Post on 13-Oct-2020
Control Room Integration: Switching FocusNabil Hitti, VP Network Operations, TransmissionSeptember 14, 2009
2
Switching Focus: Control Room Operation
Who is National Grid?
The Opportunity and the Challenge
Moving Forward
How it went….switching & staffing
Lessons learned
Q&A
Who is National Grid?
4
National Grid
National Grid is an international electricity and gas company primarily based in the UK and northeastern US. We play a vital role in delivering gas and electricity to millions of people in a safe, efficient and reliable manner.
One of the largest investor-owned utilities in the world. It is the largest utility in the UK and the second largest utility in the US.*
Almost 18 million customers
50% UK, 50% US
50% Electricity, 50% Gas
50% Transmission, 50% Distribution
27,000 plus employees
*Based on customer numbers; includes the servicing of LIPA’s 1.1 million customers
5
National Grid - UK
National Grid owns the high-voltage electricity transmission system in England and Wales, operates the system across Britain, and owns and operates the high pressure gas transmission system in Britain.
The company also operates the UK gas distribution system, distributing gas on behalf of shippers and suppliers to 11 million consumers.
6
National Grid - US
Distributes electricity to 3.3 million customers
Provides natural gas to 3.5 million customers
Services 1.1 million customers of Long Island Power Authority (LIPA)
Currently owns over 4,000MW of generation
The Opportunity and The ChallengeGiving ‘Power Control’ more control
The US Transmission Organization
EVP &Chief Operating Officer
VPNetwork Operations VP
Asset ManagementVP, Work Delivery VP
Regulation & Commercial
DirectorNY Control
DirectorAsset Strategy
DirectorSystem Delivery
DirectorT - Commercial Services
DirectorNE Control
DirectorOp. Planning & Review
DirectorEMS Program
DirectorPlanning
DirectorInvestment Mgmt.
DirectorLine Engineering
DirectorRegional Delivery
DirectorWorks Program Mgmt.
DirectorHVDC Operations
DirectorReliability Compliance
DirectorT - Policy
DirectorProject Mgmt.
US Network Operations – Control Centers
Working closely with several other transmission owners as well as the NYISO and ISO-NE
ISO-NE Peak Load: 28,000+ MW (7331 MW – NG customer load)
NYISO Peak Load: 35,000+ MW (6747 MW – NG customer load)
One NE Transmission Control Center
Previously, one NY Transmission Control Center, with system security responsibilities:
Voltage
Thermal loading
Constraints
Switching undertaken by three separate T&D Regional Control Centers
10
The Business Imperative
Greater Visibility of Transmission Network Operations
Better alignment with global operating model
Internal consistency
Increased focus on transmission switching
Less reliance on our distribution control centers
Industry best practice
Increase operational efficiency
Reduce human errors
More direct implementation of new capital work plan
Moving forward
Moving Forward – in the starting blocks….
Detailed analysis of the existing hurdles we faced:
Varied switching guidelines & practices
Resources & knowledge
Training
Control room set-up
Timeline
Department / responsibility changes
Moving Forward
To address these, we had to….
Recognize training needs
Ensure adequate resources
Project team & integration / switchover plan
Three-stage process
Update switching guidelines
Staffing
To achieve smooth operational handovers
Moving Forward - approach
Project team in place2.5 FTE equivalent
Timeline agreed –April 1, 2007 – Integrate Central Region
October 1, 2007 – Integrate Western Region
April 1, 2008 – Integrate Eastern Region
Outreach & initial trainingInternal
Field Forces
How it went….switching & staffing!
How it went….switching and staffing
A whole new world – training & recruitment
New procedures for Distribution Control & Transmission Control
Added Control Room Responsibilities - NYSystem Operators – switching oversight
Control room supervisor – another set of employees
Trainer on site
Switching guidelines created for all transmission assetsLines
Busses
Other station equipment
How it went….switching and staffing
New demarcation
The high-side taggable disconnect capable of interrupting bank magnetizing current
Switch 18, right
Both control centers may operate and tag this device
Neither may go ‘beyond’this device
Upstate New York Service Territory
How it went….D-Day!
April 1, 2007 – Central RegionDay 1 – Alarms! -- minor EMS problem
Implemented on a Sunday – low work volume
Monday (4/2/07) went smoothly
Started to lose staff soon after
Staffing – An Immediate Problem
Soon after the Central integration, TCC began to lose staff
3 qualified operators filling a 6-person schedule
Pushed to keep on schedule
Retiree-contractors hired to fill union positions
How it went….D-Days(s)!
Western 0500hrs, Oct 2, 2007
Staffing challenges
Similar technical challenges
Lots of 2-way training
Similar alarms – fixed!
New ways of workingField forces
WRCC Operators
How it went….D-Days(s)!
Eastern 0500hrs, April 1, 2008
Sep 29, 2008
Technical challenges
Staffing
Similar alarms – fixed
Tribal knowledge vs. Procedures
Lessons Learned
Lessons Learned
Project planningIntegration process - should have started earlier
Updating switching guidelines – challenging
Scheduling Flexibility!
TrainingNeed more than a half-day of classroom training
Iterative and repetitive
Practical / field training worked well - meeting people!
Visiting major/unique substations would prove valuableAssociate an EMS screen with a field device
Unique station configurations & limitations became visible
Lessons Learned
Communication:
Sharing information
Taken for granted
Constant two-way communication
Resourcing:
Attracting qualified applicants into a new department
Past projects with limited success
Creative solutions – retiree-contractors filling union jobs temporarily
Previous regional experience was vital
Using local knowledge is key in consolidation & integration efforts
Project Summary
Where are we today?
Largely realized increased reliability and safety
HE reduction trend
Record reliability
Fully integrated TCC
Well-defined and solid operating model
Internally and externally recognized as a successful department
Lessons Learned
Above all –
be flexible….
……and be prepared!
Questions?Nabil Hitti, VP Network Operations, Transmission