.2009 134 55 4 7 BDL BDL
12.1.2009 146 60 7 7 BDL BDL13.1.2009 156 52 6 5 BDL BDL
19.1.2009 120 43 9 11 BDL BDL
20.1.2009 156 54 7 14 BDL BDL
26.1.2009 118 56 8 13 BDL BDL
27.1.2009 129 62 9 11 BDL BDL
3.2.2009 129 62 8 10 BDL BDL
4.2.2009 113 47 6 11 BDL BDL
10.2.2009 148 33 9 10 BDL BDL
11.2.2009 150 49 9 9 BDL BDL
17.2.2009 144 49 7 10 BDL BDL
18.2.2009 133 46 6 12 BDL BDL
24.2.2009 138 45 8 12 BDL BDL
25.2.2009 136 46 6 13 BDL BDL
Maximum 156 66 9 14
Minimum 110 33 4 5
Average 135 52 7 11
98th Percentile 156 64 9 14
8/20/2019 Exe Summ Aryan Coal Eng
25/28
Rapid EIA Study for proposed 1200 MW TPS Annexures
Location: Nigri (A8)
Date SPM (µg/m3) RPM(µg/m 3)
SO2(µg/m 3)
NOx (µg/m3)
Hg(µg/m3)
Ozone(µg/m3)
24 hrs concentrations
1.12.2008 144 58 9 12 BDL BDL
2.12.2008 142 52 9 12 BDL BDL8.12.2008 155 58 10 13 BDL BDL
9.12.2008 144 61 9 14 BDL BDL
15.12.2008 146 62 8 13 BDL BDL
16.12.2008 121 64 9 14 BDL BDL
22.12.2008 151 66 11 12 BDL BDL
23.12.2008 149 62 11 13 BDL BDL
29.12.2008 149 70 12 15 BDL BDL
30.12.2008 144 62 11 14 BDL BDL
5.1.2009 149 66 12 15 BDL BDL
6.1.2009 132 54 10 16 BDL BDL
12.1.2009 136 64 10 15 BDL BDL13.1.2009 161 60 12 13 BDL BDL
19.1.2009 136 54 10 17 BDL BDL
20.1.2009 149 54 11 15 BDL BDL
26.1.2009 145 58 11 16 BDL BDL
27.1.2009 137 41 9 14 BDL BDL
3.2.2009 135 36 9 13 BDL BDL
4.2.2009 125 44 10 14 BDL BDL
10.2.2009 122 36 8 12 BDL BDL
11.2.2009 135 48 9 13 BDL BDL
17.2.2009 142 50 10 15 BDL BDL
18.2.2009 103 28 8 11 BDL BDL
24.2.2009 108 29 9 13 BDL BDL
25.2.2009 95 51 8 11 BDL BDL
Maximum 161 70 12 17
Minimum 95 28 8 11
Average 137 53 10 14
98th Percentile 158 68 12 17
8/20/2019 Exe Summ Aryan Coal Eng
26/28
Rapid EIA Study for proposed 1200 MW TPS Annexures
Location: Katai (A9)
Date SPM (µg/m3) RPM(µg/m 3)
SO2(µg/m 3)
NOx (µg/m3)
Hg(µg/m3)
Ozone(µg/m3)
24 hrs Concentrations
1.12.2008 105 35 5 6 BDL BDL
2.12.2008 128 43 6 12 BDL BDL8.12.2008 139 46 5 10 BDL BDL
9.12.2008 127 56 6 8 BDL BDL
15.12.2008 131 53 4 10 BDL BDL
16.12.2008 142 59 6 8 BDL BDL
22.12.2008 127 62 7 11 BDL BDL
23.12.2008 136 64 7 9 BDL BDL
29.12.2008 140 68 5 7 BDL BDL
30.12.2008 146 46 7 10 BDL BDL
5.1.2009 148 48 7 8 BDL BDL
6.1.2009 127 51 4 7 BDL BDL
12.1.2009 144 56 7 12 BDL BDL13.1.2009 132 48 4 9 BDL BDL
19.1.2009 124 39 7 13 BDL BDL
20.1.2009 140 50 9 12 BDL BDL
26.1.2009 144 52 7 9 BDL BDL
27.1.2009 132 58 6 11 BDL BDL
3.2.2009 126 58 6 6 BDL BDL
4.2.2009 110 43 8 12 BDL BDL
10.2.2009 145 50 6 9 BDL BDL
11.2.2009 147 45 7 11 BDL BDL
17.2.2009 125 55 6 8 BDL BDL
18.2.2009 130 42 7 9 BDL BDL
24.2.2009 135 41 5 9 BDL BDL
25.2.2009 141 42 5 10 BDL BDL
Maximum 148 68 9 13
Minimum 105 35 4 6
Average 133 50 6 9
98th Percentile 147 66 9 13
8/20/2019 Exe Summ Aryan Coal Eng
27/28
Rapid EIA Study for proposed 1200 MW TPS Annexures
Location: Chhamrachh (A10)
Date SPM (µg/m3) RPM(µg/m 3)
SO2(µg/m 3)
NOx (µg/m3)
Hg(µg/m3)
Ozone(µg/m3)
24 hrs Concentrations
1.12.2008 119 45 8 13 BDL BDL
2.12.2008 146 52 9 9 BDL BDL8.12.2008 121 53 8 14 BDL BDL
9.12.2008 150 51 7 7 BDL BDL
15.12.2008 155 41 6 11 BDL BDL
16.12.2008 146 45 9 13 BDL BDL
22.12.2008 130 54 6 6 BDL BDL
23.12.2008 121 56 5 12 BDL BDL
29.12.2008 133 55 4 5 BDL BDL
30.12.2008 129 56 6 13 BDL BDL
5.1.2009 126 57 7 13 BDL BDL
6.1.2009 133 64 6 10 BDL BDL
12.1.2009 138 54 8 15 BDL BDL13.1.2009 126 51 9 11 BDL BDL
19.1.2009 135 54 8 14 BDL BDL
20.1.2009 136 47 7 14 BDL BDL
26.1.2009 135 47 8 14 BDL BDL
27.1.2009 122 37 9 13 BDL BDL
3.2.2009 115 34 8 8 BDL BDL
4.2.2009 136 40 10 16 BDL BDL
10.2.2009 127 36 9 15 BDL BDL
11.2.2009 126 37 9 9 BDL BDL
17.2.2009 127 37 8 12 BDL BDL
18.2.2009 133 44 8 7 BDL BDL
24.2.2009 134 39 9 13 BDL BDL
25.2.2009 117 33 8 12 BDL BDL
Maximum 155 64 10 16
Minimum 115 33 4 5
Average 131 47 8 12
98th Percentile 153 61 9 15
8/20/2019 Exe Summ Aryan Coal Eng
28/28
Rapid EIA Study for proposed 1200 MW TPS Annexures
Location: Bajbal (A11)
Date SPM (µg/m3) RPM(µg/m 3)
SO2(µg/m 3)
NOx (µg/m3)
Hg(µg/m3)
Ozone(µg/m3)
24 hrs Concentrations
1.12.2008 110 48 7 9 BDL BDL
2.12.2008 115 46 7 11 BDL BDL8.12.2008 122 45 8 13 BDL BDL
9.12.2008 114 46 9 13 BDL BDL
15.12.2008 99 50 8 11 BDL BDL
16.12.2008 107 48 6 13 BDL BDL
22.12.2008 90 37 10 12 BDL BDL
23.12.2008 94 32 9 13 BDL BDL
29.12.2008 76 35 5 10 BDL BDL
30.12.2008 81 33 8 11 BDL BDL
5.1.2009 104 36 6 13 BDL BDL
6.1.2009 95 44 11 14 BDL BDL
12.1.2009 90 42 9 13 BDL BDL13.1.2009 109 33 8 14 BDL BDL
19.1.2009 112 29 9 12 BDL BDL
20.1.2009 119 39 8 11 BDL BDL
26.1.2009 107 29 7 12 BDL BDL
27.1.2009 111 32 6 10 BDL BDL
3.2.2009 116 32 7 12 BDL BDL
4.2.2009 125 32 8 12 BDL BDL
10.2.2009 128 29 8 12 BDL BDL
11.2.2009 118 29 9 13 BDL BDL
17.2.2009 126 29 8 13 BDL BDL
18.2.2009 131 31 10 14 BDL BDL
24.2.2009 133 29 11 11 BDL BDL
25.2.2009 128 32 8 11 BDL BDL
Maximum 133 50 11 14
Minimum 76 29 5 9
Average 110 36 8 12
98th Percentile 130 49 10 14