1LCLS EIR, 10/9/07D. Schultz
Electron Beam SystemsETC and Methodology
Electron Beam Systems Definition of terms
Schedule Overview Start-Up Test PlanE-Beams CostsRisk Analysis
David Schultz
E-Beams Systems Manager
2LCLS EIR, 10/9/07D. Schultz
BC1
LXL1
Laser lab
Sector 20
Sector 21E-Beams Systems layout
Injector Injector Commissioning complete
3LCLS EIR, 10/9/07D. Schultz
The electron gun in the InjectorLaser beam
transport
Electron gun
4LCLS EIR, 10/9/07D. Schultz
SLAC linac tunnelSLAC linac tunnel research yardresearch yard
Linac-0L =6 m
Linac-1L 9 m
Linac-2L 330 m
Linac-3L 550 m
BC1L 6 m
BC2L 22 m
LTU L =275 m
undulatorL =130 m
6 MeV 135 MeV 250 MeV 4.30 GeV 13.6 GeV
Linac-XL =0.6 m
...existinglinac
rfgun
X
E-Beams Systems layout
L2/BC2/L3Injector/BC1
Comm
issio
ned
Now In
stal
ling
5LCLS EIR, 10/9/07D. Schultz
Beam Transport Hall Transport the electron beam to the Undulator
E-Beams Systems layout
SLAC Linac LCLS uses the last 1/3 of the existing Linac.
Controls Beamline and diagnostics control for e-beams systems.
Undulator Hall Underground tunnel housing the undulator.
Electron Beam Dump Underground facility for the beam dump.
Near and Far Halls – Areas for x-ray experiments
6LCLS EIR, 10/9/07D. Schultz
Injector WBS 1.02, 2.02Jose Chan, Control Account Manager
Laser/Gun/L0/Spectrometer
– Installed and commissioned
Create electrons, accelerate, analyze beam quality
E-Beams Systems WBS structure
Laser HeaterAccelerator R&D activity
7LCLS EIR, 10/9/07D. Schultz
Linac WBS 1.03, 2.03Jose Chan, CAML1/Lx/BC1 – Installed and commissioned
Accelerate the beam, initial beam bunch compression
L2/BC2/L3Full beam acceleration, second compression of bunch
E-Beams Systems WBS structure
LTUTransport electron beam from Linac to Undulator
Electron dumpSafely dispose of the electron beam
8LCLS EIR, 10/9/07D. Schultz
Undulator WBS 1.04, 2.04Generate x-rays as the high power electron beam passes through.
Undulator Systems at ANL, Geoff Pile, CAMFabricate components and supports for the Undulator system
Undulator Integration at SLAC, Rodd Pope, CAMTune, fiducialize, assemble, and install the Undulator system
E-Beams Systems WBS structure
9LCLS EIR, 10/9/07D. Schultz
Accelerator Controls WBS 1.02.02, 2.02.02,
1.03.02, 2.03.02, 1.04.02, 2.04.02
Hamid Shoaee, CAMControlling hardware, cable plant and software for Injector, Linac and Undulator Systems
Commissioning WBS 2.01.01, 2.02.17, 2.03.07, 2.04.06
David Schultz, CAMLOE manpower for LCLS personnel and maintenance groups during the electron beam commissioning process.
E-Beams Systems WBS structure
10LCLS EIR, 10/9/07D. Schultz
System engineering resource loaded schedule is controlled through P3.Design process:
Interface Control Documents specify which group has responsibility for each system.Physics Requirements Documents are written by the LCLS Physics group specifying subsystem needs.Engineering group holds Design Reviews, and writes Engineering Specification Documents to detail how the PRD is to be satisfied.
Physicists and Engineers sign-off on component assembly and testing prior to installation.
System Design Management
11LCLS EIR, 10/9/07D. Schultz
E-Beams Systems Level 3 Milestones
L3 milestones sufficient and properly distributed to monitor performance.
12LCLS EIR, 10/9/07D. Schultz
E-Beams Systems Level 3 Milestones
13LCLS EIR, 10/9/07D. Schultz
LCLS Installation and Commissioning Time-Line
SS OO NN DD JJ FF MM AA MM JJ JJ AA SS OO NN DD JJ FF MM AA MM JJ JJ
Linac/BC2 Install
Linac/BC2 Commissioni
ng
LTU/Und/Dump Install
20072007 20082008
CF Early Occupancy
LTU/Und Commissionin
g
Flux milestone
AA SS OO NN DD
20092009 20102010PPS
X-ray tunnel/FEH Install
CD-4(7/30/10)
PPS
FEE/NEH Commissioning
Tunnel/FEH Commissioning
JJ FF MM AA MM
FEE/NEH Install
FEH X-rays milestone
14LCLS EIR, 10/9/07D. Schultz
LCLS Safety Assessment Document is due 7/2008
LCLS Accelerator Readiness Review is needed 10/2008
Systems installed, checked out, signed off by responsible parties.
Safety officers’ sign offs on approvals and installations.
Safety specific systems (Personnel Protection) certified.
Maintenance groups have procedures and training in place.
Procedures in place for Operations, and Operators trained.
Beam Authorization Sheet prepared.
Detailed commissioning schedule and performance goals are produced by the LCLS Physics group.
Approval to begin commissioning given by the Director’s office
Start Up Test Planning
15LCLS EIR, 10/9/07D. Schultz
As installation is approaching, systems are well defined.Installation costs
Based on experience in 2006 Injector installation. Hardware install estimate done top-down and bottom-up.
Based on experience on undulator prototype at ANL.Cable plant install estimated using R.S. Means.
Fabrication/procurementCosts based on quotes and experience with prototypes at SLAC and ANL.
Engineering and CommissioningTimetable for completion well understood.
E-Beams Systems Cost Estimation
16LCLS EIR, 10/9/07D. Schultz
Risk Assessment
Design maturity and cost/schedule exposure are used in the contingency analysis for all DCE activities.Major risks are identified as Risk Registry entries, and assessed and maintained by the System Manager.The Senior Management team reviews the Registry monthly.
Summary of E-Beams Systems entries:Linac (2)
Risk: Linac diagnostics may need to be enhanced to have sufficient sensitivity for FEL commissioning.
Mitigation: The upcoming BC2 commissioning will determine if an upgrade is warranted.
17LCLS EIR, 10/9/07D. Schultz
Risk registry
Summary of entries (cont.):Undulator (3)
The assembly of the Undulator Girders is a pacing item for Undulator commissioning. Several components from ANL are close to being the limiting factor
Risk: Any rework or modification of parts at SLAC will delay girder assembly.
Mitigation: We have multiple weekly video meetings with ANL and quarterly Undulator collaboration meetings to ensure coordination.Integration engineers at ANL and at SLAC have been established to coordinate the receipt and assembly.
18LCLS EIR, 10/9/07D. Schultz
Electron Beams Systems are approaching final installation.Systems are well defined,
Based on Project documentation.Resource loaded schedule in P3.Costs have a solid basis.
The start up test plan is based on the successful turn-on of the LCLS Injector.Identified risks are being controlled.
Summary