Easy Cost Planning in PSSkip to end of metadata
Created by Guest, last modified by psjalu on Feb 19, 2013Go to start of metadata
This Wiki page will demonstrate how to create costing model for Easy Cost Planning and carry out Cost planning using ECP.
Introduction
The Easy Cost Planning tool enables you to plan costs at WBS level, based on quantities and characteristics. ECP can
also be used for Internal Orders & Appropriation Requests.
You use it to create quantity structures (possibly temporary) for the cost calculation, starting from the project structure. The
system valuates your entries using the prices and rates defined in the system, then distributes the costs in line with the basic
dates for the respective WBS elements.
You can make best use of this tool in the following processes:
● Project processing concentrating on cost controlling
● preliminary costing for complex projects
You need to define Costing Model to plan using Easy Cost Planning. Costing Model becomes a predefined template for
costing using quantities.
Following are steps to be followed to create costing model. Create as many characteristics based on number of parameter
required for calculating the cost. For example if the cost of the computer to be calculated based on 1.No. of Computers 2.
Hard Disk Capacity 3. Monitor Size 4.Mother Board configuration, then create 4 characteristics.
STEPS FOR CREATING COSTING MODEL:
1. Create Characteristic (Enter T Code: CT04)
Under value tab define predefined values (these would be available as a drop down)
Similarly define other characteristics 1.MENGE 2.MONITORSIZE 3.MOTHERBOARD
Note: You can create the characteristics directly in Costing Model also.
2. Create Costing Model (Enter T Code:CKCM)
Select Create model as shown below
Add characteristics created in step1 or else you can create the characteristics directly here.
Click on "Define the derivation rules"
Select reference object as "WBS Element" . Reference Object defines which objects should use this costing model. Since,
WBS Element is chosen here, other objects like IO or AR cannot use this Costing model.
Define derivation rule for Number the computers i.e. MENGE Characteristic. Labor charges are calculated based on number
of Computers.
Type: Cost Center/Activity Type
Object: 4205 (Cost Center) / 1421 (Activity Type)
Quantity: MENGE Characteristic
Define derivation rule for Characteristic "HARD DISK". Based on the Hard Disk Capacity, cost should flow from different
material master data. For each Hard disk value, material master data mapping to be done.
Type: Material
Object: 1000(Plant) / DPC1095 (Material)
Quantity: MENGE Characteristic (to multiply the cost based no. of computers)
In activation the relevant value is mentioned to which this derivation rule is applied i.e. here when Hard Disk value is 6 then
Material Cost is picked up from Mat:DPC1095).
Similarly define for Hard disk value 9 GB
Similarly define derivation rule for other Characteristics and save the Costing model.
EASY COST PLANNING:
Select the WBS then press SHIFT+F11
Select the Costing Variant and click on "Create Cost Estimates"
Cick on Choose Planning Form and select Costing Model
Input values and click on "Confirm"
Cost is calculated and reflected on left i.e. Costing structure. Overheads are calculated based on Costing Sheet defined in
the Costing variant.