Post on 16-Jul-2020
NHS Rotherham Clinical Commissioning Group
Operational Executive 18 July 2016
Strategic Clinical Executive 20 July 2016
GP Members Committee 27 July 2016
Governing Body 3 August 2016
Commissioning Plan Performance Report
Lead Executive: Ian Atkinson, Deputy Chief Officer Lead Officer: Lydia George, Planning and Assurance Manager
Lead GP: N/a Purpose:
For the Governing Body to note:
• that the 2016/17 Commissioning Plan Performance Report has been substantially revised
• current progress with delivery of the Commissioning Plan
Background:
In 2013 a performance framework for the Commissioning Plan was developed so that the CCG could assess its progress against key priorities and on its implementation of the plan. The report has been refined each year but has broadly remained the same.
The performance report each year has been undertaken in July, October and March and reported to OE, SCE, GPMC and Governing Body each time. The report provided important evidence for Investors in Excellence.
Analysis of key issues and of risks In line with the new CCG Improvement and Assessment Framework and the revision of the GB overall performance report it was decided that the Commissioning Plan performance framework would be revised to provide a fuller picture of delivery. The key changes are:
• Each of the 15 priority areas from the Commissioning Plan are reported • Each priority area has clear milestones and targets aligned to the Commissioning Plan • Each priority area includes Key Performance Indicators taken from the new CCG
Improvement and Assessment Framework metrics, the new Governing Body Performance report, Quality Premiums, the Better Care Fund or are regular key local metrics already reported
• QIPP information is included for those priority areas that are subject to QIPP • Any associated risks from the GB Assurance Framework / Risk Register are reported • Lead GP and Lead officers are reported
Lead officers have provided commentary against the milestones and metrics where performance is off track. In quarter 2 officers will also be asked to provide a forward view where it is anticipated that they would be off track by the following reporting quarter.
From 2016/17 the performance framework will be reported 4 times a year and will be received at Governing Body in August, November, February with a final year- end report in May.
To note
This is a substantial update of the report and is still very much work in progress and still is subject to minor modification.
In addition, a number of the metrics taken from the Improvement and Assessment Framework are still awaiting data nationally.
Progress with implementation of the Commissioning Plan by the end of quarter 1 Milestones There are 51 milestones in total, see breakdown below:
Red 1 Amber 3 Green 43 *TBC 4 Total 51
*Note – these milestones need further clarification with the lead officer.
Overall there are approximately 82% of milestones on track, however this is not conclusive given the number of milestones to be confirmed.
RAG rate
No. Milestone description Commentary
Red 1 Involvement of the Care Co-ordination Centre in the End of Life Care pathway
Discussions are still taking place on its implementation.
Amber 3 Primary care self-care pilot complete tele-health evaluation
Expand the role of the CCC to manage the interface between acute/community
Achieve 40% implementation of the case management palliative care template in primary care
Delay in commencing due to provider (‘EE’) connection
CCC expansion on track, further discussions needed around the clinician to clinician proposal
Decision to be included only recently made, therefore implementation is just taking traction
Key Performance Indicators There are 48 milestones in total, see breakdown below:
Red 6 Amber 5 Green 13 **TBC 25 Total 48
** Note – these metrics need either further clarification with the lead officer or are awaiting further data nationally
Overall there are approximately 27% of KPIs on track, however this is not conclusive given the number of KPIs still to be confirmed.
Below is a list of the red and amber Key Performance Indicators, commentary on performance can be found in the Governing Body Performance Report or Governing Body Quality Report.
RAG No. Key Performance Indicator Description
rate
Red 7 Utilise NHS e-referral service to enable choice at 1st routine elective referral
Achieve A&E 4 hour access standard
People who have had a stroke who are admitted to the acute stroke unit in 4 hours of arrival to hospital
Number of A&E attendances by care home residents
Cat A ambulance response calls within 8 minutes
Percentage of people moving to recovery of those who have completed IAPT treatment
Cancer (all) diagnosed at stage 1 and 2
Amber 4 Proportion of people waiting 6 weeks or less from referral to entering a course of IAPT treatment
Patients requiring a Continuing Healthcare assessment will have an eligibility assessment within 28 days from the receipt of the continuing healthcare checklist – Adults
Patients requiring a Continuing Healthcare assessment will have an eligibility assessment within 6 weeks from the receipt of the continuing healthcare checklist – Childrens
Percentage seen within 62 days after a referral by GP
The level of QIPP savings is still to be determined.
Approval history:-
OE 18 07 2016
SCE 20 07 2016
GPMC 27 07 2016
Recommendations:
The Governing Body are asked to:
1. Note the revised Commissioning Plan Performance Report and provide any feedback to its development at this stage.
2. Note that the Performance report is still work in progress, and is still subject to minor modification.
3. At this point it is difficult to gain an overall understanding of progress to date since there are a number of milestones, and a significant number of Key Performance Indicators still to be confirmed. Note that the latter is mostly due to the data not being available yet nationally.
4. Note that reporting for 2016/17 has increased from 3 times per year to 4 times per year.
Commissioning Plan Performance Report 2016/17
Meeting Date
Operational Executive 18 07 2016 Strategic Clinical Executive 20 07 2016 CCG Governing Body 03 08 2016 GP Members Committee 27 07 2016
DRAFT Definitions for RAG Ratings:
Red KPI Milestones QIPP
Less than 2% achieved Not started or significant issues Not started or Started but still high risk
Amber
KPI Milestones QIPP
Within 2% achieved Started but not on track OK with medium risk
Green
KPI Milestones QIPP
Achieved On track Achieving as planned
Please note
• That there are a significant number of KPIs from the new Improvement and Assessment Framework where data is not available yet.
• There is a glossary on the back page. • The QIPP position will be reported in the Governing Body version of this paper.
1 Primary Care Lead GP: Jason Page Lead Officer: Jacqui Tufnell
Funding in 2016/17 = £0.6m for the LIS, £1.2m for Case Management and funding for the CCG Commissioned LES’s
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Primary Care Quality Contract – implement and monitor 3 standards for 2016/17.
Com / primary care plan
Q1 On track
M2 Primary Care Quality Contract – develop remaining standards for 2017/18
Com / primary care plan
Q3 On track
M3 Primary Care Quality Contract – Agree contracts for 2017/18 standards
Com / primary care plan
Q4 On track
M4 Primary Care Self-care pilot – complete tele-health evaluation
Com / primary care plan
Q2 Scheme started but not on track, delay with start due to provider (‘EE’) connection
M5 Monitor and evaluate the effectiveness of the Care Home Alignment with GP practices
Com / primary care plan
Q4 On track
Key Performance Indicators (KPIs) 2016/17 Target Q1 Q2 Q3 Q4
K1 Patient experience of GP services I&A Framework Quality
premium
85% or a 3% increase on Jul-
16
TBC Jan 15 – Sep 15 performance = 70.5%
K2 Utilise NHS e-referral service to enable choice at 1st routine elective referral
I&A Framework Quality
premium
80% or 20% increase on
Mar-16
63.7% April 16
Not on track - AHD Note - March 16 figure is 64% so we will be looking at the 80%.
QIPP APMS Core Contract Values QIPP Plan £125,000 G Premises Costs reimbursements QIPP Plan £118,000 G Property Services QIPP Plan £274,000 G
Risks Risk Description Risk Score GP quality and Efficiency GB Assurance
Framework Failure to improve GP quality and efficiency in partnership with NHS England (current concerns are due to overall GP capacity
d l )
12
CQC inspection of practices GB Assurance Framework
Worst case scenario, a practice may be identified as so inadequate that emergency arrangements have to be enacted
12
Impact of changes to primary care support England from NHS to Capita contract
GB Assurance Framework
Issues in relation to collection and delivery of medical records, this is a national not local issue
16
To note, the following KPIs are within the I&A Framework but are not currently in publication • Primary care access • Primary care workforce
2 Unscheduled Care Lead GP: David Clitherow Lead Officer: Dominic Blaydon
Funding in 2016/17 = £60.1m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Completion of the capital Build for the Emergency Centre (Q2 2017/18)
Com Plan STP
Q4 On track - Handover from Kier planned for May 17 (currently ahead of schedule likely April 17). Once handed over, infrastructure (IT and equipment) will be put in place before cleaning ready for decant from B1.
M2 Implement new IT system Com Plan Q3 On track for Oct 16
M3 Full implementation of the Emergency Centre Model
Com Plan STP
Q3 On track - scheduled for 6th July 17
M4 Expand role of the Care Co-ordination Centre (CCC) to manage the interface between acute /community
Com Plan STP
Q3 Expansion of CCC on track but further discussions to take place around the clinician to clinician proposals still ongoing.
M5 Ensure replacement Risk Stratification Tool is in place to support the reduction in emergency admissions
Com Plan Q3 On track
Key Performance Indicators (KPIs)
K1 Contain growth in the number of non-elective admissions
Contractual target
BCF
29417 Admissions
TBC AHD Note - this is probably best coming from NHSE monitoring of our planning return. – I haven’t seen any yet which is unusual. They may be waiting till their new portal is up and running. Checked with Andy at Bassetlaw as well and he hasn’t seen anything.
K2 Contain growth in A&E attendances Contractual target
82031 Attendances
TBC As above
K3 Achieve 4 hour access standard for A&E Constitutional GB Report
95% by Q4 As at 18 07 16
91.07%
Not on track - Performance decreased April to May but steadied through June. Pressures continue to be seen within the system with May seeing the highest number of attendances (6978) at A&E for the last 2 years. The agreed A&E action plan continues to be monitored. The cumulative position for our health economy (A&E and WIC) would have achieved 94.56% for April and May against an England national position of 90.0%. Further information can be found in the GB performance report.
K4 Reduce unplanned hospitalisation for chronic Ambulatory Care Sensitive conditions
I&A Framework GB Report
1,074 TBC AHD note - Will check with EMBED exactly what this target is – think it is a rate
QIPP Delivery of A and E Assessments through the Clinical Decision Unit
QIPP Plan £286,000 G
Reducing levels of Activity growth in A&E QIPP Plan £280,000 A
Reduce IHAM NHSE growth assumption in line with local trend analysis
QIPP Plan £226,000 R
Risks Risk Description Risk Score Unscheduled Care QIPP GB Assurance
Framework Failure to deliver system wide efficiency programme for unscheduled care
20
A&E target GB Assurance Framework
Failure to meet A&E targets 16
3 Transforming Community Services
Lead GP: Phil Birks Lead Officer: Dominic Blaydon Funding in 2016/17 =£28.5m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Implement and monitor the Integrated Locality Team at the Health Village
Com Plan Q2 On track
M2 Implement and monitor the Integrated Rapid response Service
Com Plan Q2 On track - Note that staff are integrated on one site a lead has been identified but not in place as yet
M3 Completion of the Business Care for the Re-ablement Village
Com Plan Q4 On track
Key Performance Indicators (KPIs)
K1 People who have had a stroke who are admitted to the acute stroke unit in 4 hours of arrival to hospital
Quality Premium
90% national standard
50.0% Not on track – as per GB report in January 2016 – the target is not being achieved because non-elective workloads have meant that stroke beds have had to be used to accommodate medical outliers. TRFT have addressed by implementing a new policy which sets out criteria for exceptional utilisation of the Stroke Unit beds. Medical outliers on the Stroke Unit are being identified at daily bed meetings and the patient flow team has been instructed to prioritise repatriation. This policy is starting to gain traction.
K2 Emergency readmissions within 30 days of discharge from hospital
BCF GB report
10% TBC
K3 Delayed transfers of care from hospital I&A Framework BCF
GB Report Quality
Premium
Threshold = 5595 delayed
days
252.4 On track
K4 Number of unscheduled admissions of patients > 65 years out of hours
TCS reporting Threshold = -15%
TBC Waiting for data
K5 Number of A&E attendances by care home residents
TCS reporting Threshold = 1250
April / May =
270
Not on track – total number for April and May attendances were 270, continuation on this trajectory would equate to 1620 by Q4. Audit/review of the ANP Care Homes Service has been proposed
K6 GP satisfaction rate for the Integrated Community Nursing Service
TCS reporting Threshold = 80%
TBC Q4 2015/16 achieved green, awaiting data for Q1
QIPP Reducing levels of Activity in Emergency Admissions - neuro rehab, integrated rapid response and integrated locality teams
QIPP Plan £1,039,000 A
Risks Risk Description Risk Score None identified GB Assurance
Framework
4 Ambulance and Patient Transport Services
Lead GP: David Clitherow Lead Officer: Julia Massey
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Develop a process to understand the CPR performance delivered to support improved patient outcomes
Com Plan Q4 TBC Milestones to be checked with DB
M2 Improved hospital pre alert and treatment plans for patients with suspected Sepsis
Com Plan Q4 TBC Milestones to be checked with DB
Key Performance Indicators (KPIs) K1 Response to category A (Red1)
ambulance calls within 8mins I&A Framework 75% 58.7% Not on track - YAS continue to participate
in an NHS England-led Ambulance Response Programme (ARP), which went live from the 21st April 2016. The pilot will run for 3 months initially with evidence reviewed on a bi weekly basis. This review involves a change in how calls are recorded from the previous current Red/Green system. Given the YAS participation in the pilot, the CCG is not in a position to report the Ambulance constitutional standards at this point in time.
QIPP None identified
Risks Risk Description Risk Score Ambulance Targets GB Assurance
Framework Failure of YAS to achieve RED 1 8 minute Target at CCG level and Yorkshire & Humber wide
20
5 Clinical Referrals (Diabetes is a clinical priority within the I&A Framework)
Lead GP: Anand Barmade Lead Officer: Janet Sinclair-Pinder Funding in 2016/17 = £66.7m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Implement 10 clinical thresholds Com Plan Q4 On track M2 Extension of virtual clinics from
haematology to other areas such as endocrinology
Com Plan Q2 On track
M3 Delivery of agreed audit programme and implementation of recommendations (6 in 2016/17 – 4 clinical thresholds, 1 cancer, 1 emergency admissions)
Com Plan Q4 On track
M4 Review and implement Rotherham Diabetes Care model around the Portsmouth care model which focuses around “super six” care.
Com Plan Q4 On track
Key Performance Indicators (KPIs) K1 Patients waiting 18 weeks or less from
referral to hospital treatment Constitution /
I&A Framework GB Report
92% 95.1% - % Patients on incomplete non-emergency pathways waiting no more than 18 weeks
K2 Contain growth in elective activity Contractual 39671 Spells TBC AHD note - This is probably best coming from NHSE monitoring of our planning return. – I haven’t seen any yet which is unusual. They may be waiting till their new portal is up and running. Checked with Andy at Bassetlaw as well and he hasn’t seen anything.
K3 Achievement of outpatient follow up ratios
Contractual TBC TBC AHD note - May need to reconsider – target is specialty level not overall
QIPP Reduction in follow-ups where TRFT are above peer average
QIPP Plan £816,000 G
Reducing levels of Activity growth in direct access pathology in line with clinical pathways
QIPP Plan £73,000 R
Reduce IHAM NHSE growth assumption in line with local trend analysis
QIPP Plan £509,000 G
Risks Risk Description Risk Score Planned Care QIPP GB Assurance
Framework Failure to deliver system wide efficiency programme for planned care
20
6 Medicines Management
Lead GP: Avanthi Gunasekera Lead Officer: Stuart Lakin Funding in 2016/17 =£48.0m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Potential savings of £447,500 have been identified by the introduction of a range of branded generic drugs. This figure will be adjusted as further schemes evolve. A target of 90% compliance has been set = annual savings £402,750.
Meds Management
Priority
90% Progress May 2016
Octasa 26%, Biquille 79%, Neditol 35%, Repinex 19.3%
M2 12 projects to be delivered over the financial year two have been completed £273,000 savings identified this figure will evolve has schemes are still being evaluated
Meds Management
Priority
12 projects Two schemes have been completed and have delivered £103,456.
M3 6 practices to have committed to become waste beacons and have begum the transformational work plan by September 2016. 9 practices have committed to the programme and timescales
Meds Management
Priority
Q3 TBC No figures will be available until Q3.
Key Performance Indicators (KPIs) K1 Reduction in the number of antibiotics
prescribed in primary care Quality
premium / I&A Framework /
GB Report
4% reduction or 1.161 items per
STAR-PU
1.192 On track
K2 Appropriate prescribing of broad spectrum antibiotics in primary care
Quality premium / I&A Framework /
GB Report
lower than 10%, or to reduce by 20% from each CCG’s 2014/15
value
8.5 On track
K3 Number of finance and quality “green” indictors
Meds Management
75% og 1302 indicators to be
green 976
552 (42%) Green
On track
QIPP Medicines Waste reduction QIPP Plan £700,000 A Medicines Management QIPP QIPP Plan £550,000 A Branded Generics QIPP Plan £250,000 G Rebates and contract efficiencies. QIPP Plan £200,000 G Do not prescribe QIPP Plan £150,000 A Nationally Negotiated Price Reductions QIPP Plan £1,000,000 A Service redesign - Nutrition/Gluten Free QIPP Plan £90,000 A UNIDENTIFIED QIPP Plan £190,000 R
Risks Risk Description Risk Score Prescribing QIPP GB Assurance
Framework Failure to deliver system wide efficiency programme for prescribing
20
7 Mental Health (Mental Health and Dementia are clinical priorities within the I&A Framework) Lead GP: Russell Brynes (Adults) Richard Cullen (Childrens) Lead Officer: Kate Tufnell (Adults) Nigel Parkes (Childrens)
Funding in 2016/17 =£35.0m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Externally evaluate Adult Mental Health Liaison and MH Social Prescribing programmes
Com Plan STP
Q3 On track
M2 RDaSH to produce a delivery plan including milestones and timescales for the delivery of the Adult Transformation Plan
Com Plan Q3 On track
M3 Dementia – Implement and evaluation the Dementia LES
Com Plan Q3 On track
M4 Children and Young People - All children and young people will follow the agreed process in transitioning to adult services and all will have a transition plan in place.
Com Plan STP
Q4 On track
M5 Review of out of area placements in partnership with RDASH
Com Plan STP
Q2 On track
Key Performance Indicators (KPIs) K1 People with 1st episode of psychosis
starting treatment with a NICE- recommended package of care treated within 2 weeks of referral
I& A Framework STP
GB report
50% 72.9% On track
K2 Percentage of people who are "moving to recovery" of those who have completed IAPT treatment
I&A Framework GB Report
Quality Premium
51.3% 47.6% at the end of
Q1
Not on track - IAPT remedial discussions are on-going. Steps are being taken to increase clinical and administration staff capacity to cover vacancy and lost capacity. A move to self-referral has been proposed by RDASH to address the extremely high attrition and DNA rates.
K3 Diagnosis rate for people with dementia, as a percentage of the estimated prevalence
GB Report I&A Framework
67% 72.9% On track
K4 Proportion of people waiting 6 weeks or less from referral to entering a course of IAPT treatment
GB Report I&A Framework
75% 71.8% Started but not on track, As no. 2
K5 95% of children and young people who present at A&E in crisis will be seen within 1 hour
STP Com plan
No existing data – awaiting
STP
TBC No data for Q1
K6 95% of adults who present at A&E in crisis will be seen within 1 hour
STP Com plan
No existing data – awaiting
STP
TBC No data for Q1
QIPP MH and LD – joint risk share with RDASH to reduce the Out of Area activity
QIPP Plan £369,000 R
Risks Risk Description Risk Score IAPT Waiting Times GB Assurance
Framework Failure to deliver the National IAPT waiting times standards for 6 and 18 weeks
16
CAMHS Reconfiguration GB Assurance Framework
Inability to deliver CAMHS reconfiguration in a timely manner
16
CAMHS Transformation GB Assurance Framework
Delivery of the CAMHS Local Transformation Plan 12
8 Learning Disability (Learning Disabilities is a clinical priority within the I&A Framework)
Lead GP: : Russell Brynes (Adults) Richard Cullen (Childrens) Lead Officer: Kate Tufnell
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Deliver the required number of bed reductions as per Rotherham element of the plan
Com plan Q4 On track
M2 Deliver GP training to support the Annual Health check DES
Com plan Q2 On track
Key Performance Indicators (KPIs)
K1 Ensure that patients receive a CTR prior to a planned admission to an Assessment and Treatment Unit or mental health inpatients
Com Plan STP
95% On track
K2 Ensure that patients in an Assessment and Treatment Unit receive a Care and Treatment Review (CTR) every 6 months
Com Plan STP
100% On track. Note that of the 5 patients, 4 received a CTR and 1 (due to the complexity of the individual who was transferring from hospital to hospital) received a more in-depth CTR
K3 Reduce the number of people admitted in line with the South Yorkshire and North Lincolnshire LD TCP trajectory
Local Reporting Target = 3 – CCG funded
LD beds
5 – NHSE funded secure
LD beds
On track – position as at July data – 4 and 4
QIPP Review of Assessment and Treatment Unit capacity in block purchase or spot purchase
QIPP Plan £483,000 G
Risks Risk Description Risk Score None identified GB Assurance
Framework
To note, the following KPIs are within the I&A Framework but are not currently in publication • % of people with a learning disability on a GP register having annual health check • Reliance on specialist inpatient care for people with learning disability/autism
9 Maternity and Children’s Services (Maternity is a clinical priorities within the I&A Framework)
Lead GP: Richard Cullen Lead Officer: Emma Royle
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Complete a gap analysis and ‘next steps’ against the National Maternity Review: Better Births
Com Plan
Q3 On track - TRFT have undertaken a gap analysis which they will share once it has been through their governance structure.
M2 Complete a revised strategy and service specification for maternity services
Com Plan
Q3 On track - The strategy is complete, and will be sent to the CCG DCO and Assistant Joint Director of Commissioning and Performance for comment. It will then go through the CCG governance structure. The service Specification is in development.
M3 Develop a new community services specifications including children’s community nursing and specialist nurses to support the Care Closer to Home work-stream
Com Plan
Q3 On track - Consultation has taken place with staff, and the parent carers forum are undertaking a consultation exercise. Work is taking place with the Deputy Chief Nurse, who will be key to its development.
Key Performance Indicators (KPIs)
K1 Reduce the number of neonatal mortality and still births
I&A Framework Outcomes
Framework
TBC TBC Latest position is 8 in 2013
K2 % of children aged 10-11 classified as overweight or obese
I&A Framework Public Health
TBC TBC Latest position is 35.3% in 2014/15
K3 Maternal smoking at delivery I&A Framework Public Health
TBC TBC Latest position is 19.3% at Q3 2015/16
K4 Improve Women’s experience of maternity services (national maternity services survey)
I&A Framework Outcomes
Framework
TBC TBC Not currently in publication
K5 Emergency admissions for children with lower respiratory tract infections
I&A Framework 541.8 TBC Latest position is 541.8 in 2014/15
K6 Unplanned hospitalisation for asthma, diabetes and epilepsy in under 19’s
I&A Framework 364 TBC Latest position is 364.0 in 2014/15
QIPP None identified
Risks Risk Description Risk Score Health Assessments for Children in Care GB Assurance
Framework NHS RCCG reputation as responsible commissioner for Children in Care - not having initial health assessments within statutory framework
12
10 Continuing Care and Funded Nursing Care Lead GP: Richard Cullen Lead Officer: Alun Windle
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Put in place a comprehensive range of agreed local policies and protocols in line with any contemporary guidance
CHC Standards AQuA
Assurance Report
Adults November
On track
Children September
On track
M2 Develop a CHC training package for health and social care staff regarding local process and provision of CHC
CHC Standards AQuA
Assurance Report
Q4 On track
M3 Implement processes fit for purpose with identified panels having an appropriate number, scope, size and membership
CHC Standards AQuA
Assurance Report
Adults Q1
On track
Children Q3
On track
Key Performance Indicators (KPIs) K1 People eligible for standard NHS
continuing healthcare I&A Framework
GB report TBC TBC Not currently in publication
K2 Personal Health Budgets I&A Framework GB report
TBC TBC Not currently in publication
K3 Patients in receipt of CHC will have a completed annual review
CHC Key Performance
Indicators
Adults 25-30%
outstanding
Children 0%
outstanding
K4 Patients referred by Fast Track referral will receive a funding decision within 48 hours
CHC Key Performance
Indicators
100% Q4
K5 Patients requiring a Continuing Healthcare assessment will have an eligibility assessment within 28 days from the receipt of the continuing healthcare checklist - Adults
CHC Key Performance
Indicators
100% Q4
Started but not on track - increased focus on implementation and monitoring of the national framework, it is anticipated that it will gain traction.
K6 Patients requiring a Continuing Healthcare assessment will have an eligibility assessment within 6 weeks from the receipt of the continuing healthcare checklist – Childrens
CHC Key Performance
Indicators
100% Q4
Started but not on track - increased focus on implementation and monitoring of the national framework, it is anticipated that it will gain traction.
QIPP Review of Children's CHC packages QIPP Plan £250,000 A Review of Assessment tool for determining care packages
QIPP Plan £150,000 A
Review of High Cost Care packages QIPP Plan £100,000 A Risks Risk Description Risk Score
Equipment via IFR/CHC GB Assurance Framework
Equipment provided by RCCG via IFR/CHC - failure to have a procurement service to ensure cost effectiveness and service that ensures that the purchased equipment has a record of maintained and safety.
15
11 End of Life Care (EOLC)
Lead GP: Avanthi Gunasekera Lead Officer: Nigel Parkes Funding in 2016/17 =£3.0m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Involvement of the Care Co-ordination Centre in the EOLC pathway
Com Plan Q4 Not on track - discussions still take place on implementation.
M2 Achieve 40% implementation of the Case Management Palliative Care Template in Primary Care
Com Plan Q4 Started but not on track, target = Q2 20%, Q3 30%, Q4 40%. The decision for this to be part of the case management template was taken recently so implementation is just taking traction.
Key Performance Indicators (KPIs)
K1 Percentage of deaths which take place in hospital
I&A Framework GB Report
TBC TBC 2014/15 Q4 - 2015/16 Q3 – latest data - 48.8%. AHD - Can’t immediately find a target for this – perhaps a reduction
K2 Percentage of deaths not in hospital Public health 54% by Q4 TBC On track - Please note - 5 month lag on data. 2016 has started well with January to March all above 2015 average and above 2015 January to March values. This has maintained the upturn in the 12 month moving averages. However, January and February are provisional and March and April are incomplete therefore liable to change. Q1 2016 provisional = 55%
QIPP None identified
Risks Risk Description Risk Score None identified GB Assurance
Framework
12 Specialised Services
Lead GP: Richard Cullen Lead Officer: Jacqui Tufnell
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Ensure robust arrangements for tier 3 Obesity in readiness for the transfer of tier 4 bariatric surgery in collaboration with public health
Com Plan Q4 On track
Key Performance Indicators (KPIs) K1 n/a No KPIs
QIPP None identified
Risks Risk Description Risk Score Collaborative commissioning GB Assurance
Framework Effective collaborative commissioning of specialised services
12
13 Joint Work – local and Regional
Lead GP: Julie Kitlowski Lead Officer: Dominic Blaydon Funding in 2016/17 = BCF is £24.3m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Develop and deliver the STP STP Q3 On track M2 Develop and deliver the local place
based plan STP Q3 On track
M3 Oversee the implementation of the BCF with RMBC
Com Plan / BCF Plan
Q4 On track
Key Performance Indicators (KPIs) K1 Achievement of BCF KPIs – see BCF Plan Com Plan / BCF
Plan Q4 Please see BCF page of GB report
QIPP None identified
Risks Risk Description Risk Score Funding for BCF GB Assurance
Framework Resources reduced through introduction of BCF 12
14 Child Sexual Exploitation
Lead GP: Lead Officer:
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 As part of the annual update for GPs and practice staff, ensure minimum training level 3 is delivered
Com Plan Q1 On track
M2 Offer the same training as above to the remainder of primary care, social care and providers
Com Plan Q1 On track
M3 Provide ongoing support to current and emerging SYP and NCA historic investigations
Com Plan Q1-Q4 On track
M4 Provide 2 members to be part of the Multi Agency Safeguarding Hub team
Com Plan Q1- Q4 On track
Key Performance Indicators (KPIs) K1 None identified
QIPP None identified
Risks Risk Description Risk Score None identified GB Assurance
Framework
15 Cancer (Cancer is a clinical priorities within the I&A Framework)
Lead GP: Richard Cullen Lead Officer: Janet Sinclair-Pinder
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Support on-going delivery of the TRFT Cancer Improvement action plan focusing on one year survival rates.
Com Plan STP
Q4 On track
M2 Implementation of NICE Cancer Guidelines
Com Plan STP
Q4 On track
M3 Fully engage with the Macmillan Living With and Beyond Cancer (LWABC) Programme to identify gaps in service and develop an action plan
Com Plan STP
Q3 On track
M4 Focus work on awareness raising / early diagnosis / 2 week wait
Com Plan STP
Q3 On track
Key Performance Indicators (KPIs) K1 Cancer (all) diagnosed at stage 1 and 2 I&A Framework
Quality Premium
>60% or 4 % point
improvement
36.5% Off track but inconclusive as the latest reporting period was 2014
K2 Percentage seen within 2 weeks following an urgent referral by GP for suspected cancer
GB Report 93% 95.9% On track - EMBED are producing a new cancer dashboard – AHD / DJ have access
K3 Percentage seen within 62 days after a referral by GP
Quality Premium
I&A Framework
85% 82.4% Not on track - 62 day GP RTT target was under the national standard of 85% at 82.4%, a decrease from March position of 84.21%. TRFT performance dropped from March 96.2% to April 89.0% but were still within the national standard. National performance as at Q4 15/16 was 81.9%. There were 9 breaches in April for RCCG patients: • 3 due to inadequate elective capacity, 2
of these at Sheffield Teaching FT, 1 at Rotherham FT.
• 5 due to pathway delays, 4 between Rotherham FT and Sheffield Teaching FT. 1 within Rotherham FT only.
K4 Patient satisfaction rates >89% (Secondary care)
Com Plan STP
Q1 On track – note this is annual data
K5 Percentage of patients satisfied with support from their GP during treatment >66%
Com Plan STP
Q1 On track – note this is annual data
QIPP None identified
Risks Risk Description Risk Score None identified GB Assurance
Framework
To note, the following KPIs are within the I&A Framework but are not currently in publication • Cancer one year survival rates – 2013 data • Cancer patient experience – 2014 data
Glossary (AHD refers to Alex Henderson-Dunk, DB refers to Dominic Blaydon)
APMS Alternative Provider Medical Services BCF Better Care Fund CCC Care Co-ordination Centre CHC Continuing Healthcare
CAMHS Child and Adolescent Mental Health Services CQC Care Quality Commission EOLC End of Life Care GB Governing Body IFR Individual Funding Request I&A Improvement and Assessment LES Local Enhanced Services ‘Q’ ‘Quarter’
QIPP Quality Innovation Productivity and Prevention RMBC Rotherham Metropolitan Borough Council STP Sustainability and Transformation Plan TRFT The Rotherham Foundation Trust WIC Walk in Centre