Dynamics AX 2009 MRP training

Post on 08-Dec-2014

12.168 views 14 download

Tags:

description

Master planning training for Dynamics AX 2009

Transcript of Dynamics AX 2009 MRP training

OADDynamics AX 2009 Training:Master Plan

Agenda

Master Plan Overview

Parameters Setting

Master Scheduling

Forecast Scheduling

Items Coverage

Planned Order

Master Plan Overview

Dynamics AX Master Plan Position

Materials Requirements Planning(MRP)

CapacityRequirements Planning(CRP)

Microsoft Dynamics AXMaster Plan

• Materials Planning• Finite Materials• Items Dimensions• Lead Time• BOM structure• ……

• Work Center• Work Capacity• Finite Capacity• Job Scheduling• …….

Multi-sites Master Plan

Generous Flow in Master Plan

Item MasterSetting

Item Coverage

RunMasterPlan

SetupMaster

Plan

ParametersSetting

PlannedPurchase

Order

PlannedProduction

Order

PlannedTransfer

Order

PurchaseOrder

ProductionOrder

TransferPlan

Optional

ParametersSetting

Master Plan Setup ParametersGeneral Tag

1

2

3

1. 1 Static Master Plan

Calculate requirements based on current data.

The plan remain unchanged until next static master plan running.

It is an operation plan most likely run by purchaser or production planner.

1.2 Dynamics Master Plan

Calculate requirements based on net requirements.

It is an sales plan most likely run under the changing of sales order.

1.3 Dual Plan

Single plan (both static and dynamics are the same plan) and Dual plan (use different plan for static and dynamics).

Dual plan is used while sales simulation without affecting current results.

Single plan is used when the sales simulations is usually firmed to planned order.

2.1 General Coverage Group

It is default item coverage group in running master plan when item has not defined Item coverage group.

Priority:

Item Coverage >> General Coverage Group

2.2 Future Time

If receipt time > future time, one day will be added in future day (planned day).

E.g.

3. Today date

Running master plan based on this calendar.

User can select different calendar and run master plan.

4

Master Plan Setup ParametersPlanned Order Tag

4.1 Find Trade Agreement

Search vendor either in lowest price or shortest lead time when running master scheduling.

4.2 Receipt Time

Automatically assigned to planned production order.

If receipt time > future time, future message will be generated.

User can choose amend delivery date (receipt date of planned order) as future date.

Master Plan Setup ParametersStandard Update tag

5

5.1 Group by Vendor/ buyer / Period

Group planned purchase order by vendor / buyer / period.

MasterPlan

Master Plan Setup Plans Master PlanStandard Update tag

6

7

8

6 Include criteria

User can include following criteria in master plan:

- On hand

- Inventory Transaction

- Sales Quotation (include %)

- RFQ

- Forecast Plan

7.1 Scheduling Method

Operation Scheduling

- Production will be scheduled in work center group and date

Job Scheduling

- Production will be scheduled in work center and time

7.2 Time fence (I)

Background capacity time fence

- Search for capacity which available

- usually 0 (search to today) Finite capacity

- Time fence for finite production scheduling Bottleneck capacity

- Time fence for bottleneck resources

Normally, finite capacity for short-term scheduling and bottleneck capacity for middle term scheduling

8. Forecast Plan

Forecast Plan: link to forecast plan Reduction Key: used to reduce forecast

amount in future Alternative: set reduction principle in

master plan

Master Plan Setup Plans Master PlanTime Fence tag

9

9. Time fence (II)

Coverage: time fence for master plan cover

Freeze: will not create planned orders in this period

Firming: will automatically generate purchase / production order

Explosion: will explore BOM item in this period

Con’t

Forecast Plan: Consider forecast in this time period.

Capacity: Consider working capacity for this period

Action Message: Time fence to consider action date

Future Message: Time fence to consider possible future date.

Master Plan Setup Plans Master PlanFuture Message tag / Action Message tag

10

11

10. Future Message

Update planned production / purchase / transfer order

- Update delivery date to possible future date

- e.g.

11. Action Message

Update delivery date to date which nearest requirement datee.g.

Master Plan Setup Plans Master PlanSafety Margin tag

12

12. Safety Margin

Receipt Margin

- Additional time for purchase receipt Issue Margin

- Deduce issue requirements (Sales Order) from master scheduling

Reorder Margin- Additional lead time for purchase in master

scheduling

Forecast Scheduling

Forecast plan overview

Forecast Plan

Forecast Scheduling

Forecast Model 1

ForecastModel 2

Forecast Model n

………

ITEMs

Inventory Management Setup Forecast Forecast ModelForecast Model

13

13. Forecast Model

Arrange sub-model for the forecast model Run forecast plan using upper forecast

model

Master Plan Setup Forecast PlansForecast Plan

14

14. Define the forecast plan

User can select whether forecast plan include sales/purchase forecast

Select forecast model the forecast plan apply to.

Inventory Management Periodic Forecast Item EntryItem

15

15. Define forecast

Model: Define which forecast model to be run

Customer Account / Group: Create customer-based forecast

Item Allocation Key: allocate item ratio to item group

Sales Quantity: forecast Qty for 1 unit per forecast

Allocation: Set length of forecast period

Item Coverage

Inventory Management Periodic Forecast Item EntryItem

1415

16

14. Coverage

Coverage plan: Days coverage in this group

Coverage code:

- Period

- Requirements

- Min.Max

Con’t

Period: consolidate requirements by period

Requirements: Driven by sales order / forecast

Min/ Max: Safety stock

15. Positive & Negative Days

Positive days: Days of period not issue PO under positive requirements

Negative days: Days of period not issue PO under negative requirements

16. Others

BOM version requirements: Requirements by BOM version.

Route Version requirements: Different route will be taken consideration in coverage planning

Planned Order

Master Plan Periodic Forecast Plan / Master Plan

17

17. Planned Order

Select master plan / forecast plan to run Planned order will be generated Release planned purchase order /

production order / transfer order in

“ Master Plan Place Planned”

Lab

Please follow the instruction sheet.

Q & A