City of Black Hawk Water Hammer September 2002

Arber

Water Hammer

Travis Meyer, P.E.Richard P. Arber Associates

City of Black Hawk Water Hammer September 2002

Arber INTRODUCTION

• Background• Water Hammer Modeling• System Improvements• Results• Conclusions

City of Black Hawk Water Hammer September 2002

ArberCity of Black HawkDistribution System

1

2

3

4

5

Pressure Reducing StationPump Station

Dory HillTank

MesaTank

City of Black Hawk Water Hammer September 2002

Arber Distribution System ProfileGradeHydraulic Grade Pressure Reducing Station

Dory Hill Tank (8375 ft)

Mesa Tank

(8775 ft)

1

2

3 140psi

120/40

160/70

34

5

140/90

140/65

70

Pump Station

Pump Suction Line

City of Black Hawk Water Hammer September 2002

Arber Problem

City of Black Hawk Water Hammer September 2002

Arber Water Hammer - Causes

• Sudden Velocity Change– fire hydrant– fire sprinkler system– pumps

• Vapor Cavity Formation– pressure down surge at a low

pressure dead end

• Equipment Malfunction– fire hydrants, valves, PRVs

City of Black Hawk Water Hammer September 2002

ArberSURGE 5 MODEL

SUDDEN VALVE CLOSURE

50

100

150

200

250

300

-5 0 5 10 15 20 25 30 35 40 45 50 55 60

Time (seconds) - Valve closure initiated at Time 0

Pre

ss

ure

(p

si)

1" Pressure Relief Valve

2" Pressure Relief Valve

3" Pressure Relief Valve

No Pressure Relief

2,000 GPM TO 0 GPM IN 3 SECONDS

City of Black Hawk Water Hammer September 2002

ArberSURGE 5 MODEL

SUDDEN VALVE OPENING

-50

0

50

100

150

200

-5 0 5 10 15 20 25 30 35 40 45 50 55 60

Time (seconds) - Demand change initiated at Time 0

Pre

ss

ure

(p

si)

Main St & Mill St

Lodge Garage

Dory Hill PRV Station

Pump Station

Vapor Cavity Formation

Vapor Cavity Collapse

Model Not Valid Beyond This Line

0 GPM TO 2,000 GPM IN 3 SECONDS

City of Black Hawk Water Hammer September 2002

ArberSURGE 5 MODEL

SUDDEN VALVE OPENING

-50

0

50

100

150

200

-5 0 5 10 15 20 25 30 35 40 45 50 55 60

Time (seconds) - Demand change initiated at Time 0

Pre

ssu

re (

psi

)

Lodge Garage

Main St & Mill St

Dory Hill PRV Station

0 GPM TO 2,000 GPM IN 3 SECONDS

PUMP SUCTION ISOLATED

City of Black Hawk Water Hammer September 2002

ArberWater Hammer Modeling

Conclusions

• Sudden Large Demand Changes Can Initiate a Water Hammer Event

• Vapor Cavity Formation and Collapse Can Occur in the Pump Suction Line

• Unable to Model PRV Behavior During Water Hammer– Cause of Extended Hammers?

City of Black Hawk Water Hammer September 2002

Arber Water Hammer - Solutions

• Sudden Velocity Changes– Pressure Relief Valves– Surge Tanks– Surge Anticipation Valves– Standpipe

• Vapor Cavity Formation– Eliminate Low Pressure Dead

Ends– Connect System High Points to

Open Tanks

City of Black Hawk Water Hammer September 2002

ArberRecommended Improvements

• Reconfigure Pump Suction to Eliminate Possibility of Vapor Cavity Formation and Collapse

• Install Pressure Relief Valves in Pressure Zones 3 and 4

• Reconfigure Existing, Unused 12” Pipe as a Standpipe

• Optimize PRV Settings• Lower System Pressures• Require Surge Tanks for New

Construction with Fire Service

City of Black Hawk Water Hammer September 2002

Arber System Improvements

1

2

3

4

5

6

Pressure Reducing Stationwith Pressure Relief ValvePump Station

Standpipe

City of Black Hawk Water Hammer September 2002

Arber System ImprovementsGradeHydraulic Grade Pressure Reducing Station

Dory Hill Tank (8375 ft)

Mesa Tank

(8775 ft)

1

2

3

120/40

160/70

34

5

140/90

140/65

70

Pump Station

Pump Suction Line

City of Black Hawk Water Hammer September 2002

Arber Initial Implementationof Improvements

• Isolated Pump Suction Line• Installed Temporary

Pressure Relief Valves• Put Locks on Fire Hydrants• Lowered System Pressures

Where Possible (Zone 4)

City of Black Hawk Water Hammer September 2002

Arber Initial Implementation

City of Black Hawk Water Hammer September 2002

Arber Initial Implementation

City of Black Hawk Water Hammer September 2002

Arber Water Hammer Test

• Fire Dept Indicated That One Fire Hydrant Always Seemed to Cause Water Hammer

• Initiated a Water Hammer Event on Purpose

• Monitored System Pressures and PRV Behavior During Water Hammer

City of Black Hawk Water Hammer September 2002

Arber Water Hammer Test

City of Black Hawk Water Hammer September 2002

Arber Water Hammer TestConclusions

• Damaged Stem Extension on Fire Hydrant– City Subsequently Inspected

All Fire Hydrants for Damage

• Pressure Regulating Valves– Appeared to Operate Smoothly

During Water Hammer

City of Black Hawk Water Hammer September 2002

Arber Final Implementationof Improvements

• Pump Suction Line Reconfigured

• Standpipe On-Line• Two New PRV Stations with

Pressure Relief Valves On-Line

• System Pressures Lowered to Final Levels

City of Black Hawk Water Hammer September 2002

Arber Another Water Hammer

City of Black Hawk Water Hammer September 2002

Arber Probable Cause

• Contractor Started Work Approximately Same Time as Water Hammer– May Have Filled Water Truck

from Fire Hydrant

• Pressure Regulating Valve– Corrosion Buildup on Stem

Guide Caused Valve to Stick and Operate Unevenly

City of Black Hawk Water Hammer September 2002

Arber Another Water Hammer

City of Black Hawk Water Hammer September 2002

Arber Final Adjustments - PRV Stations

Pressure Zone

PrimarySupply100 psi

SecondarySupply95 psi

EmergencySupply90 psi

Pressure Zone

100 psi 100 psi

100 psi

City of Black Hawk Water Hammer September 2002

Arber Success!!??

City of Black Hawk Water Hammer September 2002

Arber Conclusions

• To Avoid Water Hammer– Eliminate Potential for Vapor

Cavity Formation (Low Pressure Dead-End Lines)

– Maintain Fire Hydrants, System Valves, Fire Protection Systems, Pressure Regulating Valves for Proper Operation

– Try Alternate PRV Strategy for Multiple PRV Pressure Zones

City of Black Hawk Water Hammer September 2002

Arber Conclusions

• To Protect System and Customers– Install Pressure Relief Valves– Install Standpipes– Require Surge Tanks on Fire

Service Taps– Lower System Pressure

City of Black Hawk Water Hammer September 2002

Arber Proud Papa

Jeffrey - Born 9/10/02