Campus Plan

Roosevelt Island campus> Laboratory of innovation> Open and inviting to the public> Sustainable and energy-efficient

BLOOMBERG CENTER

Public Open Space> More than 20% of the Site> No Gates, Walls or Barriers> Public Programming

Public Open Space> Laboratory of innovation> State of the art technologies> Sustainable and energy-efficient

Bloomberg Center> Collaborative Work Environment> Net-Zero Goal> Public Café, Art and Programming

The Bridge> Co-Location Space for Companies> Cornell Tech Studio Space> Common Spaces for Programming

Residential Building> First High Rise Passive House in the World> Housing for Students, Faculty & Staff

2017Phase One

Project Schedule

Start of Demolition January 2013End of Demolition June 2015

Start of Sitework December 2014Start of Bloomberg Ctr. March 2015Start of The Bridge May 2015Start of Residential June 2015

Phase I Opening Summer 2017

December 2014

January 2015

February 2015

March 2015

April 2015

May 2015

June 2015

July 2015

August 2015

September 2015

October 1, 2015

October 1, 2015

Bloomberg Center

October 1, 2015

Bloomberg Center

The Bridge (Co-Location)

October 1, 2015

Bloomberg Center

The Bridge (Co-Location)

Residential Building

October 1, 2015

Current & Upcoming Work

Sitework• Utility installation on East and West roads (closed to public)• Utility installation on campus• Completion of CUP structure & start of equipment installation

• North Road to re-open by the week of October 12

Bloomberg Center• Steel structure started September• Façade/enclosure to start in January 2016

The Bridge (Co-Location)• Steel structure to start in early October• Façade/enclosure to start in Winter 2016

Residential• Superstructure to start in mid October• Façade/enclosure to start in Winter 2016

September 2015

Utilities & Roadways

September 2015

Utilities & Roadways

September 2015

Bloomberg Center

September 2015

Bloomberg Center

September 2015

Bridge (Co-Location)

September 2015

Bridge (Co-Location)

September 2015

Residential

September 2015

Residential

Construction Commitments Reduce truck traffic through largest voluntary

barging effort in NYC history

Minimum 17% MWBE participation in construction

Union labor on all construction projects

On-site air monitoring for duration of the project

Extensive roadway & utility improvements

Close communication with Roosevelt Island stakeholders

Barging for Demolition

Reduction of more than 12,000 truck trips on Main Street

September 2015

Barging for Demolition

Barging for Construction

Barging for Construction

Barging for Construction

Barging for Construction

Barging for Construction

September 2015

Barging for Construction

1

3

2

4

Upcoming Milestones

• Reopening of North Loop Road

• Relocation of West Road fence to facilitate road reconstruction

• Steel construction at Bloomberg Center & The Bridge

• Concrete superstructure at Residential Building

• Start of geothermal wellfield

2017