CMS Barrel Resistive Plate Chambers - from Assembly to Operation

Post on 06-Jan-2016

51 views 1 download

description

CMS Barrel Resistive Plate Chambers - from Assembly to Operation. ANTON DIMITROV. CMS. Muon System. Barrel 5 Wheels (-2,-1,0,1,2) 12 Sectors 4 Stations (RB 1,2,3,4) 2 RPC in station => 480 Barrel chambers in total. Resistive Plate Chambers. Single Gap. Readout strips. -HV. - PowerPoint PPT Presentation

Transcript of CMS Barrel Resistive Plate Chambers - from Assembly to Operation

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

CMS Barrel Resistive Plate Chambers -

from Assembly to Operation

ANTON DIMITROV

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

CMS

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Muon System

Barrel

5 Wheels (-2,-1,0,1,2)

12 Sectors

4 Stations (RB 1,2,3,4)

2 RPC in station

=> 480 Barrel chambers in total

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Resistive Plate Chambers

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Double Gap DesignSingle Gap

Single Gap

Readout strips

FW - up BW - up

FW - down BW - down

GAS GAP GAS GAP

GAS GAP GAS GAP

HV electrodes (graphite)

Bakelite

Signal Strips

Gas

-HV

-HV

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

RPC Test Overview

1) Cosmic Tests after chamber construction – Bari, Pavia, Sofia

2) Transportation to CERN – Quality test at ISR

3) Coupling – test after coupling

4) Test after transportation to SX5

5) Chamber Installation – Precommissioning test after installation

6) Final Cabling – test after final cabling

7) Lowering down the wheel – test after the lowering

8) LV Test after the cabling, test of DCS cables.

9) Tower Test

10) MTCC

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Barrel production

GTHT

Bari

Pavia

Sofia

ISR

Chamber Test Sites

RB1 in Pavia

RB2 & RB4 in Bari

RB3 in Sofia (& Bari)

120 RB1 at HT

240 RB2 and RB4 at GT

120 RB3 in Sofia (& Bari)

Double gap

GT

Chambers production and quality

certification involve several steps.

China

Single gap

Chamber Assembling Sites

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

1.RPC Tests with Cosmics

Trigger scintillator

Trigger scintillator

RPC

μ

1. Efficiency2. Cluster size3. Noise rate4. Dark Current

Main RPC Parameters:

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Trigger System - Bari

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Main RPC Parameters

Trigger scintillator

Trigger scintillator

RPC

μ

1. Efficiency2. Cluster size3. Noise rate4. Dark Current

Main RPC Parameters:

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

RPC Parameters

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

CMS Requirements

≤ 45 %Humidity

≤ 5 Hz/cm2Intrinsic Noise Rate

≥ 1 kHz/cm2Rate Capability

≥ 95 %Efficiency

≤ 2 nsTime Resolution

CMS RequirementsItem

≥ 300 VHV Plateau

≤ 10 %Streamer Probability

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

RPC Results 2006

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

RPC Results 2006

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

2.Transportation to CERN

ISR RPC storage and test area

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

2.Quality Tests at ISR Final dressing

Final cooling HV connectors Temperature sensors

Detector control Gas leak Threshold setting and reading Current vs. HV Long stability test (15-20 days @

9200 V) Gas input overpressure test

Performance Noise rate (cluster count.) vs. HV

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

RPC – current stability

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Noise rate performance

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

3.Coupling DT - RPC

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

4.Transportation to SX5

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Before Installation

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

5.Chamber Installation

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

5.Chamber Installation

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

5.Chamber Installation

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

5.After Installation

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

5.Test after Installation

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

5.Precommissioning at SX5

Gas system Commissioning of the

final gas distributor Gas line equalization

HV test Current vs HV,

current stability for 48 hours

LV test Thresholds

reading/writing Noise measurement Front-end electronics Strip connectivity

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Precommissioning Results

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Precommissioning Results

Initial Behaviour After the change of the HV connector

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Precommissioning Results

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Precommissioning Results

RB4++_down

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

6.Final Cabling

HV cablesLV cablesDCS cablesSignal cables

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Final Cabling Test

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

HV Cable Problem

Return wires

HV wires

shield

7,5 mm

Plastic jacket

shield

Al/PET

HV wires Slide by D. Piccolo

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

On detector HV cables Problem

First pre-production 40 cableswith correct connections. Starting from the final productionthe connections were inverted !!

gnd

HV wires (thicker) Return wires (thiner)

gndCorrectconnection

Test done at factory:- Continuity test pin to pin- HV test at 15 KV

gnd gnd

HV wires (thicker) Return wires

Wrongconnection

Slide by D. Piccolo

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Present Status

Produced ChambersProduced Chambers 485485

InstalledInstalled 462462

Ready for installationReady for installation 1818

ReinstalledReinstalled 33

SpareSpare 22

Chamber Production and Cosmic Ray Tests are finished!

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Tower Test

Newly established procedure for detector performance, using the final rpc/trigger system:

Strip Connectivity TestSignal Cable Check OutNoise rate as a function of HV and threshold.

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Noise histogram

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Strip Connectivity Test

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

MTCC

Magnet TestTest Magnet Functionality – cooling, supply, control systemsMagnet mapping

Cosmic ChallengeReading & Synchronization signals from all subdetectorsTest of the Muon System – RPC, DT, CSCTest of the “cosmic” triggerVerification of Chamber Performance

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

MTCC Phases

MTCC I – Local DAQ (Tracker, DT, RPC, CSC)Link Boards, Synchronization, Data TakingBarrel – One Sector (10) in Wheel+1 and One Sector (10) in Wheel+2

MTCC II – Global DAQ (Ecal, Hcal, DT, RPC and CSC included)Barrel – Two Sectors (10&11) in Wheel+2 and One Sector (10) in Wheel+1

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

MTCC Event

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Noise profile

Noisy FEB before threshold setting

The same FEB after setting of thresholdsPlots by Roselli

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Noise study for a single chamber

RB2IN-B wheel1-RB2IN-B wheel1-

Sector10Sector10

1.1. Noise distribution Noise distribution

calculated on the calculated on the

entire period of entire period of

the MTCC. the MTCC.

2.2. Noise ProfileNoise Profile

Figure 1

Including all the runsIncluding all the runs

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Preliminary Results – Local and Global

EfficiencyRPC

DT

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

MTCC Efficiency

Slide by Tupputi

HV at 50 % efficiency

DT-RPC alignment is needed

5 – 10 June 2007 Primorsko, Bulgaria

National ConferenceOn Particle Physics II

Anton Dimitrov

Conclusions Cosmic Ray Tests in Bari/Pavia/Sofia are

finished Chamber Production is finished 462 Chambers Installed in CMS 18 Chambers Ready for Installation All Five Wheels are fully precommissioned Tests in the underground cavern started Tower Test with the final rpc/trigger chain

initialized MTCC Data are being processed