Transformer Advanced Off-LineDiagnostic Testing
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
3/58
Most of the techniques, whether chemical or electrical
methods, or destructive or non-destructive methods, onlyprovide partial information about the state of theinsulation condition of power transformers.
More advanced condition monitoring or condition
assessment techniques have been developed and arenow starting to come into more general use.
They have been developed in response to the need fornew materials assessment methods.
However, in some advanced diagnotics tools are still inthe developmental stage, either in the technicaldevelopment or, more likely, in the methods of analysisand interpretation of the test data.
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
4/58
Recovery Voltage Measurement (RVM)
Polarization and Depolarization Current Measurement (PDC) Frequency Domain Dielectric Spectroscopy (FDS)
Frequency Response Analysis (FRA)
Partial Discharge (PD) Measurement
RVM, PDC & FDS are based on the used of the dielectricresponse of insulating materials to the application of electricfields Conductivity, Polarization & Dielectric Response
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
5/58
When a dielectric material with polar molecular structure is
subjected to a DC voltage, the electric dipoles are oriented withinthe material in response to the applied electric field.
There is thus a polarization charge induced by the dipolemovement and realignment and this will effectively give a voltageacross the capacitance. When the dielectric is short circuited, thestored charge in the dielectric capacitance is dissipated by acurrent discharge with a time constant determined by theeffective intrinsic resistance and capacitance.
During the short circuit the voltage across the dielectric is zero,
but when the short circuit is removed before total charge toequilibrium occurs, then a voltage will appear across thedielectric. This measured voltage is known as the recoveryvoltage.
()
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
6/58
()
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
7/58
()
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
8/58
A dielectric material becomes polarized when exposed to an electric field.Polarization is proportional to the intensity of the electric field and bymeasuring the current, polarization process can be observed. The currentdensity is the sum of the conduction current and the displacement current.
When the insulating material is exposed to a step voltage, polarizationcurrent is obtained. If the step voltage is removed, a reverse polarity currentknown as depolarization current is obtained. These two currents can beused to determine the response function and the conductivity of thedielectric material.
The PDC is a DC testing method which determining the polarizationspectrum in time constant domain between 10e-3 10e3 seconds in whichthe interface polarization phenomena of long time constant are active. Therange of polarization is strongly influenced by the absorbed moisture and
the deterioration by product content of the paper insulation. It applies a500V step of DC voltage to the high or low voltage winding insulations oftransformers. Time of voltage application is typically up to 10000 seconds.Both the polarization and depolarization times are performed for the sameperiod of time.
& ()
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
9/58
The polarization current pulse has a peak magnitude, a final
steady state level and a time constant and duration that aredetermined by the quality of the oil including both the moisturelevel and the electrical conductivity. In genera the electricalconductivity affects the peak current in the first 100 seconds orso of the current pulse. The moisture in the insulation affects thelonger term polarization current level after about 1000 seconds.[Figure 8.6]
Polarization and depolarization current measurement methodgives general information about the state of insulation condition.This technique is proved to be a useful testing method inpredicting of moisture and development of ageing phenomena.
& ()
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
10/58
Effect of moisture in oil and cellulose paper on the polarization
depolarization current measurement
& ()
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
11/58
In the FDS technique, a known sinusoidal voltage is applied and
measured together with the current passing across the insulationmaterial.
The measurement is repeated for several frequency sweeps -from high frequency to low frequency for minimizing the memoryeffects.
Advantage - the complete diagnostic on the property change inthe material can be discerned
By dividing the current by the voltage and comparing the phasedifference, both the capacitance and the loss at the particular
frequency and amplitude can be calculated.
()
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
12/58
The advantage of an analysis of the dissipation factor frequencyas compare at fixed frequency:
Behaviour of insulation caused by moisture affects can be evaluated.
At higher frequencies the pressboard and the oil volume determinethe dielectric loss, at medium frequencies the oil conductivity is thedominant factor and the lower frequency range is dominated by thepressboard dielectric loss.
()
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
13/58
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
14/58
Measurement results of the insulation between primary andsecondary to tertiary windings on a power transformer.
()
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
15/58
PROGRAMMA IDA 200
()
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
16/58
How do you know whether you can energize A
TRANSFORMER after transportation to site or
after a protection trip?
Check Mechanical Integrity
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
17/58
When does Mechanical Integrity matter?
Re-location Short Circuit
Lightning
Tap-changer fault
Transportation damage can occur if the clamping andrestraints are inadequate; such damage may lead to coreand winding movement.
Radial buckling or axial deformation may occur due toexcessive short circuit forces while in service.
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
18/58
What you can identify by checking mechanical integrity?
Core Movement
Winding Deformation
Faulty Core Grounds
Partial Winding Collapse
Hoop Buckling
Broken or Loosened Clamping Structures
Shorted Turns and Open Windings
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
19/58
What Test can be Done?
Frequency response analysis (FRA) using alow voltage AC wave of varying frequency to
identify changes in natural resonance
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
20/58
Why FRA?
FRA Technique: The technique covers the full dynamic range andmaintains the same energy level for each frequency, providing resultsthat are repeatable and accurate.
Impulse Technique: This technique requires high sampling rates andhigh resolution to obtain a valid measurement. The applied impulse doesnot produce constant energy across the specified frequency, which can
cause poor repeatability that is influenced by the non-linear properties ofthe test specimen.
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
21/58
What is FRA ?
FRA is a tool that can give an indication of core or winding
movement in transformers. This is done by performing a measurement to look at how well
a transformer winding transmits a low voltage signal that variesin frequency.
Transformer does this in relation to its impedance, thecapacitive and inductive elements which are intimately relatedto the physical construction of the transformer.
Changes in frequency response as measured by FRAtechniques may indicate a physical change inside thetransformer, the cause of which then needs to be identified andinvestigated.
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
22/58
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
23/58
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
24/58
Test Equipment
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
25/58
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
26/58
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
27/58
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
28/58
What is the frequency range?
The measured frequency range is normally very large,
which can be from 5Hz up to 10MHz
This frequency range covers the most important
diagnostic areas:
Core and Magnetic Properties
Winding Movement and Deformation
Interconnections-Leads and Load Tap Changer
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
29/58
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
30/58
The magnitude and the angle of the complex transfer functioncan be obtained using a network-analyzer
The resulting amplitude of the measurement can be expressedas,
H (dB) = 20 log10 [(ZS)/(ZS+ZT)]
The resulting phase is defined by
H () = tan-1 [(ZS)/(ZS+ZT)]
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
31/58
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
32/58
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
33/58
What are the ANALYZING TECHNIQUES?
Signature
Difference
Transfer Function Statistical
FRA Signatures are analyzed based on 3 bandmethods
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
34/58
What do the 3 Bands mean?
5Hz up to 10KHz defect in core and magnetic
circuit
10KHz up to 600KHz deformation in windinggeometry
600KHz up to 10MHz abnormalities in the
inter-connection and testsystem
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
35/58
SIGNATURE TECHNIQUE
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
36/58
SIGNATURE TECHNIQUE
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
37/58
SIGNATURE TECHNIQUE
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
38/58
DIFFERENCE TECHNIQUE
(Phase A before)
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
39/58
DIFFERENCE TECHNIQUE
(Phase A after)
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
40/58
DIFFERENCE TECHNIQUEThis technique can analyze the windings phase by phase, which is not
possible in the signature technique
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
41/58
Historical data or Baseline Reference are, undoubtedly,the best reference to be used for FRA analysis
However, it is not practically easy to get historical data due
to constraints of outages
Criteria to choose reference FRA measurements in theabsence of historical data or baseline reference
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
42/58
DifferentDifferentSameSamePeer
DifferentSameSameSameSister
SameSameSameSameTwin
S/S
LOCATION
MANU-
FACTURER
MVA
RATING
KV RATIOCATEGORY
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
43/58
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
44/58
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
45/58
PD Classification
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
46/58
Occurrence of PD Inception Voltage
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
47/58
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
48/58
Occurrence & Recognition
Detection
Measurement
Location
Evaluation
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
49/58
Evaluation
Amplitude in dB Energy or charge in pC
Duration in ms
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
50/58
On-line acoustic PD Detection - Physical Acoustic DISP-24
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
51/58
Why SFRA in a factory environment?
Quality assurance
Baseline reference
Relocation and commissioning preparation
Manufacturers are using SFRA as part of their quality program to ensure
transformer production is identical between units in a batch
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
52/58
Why SFRA in a field environment?
Relocation and commissioning validation Post incident: lightning, fault, short circuit, seismic event
etc
Once a transformer arrives on site after relocation it must be tested
immediately, to gain confidence in the mechanical integrity of the
unit prior to commissioning
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
53/58
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
54/58
( ) Electrical Tests
Perform insulation-resistance tests winding-to-winding
and each winding-to-ground
Perform turns ratio tests at the designated tap position
Perform power-factor or dissipation-factor tests
Measure the resistance of each winding at thedesignated tap position
Measure core insulation-resistance at 500 volts dc ifcore is insulated
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
55/58
Inspection - look for cracks, dirt etc., tracking, copper wash,
mechanical damage Cleaning - Wash, dry wipe
Repairs - Usually replace except special cases
Testing - Megger & Power Factor test
Do not climb on or use for personal support!
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
56/58
( )
Visual inspection
Inspect physical condition for evidence of moisture and corona
Verify operation of cooling fans
Verify operation of temperature and level indicators, pressurerelief device, and gas relay
Verify correct liquid level in all tanks and bushings
Verify correct equipment grounding
Verify the presence of transformer surge arresters
Test load tap-changer
Inspect all bolted electrical connections for high resistance usingone of the following methods:
1. Use of low-resistance ohmmeter
2. Perform thermographic survey
8/13/2019 Engineering Diagnostic Tools EEEM 513 - (5) Transformer Advanced Electrical Diagnostic
57/58
( )
Electrical Tests
Perform turns ratio tests at all tap positions
Perform power-factor or dissipation-factor tests
Measure the resistance of each winding at all tap positions
Perform insulation-resistance tests winding-to-winding and each
winding-to-ground
If core ground strap is accessible, measure core insulationresistance at 500 volts dc
Remove a sample of insulating liquid in accordance with ASTMD923
Test for Oil Quality, DGA and Furan