What is tacheometry??

Easy and cheap method of collecting much topographic data.

Tachymetry (or tacheometry) also called “stadia surveying” in countries like England and the United States

means “fast measurement”; rapid and efficient way of indirectly measuring distances and elevation differences

ERT 247 GEOMATICS ENGINEERING

Figure 1 shows the set-up of a tachymetric measurement.

ERT 247 GEOMATICS ENGINEERING

Tacheometry

Concept Determine distances indirectly using triangle

geometry Methods

Stadia Establish constant angle and measure length of

opposite side Length increases with distance from angle vertex

ERT 247 GEOMATICS ENGINEERING

Stadia System

The theodolite/auto level is directed at the level staff and the distance is measured by reading the top and bottom stadia hairs on the telescope view.

ERT 247 GEOMATICS ENGINEERING

Stadia System

In the first type the distance between the two. There are two types of instruments used for stadia surveying.

Stadia hairs in the theodolite telescope is fixed.

In the second type of equipment the distance between the stadia hairs is variable, being measured by means of a micrometer.

The most common method used involves the fixed hair tacheometer, or theodolite.

ERT 247 GEOMATICS ENGINEERING

Electronic Tacheometry: Uses a total station which contains an EDM,

able to read distance by reflecting off a prism. Subtense Bar system: An accurate theodolite, reading to 1" of arc,

is directed at a staff, two pointings being made and the small subtended angle measured

ERT 247 GEOMATICS ENGINEERING

Equipment

Measurement can be taken with theodolites, transits and levels and stadia rods

While in the past, distances were measured by the “surveyor’s chain”, this can be done easier and faster using a telescope equipped with stadia hairlines in combination with a stadia rod (auto level and staff)

ERT 247 GEOMATICS ENGINEERING

Tacheometry: Stadia

L1

d1

L2

d2

)tan(0.5

0.5Ld 1

1 α

)tan(0.5

0.5Ld 2

2 α

ERT 247 GEOMATICS ENGINEERING

Stadia Readings

Middle Hair

Upper Hair

Lower Hair

ERT 247 GEOMATICS ENGINEERING

Stadia Principles

A,B rod intercepts a, b stadia hairs S = rod intercept F = principal focus of

objective lens

C d

D

i

c f

• C = stadia constant• K = f/i = stadia interval factor• d = distance from focal point

to rod• D = distance from instrument

center to rod

b

a a'

b'

F

B

A

S

• f = focal length• i = stadia hair spacing • c = distance from instrument

center to objective lens center

ERT 247 GEOMATICS ENGINEERING

Stadia Equations

Horizontal sights

100SH

0C100,K usually

CKSH

0V

α100ScosHCcosααKScosH2

2

sin2α100SVCsinαsin2αKSV

21

21

• Inclined sights

i

S

f

d

• From similar triangles

CKSD KSSi

fd

ERT 247 GEOMATICS ENGINEERING

Tacheometry: Subtense

L1

d1

L2

d2

)tan(0.5

0.5Ld

11 α

)tan(0.5

0.5Ld

22 α

ERT 247 GEOMATICS ENGINEERING

Subtense Equation Derive equation for computing distance by subtense

L

)2δ0.5Lcot()2δtan(

0.5Ld

• What value would you choose for L?

d

ERT 247 GEOMATICS ENGINEERING

Centre of instrument

o

Object lensb

x

a

staff

c

f

U V

D

A

X

B

FS i

The notes below shows the calculation of the distance (D) from the centre of the fixed hair tacheometer to a target.

ERT 247 GEOMATICS ENGINEERING

From the diagram, triangles AOB , a O b are similar

ab

AB

V

U

Ox

OX

Also if OF = f = focal length of object lens

Then + = (lens equation) and multiply both sides by (U f)

U = f + f

U = f + f

1

U

1

V

1

f

UV

AB

ab

ERT 247 GEOMATICS ENGINEERING

AB is obtained by subtracting the reading given on the staff by the lower stadia hair from the top one and is usually denoted by s (staff intercept), and ab the distance apart of the stadia lines is denoted by i.

This value i is fixed, known and constant for a particular instrument.

U = s + f

D = s + ( f + c )

f

i

f

i

ERT 247 GEOMATICS ENGINEERING

The reduction of this formula would be simplified considerably if the term (f / i) is made some convenient figure, and if the term (f + c) can be made to vanish.

D = C.S + k

ERT 247 GEOMATICS ENGINEERING

Constant determination

In practice, the multiplicative constant generally equals 100 and the additive constant equals zero.

This is certainly the case with modern instruments by may not always be so with older Theodolites.

The values are usually given by the makers but this is not always the case.

It is sometimes necessary to measure them in an old or unfamiliar instrument.

The simplest way, both for external and internal focusing instruments, is to regard the basic formula as being a linear one of the form:

D = C.S + k

ERT 247 GEOMATICS ENGINEERING

On a fairly level site chain out a line 100 to 120m long, setting pegs at 25 to 30 meter intervals.

Set at up at one end and determine two distances using tacheometer or theodolite, one short and one long. hence C and K may be determined.

I.E D1 (known) = C.S1 (known) + k D2 (known) = C.S2 (known) + k

Where the instrument designed with an anallatic lens the additive constant k = 0

ERT 247 GEOMATICS ENGINEERING

For example:Distance Readings Intervals (m) upper Stadia Centre Lower Stadia upper lower total 30.000 1.433 1.283 1.133 0.15 0.15 0.30 55.000 1.710 1.435 1.160 0.275 0.275 0.55 90.000 2.352 1.902 1.452 0.450 0.450 0.90

D =C.S + k30.00 = 0.300 * C + k90.00 = 0.900 * C + ktherefore C = 100 & K = 0

Any combination of equations gives the same result, showing that the telescope is anallatic over this range, to all intents and purposes.

ERT 247 GEOMATICS ENGINEERING

ө

ө S

D

V

hi

hL

A

B

Case of inclined sightsVertical elevation angle:

∆L

ERT 247 GEOMATICS ENGINEERING

L = C S cos Ө + K ,

D = L cos Ө

Then ;

D = CS cos2 Ө + K cos Ө ;

V = L sin Ө = ( C S cos Ө + K ) sin Ө

= 1/2 C S sin 2Ө + K sin Ө ;

∆L = h i + V – h = R.L. of B - R.L. of A ;

Where : h is the mid hair reading

ERT 247 GEOMATICS ENGINEERING

hi

D

ө

S

V

h∆L

A

B

Vertical depression angle:

ERT 247 GEOMATICS ENGINEERING

D = CS cos2 Ө + K cos Ө ;

= 1/2 C S sin 2Ө + K sin Ө ;

∆L = - h i + V + h = R.L. of A - R.L. of B ;

Where : h is the mid hair reading ;

Ө may be elevation or depression

ERT 247 GEOMATICS ENGINEERING

Example From point D three points A, B and C have been observed as follows:

If the reduced level of D is 150.10 m. , hi = 1.40 m. and the tacheometeric constant = 100 , it is required to:I ) find the horizontal distance to the staff points and their reduced levels.II) find the distance AB , BC , and CA.

Staff points

bearingVertical angles

Stadia readings

A 85º 30΄ 5º 12΄ (1.10,1.65,2.20)

B 125º 10΄ 0 (2.30,2.95,3.60)

C 104º 30΄ 9º 30΄ (1.45,2.15,2.85)

ERT 247 GEOMATICS ENGINEERING

N

D

A

B

C

H1

H2

H3

ө1

ө2

ERT 247 GEOMATICS ENGINEERING

Solution

For line DA

S1 = 2.20 – 1.10 = 1.10 m

H1 = 100 x 1.10 x Cos2 (+5o 12’) = 109.0964 m

V1 = 109.0964 x tan (+5o 12’) = + 9.929 m

R.L.of A = 150.10 + 1.40 + 9.929 – 1.65 =159.779 m.

For line DB

S2 = 3.60 – 2.30 = 1.30 m.

H2 = 100 x 1.30 x Cos2 (+00.00) = 130 m.

V2 = 130 x tan (+00.00) = + 00.00 m.

R.L. of B =150.10 + 1.40 + 00.00 – 2.95 = 148.55 m.

ERT 247 GEOMATICS ENGINEERING

For line DCS3 = 2.85 – 1.45 = 1.40 m.H3 = 100 x 1.40 x Cos2 (+9o 30’) = 136.186 m.V3 = 136.186 tan (+9o 30’) = + 22.790 m.R.L. of C = 150.10 + 1.40 + 22.79 – 2.15 = 172.140 m.θ1 = 104o 30’ – 85o 30’ = 19o 00’θ2 = 125o 10’ – 104o 30’ = 20o 40’θ = 19o 00’ + 20o 40’ = 39o 40’

From Triangle DAC

AC = AC = 48.505 m

022 19cos186.136096.1092)186.136()096.109(

ERT 247 GEOMATICS ENGINEERING

From Triangle DCB BC=

BC= 48.133 m

From Triangle DAB

AB=AB= 83.471 m

0420cos186.136000.10302)186.136()000.130( 022

022 19cos096.109000.10302)096.109()000.130(

ERT 247 GEOMATICS ENGINEERING

D D

S

S

ӨӨ

Tangential system

Horizontal line of sight :

D = S / tan Ө

ERT 247 GEOMATICS ENGINEERING

Inclined line of sight :

S

D D

Ө1

Ө2

Ө1

Ө2

D = S / ( tan Ө2 – tan Ө1 )

ERT 247 GEOMATICS ENGINEERING

Subtense bar system

1 m 1 m

ERT 247 GEOMATICS ENGINEERING

2 mtheodolite

Subtense bar

α

plan

D = cot( α / 2 )

For distance up to 80 m

ERT 247 GEOMATICS ENGINEERING

α1 α2

D1 = cot (α1/2) D2 = cot (α2/2)

D = D1 + D2

For distance 80 – 160 m

ERT 247 GEOMATICS ENGINEERING

Theodolite 1Theodolite 2

900β

αAuxiliary

base

x/2

x/2β

α

x

X = ( 2D )1/2 ;

X = cot ( α/2 ) , D = X cot β , D = X/2 cot β/2

For distance 160 – 350 m

ERT 247 GEOMATICS ENGINEERING

For distance 350 – 800 m

D1 D2

X = 0.7( 2D )1/2 ;X = cot ( α/2 ) , D = X ( cot β1 + cot β2 ) ,D = X/2 [ cot (β1/2) + cot (β2/2) ]

β1β2

α x

x/2β1 β2

ERT 247 GEOMATICS ENGINEERING

Electronic Tacheometry

The stadia procedure is used less and less often these days, more commonly geomatic engineers use a combination theodolite-EDM known in jargon as a total station.

Often these instruments are connected to a field computer which stores readings and facilitates the processing of the data electronically.

ERT 247 GEOMATICS ENGINEERING

This instrumentation has facilitated the development of this method of detail and contour surveying into a very slick operation.

It is now possible to produce plans of large areas that previously would have taken weeks, in a matter of days.

The math's behind the operation is very simple, it is in effect the same as the stadia formulae with the term for the distance replaced by the measured slope distance.

ERT 247 GEOMATICS ENGINEERING

reflector

Ө

HI

D

S

HrV

S = D cos Ө

R.L.of point A = R.L.of point B + HI + V - Hr

B

A

ERT 247 GEOMATICS ENGINEERING

Tacheometry Field Procedure

1. Set up the instrument at a reference point

2. Read upper, middle, and lower hairs.

3. Release the rodperson for movement to the next point.

4. Read and record the horizontal angle (azimuth).

5. Read and record the vertical angle (zenith).

ERT 247 GEOMATICS ENGINEERING

Error Sources

There are 4 main sources of error: Staff Readings Tilt of the Staff Vertical Angle Horizontal Angle

ERT 247 GEOMATICS ENGINEERING

ERT 247 GEOMATICS ENGINEERING

ERT 247 GEOMATICS ENGINEERING