Post on 18-Jan-2016
E. Richards
EE Chamber installation
Summary
Position Of the EE chambers
General view of EEL chambers
EEL5 chamber
Installation of other chambers ex. EEL11
10/6/08
Position of The EE chambers
10/6/08
General view of EEL chambers
10/6/08
EEL5 chamber
10/6/08
Installation of other chambers ex. EEL11
Barrel vacuum pumps must be removed Removal of gangways using “Wisconsin Tooling” or CMS tooling.
10/6/08
Installation of other chambers ex. EEL11
Installation of EEL support structure with modified Wisconsin Tooling
10/6/08
Installation of other chambers ex. EEL11
Installation of the chamber with modified Wisconsin tooling and “grabber”
10/6/08
Installation of other chambers ex. EEL11
Replace modified gangways
Reinstall vacuum pump
10/6/08