Post on 06-May-2015
10 Fire-Resistive
Construction
Objectives (1 of 2)
• Recall the difference between noncombustible and fire-resistive construction
• Describe different types of concrete structural systems
• Describe the two types of prestressing
10
Objectives (2 of 2)
• Contrast precast and site-cast concrete
• Describe the hazards of formwork
• Describe the methods of fireproofing steel and of ensuring a level fire resistance in concrete
• Detail how compartmentation works to prevent the spread of fire
10
Introduction
• Fire-resistive construction
• Considered to be the best
• Most resistant to collapse and does not contribute fuel to a fire
• Is given the largest permissible area and heights
10
Concrete
• Cementatious material produced by a chemical reaction
• Cures indefinitely; low temperatures retard the curing of concrete
• Weak in tensile strength and has poor shear resistance
10
Concrete Structures Pre-World War II
• Suitable only for structures in which aesthetics played little part
• Built of steel frames and fireproofed with concrete
• Cinder blocks use cinders as the aggregate
• Concrete blocks use other materials for aggregate
10
Underwriters Blocks
• Concrete blocks produced under Underwriters Laboratories’ classification
• Manufacturer’s certificate gives the type and number of units delivered to a specific job
• Blocks must meet fire resistance standards
10
Today’s Variety of Concrete Structures
• Use variety of building construction elements
• Steel-framed buildings now often have cast-in-place concrete floors
• Precast concrete and prefabricated metal wall panels and decorative brick veneer are common
10
Steel vs. Concrete Framing
• Designer preferences
• Some design in steel
• Others prefer concrete
• Some buildings concrete-framed and steel-framed mixed together
10
Fire Department Problems
• Problems with concrete construction
• Collapse during construction with no fire
• Fire during construction
• Fire in completed, occupied buildings
10
Types of Concrete Construction
• Cast-in-place
• Plain, reinforced, and post-tensioned concrete
• Precast
• Plain, reinforced, and pretension concrete
10
Concrete Definitions (1 of 5)
• Aggregate
• Cast-in-place concrete
• Casting
• Chairs
• Composite and combination columns
10
Concrete Definitions (2 of 5)
• Composite construction
• Continuous casting
• Continuous slipforming
• Drop panels
• Flat plate structural system (or continuous beam)
10
Concrete Definitions (3 of 5)
• Footings
• Lally columns
• Lift slab
• Monolithic construction
• Mushroom caps
10
Concrete Definitions (4 of 5)
• One-way structural system
• Plain concrete
• Pretensioning and post-tensioning
• Precast concrete
• Reinforced concrete
• Reinforcing bars or rods
10
Concrete Definitions (5 of 5)
• Slipforming
• Spalling
• Temperature rods
• Two-way structural system
10
Concrete Structural Elements
• Columns
• Beams (including t-beams) and girders
• Concrete floors
10
Virtue of Columns
• High compressive strength and low cost
• Columns are of reinforced concrete
• Steel reinforcing rods carry some of the compressive load
• The compressive strength of steel is many times that of concrete
10
Increasing Column Sizes
• Unsatisfactory in modern construction
• The useable area would vary from floor to floor
• Overcome by increasing the size of the reinforcing steel as the loads increase
10
Reinforcing Rods
• Long with a relatively thin diameter
• Ends of rods are connected
• Ties or hoops join the rods in a column
• Ties cut the long slender column into a number of relatively short columns
10
Beams and Girding (1 of 3)
• Plain concrete beam
• Strong in compression, weak in shear
• No tensile strength
• When a beam is loaded, it deflects
• Deflection brings compression in the top of the beam and tension in the bottom of the beam
10
Beams and Girding (2 of 3)
• Cantilever beam
• Tension is in the top of the beam
• Reinforcing rods are in the top of the beam
10
Beams and Girding (3 of 3)
• Continuous beam
• Supported at more than two points
• Tension in the top of the beam in the area over the tops of the columns
• Tension in the bottom of the beams between columns
10
T-Beams
• There is neither tension nor compression in the beam
• Has the neutral plane coincide with the bottom of the wide, thin floor slab
• Double T’s are floor slab and beam combinations with two beams
10
Concrete Floors
• First used for leveling brick and tile arch floors
• Early floors built of individual beams supporting a floor slab
• Hollow tiles lightened concrete floors
10
Waffle Concrete
• Closely spaced beams are set at right angles to one another
• Unnecessary concrete is formed out
10
Lighter Construction
• Floor may be just a flat plate
• This gives a smooth surface
• Easily finished
10
Left-In-Place Form
• Occurs when concrete floors are cast onto corrugated steel
• The steel provides necessary tensile strength
• If the bond fails, the floor section may fail
10
Precast T-Beam Units
• Additional concrete is often cast-in-place on top of the units
• Entire unit becomes an integral beam-and-floor element
• Cylindrical openings can be cast lengthwise through the units to remove unnecessary weight
10
Older Building Codes
• Concrete floor can be in ordinary construction
• Case example: Concrete topping over wood beams concealed the destruction of the beams by fire. Four fire fighters died
10
One-Hour-Rated Designs of Wood Floors
• Lightweight concrete topping as much as 1 to 1 1/2 inches thick
• Thickness retards the passage of heat through the floor
• National Fire Protection Association (NFPA) 251 (American Society of Testing and Materials (ASTM) E119) fire resistance standard
10
Cast-In-Place Concrete Floor
• Can be a hazard during construction
• A slot is left in the wall at the point where the floor is to be cast
• If a windstorm occurs during the time that the slot is open, a collapse may result
10
Concrete Floors in Steel Buildings
• May be precast or cast-in-place
• May be only load-bearing or provide structural stability
10
Concrete Floors in Cast-In-Place, Concrete-Framed Buildings
• Cast integrally with columns
• Provide a monolithic rigid-framed building
• May be pinned
• May be connected as a monolithic unit
10
When Slabs Are Laid Down
• A space is left between them
• Protruding bars of one slab extend past the ends of the protruding bars of the other slab
• The sections are joined by a wet joint
10
Concrete Floors in Precast, Pinned Concrete Buildings
• May not contribute to the building’s structural stability
• Precast columns are often built with haunches or shelves
• Steel plates imbedded in the concrete may be welded together
10
Prestressed Concrete
• Recently developed
• Engineered stresses placed in architectural and structural concrete
• Analogy: A row of books side by side, before and after being threaded together with wire
10
Special High-Strength, Cold-Drawn Steel Cables
• Similar to those used for suspension bridges
• These or alloy steel bars are commonly used in prestressed concrete
• Known as tendons, but also called strands or cables
10
High-Tensile-Strength Wire
• Ordinarily used for prestressing
• More sensitive to high temperatures than structural steel
• Complete loss of prestress at 800°F
10
Two Methods of Prestressing (1 of 2)
• Pretensioning
• Done in a plant
• High-tensile-strength steel strands are stretched between the ends of a form
• After processing, stretched strands draw back, thus compressing the concrete
10
Two Methods of Prestressing (2 of 2)
• Post-tensioning
• Done on the job site
• High-tensile-steel strand wires are positioned in the forms
• After processing, steel tendons are stretched and anchored at the ends of the unit
10
Bridge Girders
• Some are tensioned enough to make shipment possible, then post-tensioned after being placed
• Cement paste might be forced into the space between the tendon and the concrete to provide a bond
10
Reinforced Masonry
• Widely used to resist earthquakes
• Unsuitable for multistory buildings in which large clear spans are required
• Apartment houses and motels are well adapted to this method
10
Ordinary Brick Bearing-Wall Buildings (1 of 2)
• Walls must increase in thickness as the building’s height increases.
• Limit is generally about 6 stories
• Recent years, possible to 20 or more stories
10
Ordinary Brick Bearing-Wall Buildings (2 of 2)
• Construction methods allow higher buildings
• Two wythes of brick are built
• The width of one brick is left between them
• Reinforcing rods are placed vertically
• Concrete is poured into the void
10
Special Cases (1 of 2)
• Low-rise buildings
• Recent designs have eliminated reinforced concrete in the wall
• High compressive-strength bricks and special mortar are used instead
• Masonry wall-bearing building can be several stories high
10
Special Cases (2 of 2)
• Concrete block
• Has become popular for some resorts
• With outside open-air stairways and balconies, life safety is achieved
10
Collapse Under Construction
• Concrete structures under construction sometimes collapse
• Fire department rescues construction workers
• Fire officers should be well informed on the legal position of the fire department
10
Ordering the Removal of a Dangerous Structure
• Power given to the building commissioner
• Fire department has no right to demolish such a structure.
10
Lawsuits
• Common today
• Owner, architect, general contractor, subcontractors, and victims attempt to determine financial responsibility
• After collapses, some of those involved may try to cover up their actions
10
An Industry Warning
• Experts have warned of the collapse hazard of concrete structures
• Design engineers should use construction loads as governing loads in structures
10
Problems of Falsework
• Falsework
• Temporary structure to support concrete work in the course of construction
• Can represent 60% of the cost of a concrete structure
10
Concrete Formwork
• Designed without the extra strength calculated into a building to compensate for deterioration
• Built at the lowest possible cost
• Formwork failures can occur, but it is surprising is that they are relatively rare
10
Falsework for Walls or Columns
• Must have adequate strength to resist the pressure of heavy fluid concrete
• As concrete sets, pressure is reduced due to internal friction
• Setting of concrete is temperature dependent
10
Reshoring Concrete
• Concrete requires time to cure
• Formwork is then removed
• Reshoring is putting shores back in place to help carry the load
• Reshoring means concrete is not yet set
10
Collapses of Floors (1 of 2)
• Many involve formwork supporting newly cast or high bay floors
• Proper cross-bracing can help prevent this
10
Collapses of Floors (2 of 2)
• Formwork can also be a problem
• Often rests on the ground
• Mudsills are the planks on which the shores rest
• If mud is involved, bearing may be inadequate
10
A Widely Believed Fallacy
• “Reinforced concrete which has set hard to the touch usually has developed enough strength to be self-supporting, though it may not be capable of handling superimposed loads.”
10
Skyline Towers Collapse
• Skyline Towers collapsed in Arlington, Virginia, 1973
• Collapse proved the fallacy
• Shoring had been removed from the topmost floor
• The floor collapsed, and the collapse was progressive
10
Lessons from Skyline Towers
• Removal of shoring by laborers is no different than removal by fire
• Any concrete formwork failure presents the likelihood for catastrophic collapse
• Few concrete buildings can withstand the collapse of one floor onto another
10
Hazards of Post-Tensioning(1 of 2)
• Hydraulic jacks are used to tension the tendons or jack the cables
• No bond between the tendons and the concrete
10
Hazards of Post-Tensioning (2 of 2)
• Weight of concrete transfers to columns only when tensioning is complete
• Case example: The Skyline Towers garage was made of post-tensioned concrete. Poor sheer resistance led to collapse
10
Collapse of Reinforced Masonry
• Used widely in construction
• Workers might overload a floor portion
• Case example: In Pittsburgh, Pennsylvania an excess load caused the partial collapse of several stories of precast floors
10
Collapse of Precast Concrete
• Precast concrete buildings under construction are unstable
• Temporary bracing holds units in place
• Wooden temporary shoring might also be used
• Case example: Montgomery County Maryland. Three-story garage collapsed due to oversized washer
10
Lift-slab Collapses (1 of 3)
• Lift-slab construction
• Ground floor slab is cast first
• Bond breakers are used between the slabs
• Slabs are raised to the columns
• Each floor is temporarily connected to the columns
10
Lift-Slab Collapses (2 of 3)
• Case example: L’Ambience Plaza concrete building under construction in Connecticut was due to the failure of a single connection
10
Lift-Slab Collapses (3 of 3)
• When do the accidents occur?
• While the slabs are being lifted or while no lifting is being done
• Case example: In California, a roof slab was lifted to columns three inches out of plumb. As an attempt was made to pull the slab back into place, it collapsed
10
Fire Problems of Concrete Buildings Under Construction
• Concrete buildings under construction can present serious fire problems
• Fire in formwork can easily result in major collapse
• Little reserve strength in formwork
• Little understanding of potential hazard
10
Potential Fires at a Construction Site
• Fires at a construction site
• Causes include welding, cutting, and plumbers’ torches; temporary electrical lines; and arson
• Fuels are readily available
• Glass-fiber formwork is also combustible
10
Hazard of Heating
• Burning of scrap wood in steel barrels or the use kerosene heaters are hazards
• Liquefied petroleum gas (LPG) is also dangerous
10
Codes for LPG (1 of 2)
• Store gas away from any open flames.
• Case example: 1963, LPG explosion at the Indianapolis Coliseum; caused when a leaking gas-fired cooker cylinder exploded and gas reached heater flame
10
Codes for LPG (2 of 2)
• Install excess flow valves.
• Case example: In one city, gas stored and piped with plastic tubes at ground level; hazard should line break
10
Hazards of Post-Tensioned Concrete (1 of 2)
• Catastrophic fire collapse potential
• Include bridges and parking garages
• Falsework fire could cause the sudden collapse of an entire concrete floor slab
• After tensioning, the ends of tendons are left exposed
10
Hazards of Post-Tensioned Concrete (2 of 2)
• Hanging tendons can fail at about 800°F
• Excess tendons are rolled up and attached to a wooden rack.
• Rolled-up tendons are heat collectors
• Failure of tendons will cause the collapse of that part of the structure
10
Protection of Tendons
• Insist on fireproofing tendon anchors immediately after tensioning is completed
• Insist on temporary protection for incrementally tensioned tendons
10
A Total Collapse: Case Example
• A post-tensioned building under construction in Cleveland, Ohio, suffered a falsework fire
• After a second fire, the entire 18-story building collapsed
10
Precast Buildings (2 of 2)• Pose unique hazards while being
constructed
• Construction involves erection of precast concrete units.
10
Precast Buildings (2 of 2)
• Temporary bracing or support is used; it can collapse
• Columns can be braced with wood rather than by telescoping tubular steel braces; wood is flammable
• Cold-drawn steel cables often provide diagonal bracing in precast buildings; these fail at 800° F
10
Cantilevered Platforms
• Used by cranes delivering materials to buildings under construction
• Are braced by wooden shores that would fail in a fire
10
Tower Cranes
• Supported on the building’s structural frame
• Weight of the crane may be distributed over several floors by falsework
• A fire involving this falsework can bring down the crane
10
Falsework on a Completed Floor
• Should be investigated
• May be supporting a patch over a hole
• May be supporting a heavy load such as the crane
10
Falsework: Case Example
• Formwork for concrete placement burned on the 23rd to 25th floors of a high-rise
• Operator was trapped in his cab
• He was protected with a heavy-caliber stream from a nearby roof until rescued
10
Fire Problems in Finished Buildings
• Concrete construction
• Thought to be truly fireproof
• Later, it was learned that concrete, like any other noncombustible material, can be destroyed by fire
10
Characteristics of Concrete
• Inherently noncombustible
• Some people confuse noncombustibility with fire resistance
• Neither is synonymous with fire safety
10
Safety of Concrete Construction: Case Example
• Reinforced concrete Joelma building in Sao Paulo, Brazil, burned in 1974
• Resulted in179 deaths. The structure had minor damage.
10
Fireproofing (Insulating) Steel
• Has a fire resistance rating if the protection system previously passed a standard fire test
• No such thing as a truly fireproof building
• Fireproofed steel is protected steel
10
Types of Fireproofing (1 of 2)
• Individual fireproofing provides protection for each piece of steel
• Methods include encasement and intumescent coating
• Membrane fireproofing does not protect individual members
10
Types of Fireproofing (2 of 2)
• One method uses a rated floor-ceiling assembly
• Underwriters Laboratories can test a roof and ceiling assembly
• NFPA 251 (ASTM E119) standard fire test
10
Hazards of Floor–ceiling Assemblies
• Can present a serious menace to the safety of fire fighters
• Assemblies need to be assembled exactly as performed in the laboratory
10
Ceiling System
• At the mercy of those have reason to remove ceiling tiles
• Access to utilities and additional storage space are two reasons to remove tiles
10
Legal Provisions
• None require membrane protection be maintained
• Replacement acoustical tile may be combustible
• All penetrations of the ceiling must be rated as part of the ceiling system
10
Term “Fire-rated”
• Used quite often in the fire protection and building construction fields
• Nonspecific and meaningless
• No part of a listed fire-resistance system stands by itself
10
Integrity of a Ceiling System
• Most are unaware of its significance
• Alterations compromise integrity
• Tiles are replaced haphazardly
• Holes are cut through tiles
• Displays are hung from the metal grid
• Testing doesn’t include superimposed loads
10
Laboratory Fire Tests
• Conducted under a slight negative pressure to remove smoke and fumes
• Fires generate positive pressure, and lay-in ceiling tiles may be easily displaced by fire pressures
10
Addition of Insulation
• Might not be part of the specifications of the listed ceiling assembly
• Wrong insulation causes heat to be held in the channels supporting the tiles
• A membrane protection system must be perfect
10
Cockloft
• Occurs between the ceiling and floor
• Allows for rapid fire spread
• Case example: Fire starting in one room traveled across a hallway above the ceiling; it came down through the tile ceiling of another room to ignite books
10
Firestopping
• Some code provisions provide for this
• Use of plenum space for various services makes it probable that the firestopping will conform only to the definition of legal firestopping
10
Deep, Long-span Trusses
• In some buildings, used to provide clear floor areas
• This creates plenum spaces several feet in height
• Sometimes voids are called “interstitial spaces”
• Using such space as storage places fire load next to unprotected steel
10
Fire Resistance of Floor-Ceiling Assemblies
• Not all are intended to be fire resistive
• A steel bar-joist floor with concrete topping and flame-spread-rated tiles below may appear to be fire resistive, but it is not
10
Missing Tiles
• Does not necessarily mean that a fire resistance system has been violated
• The building may be of noncombustible construction
• In such a case, ceiling tiles are at the option of the owner
10
Concrete Construction Building
• Some concrete assemblies have suspended tiles incorporated
• Most of the time, the suspended ceiling is installed to provide a hidden void for utilities
10
Fireproofing and Building Codes
• Fireproofing
• Applied to meet the standards required by the local building code
• Further, building department will indicate which systems tested at which laboratories are acceptable.
10
Efficiency of Fireproofing
• Depends on the competence of the subcontractor
• Also depends on the building department staff and on the fire department inspectors
10
Encasement Methods
• Terra cotta tile
• Early method for encasement
• Case example: The cast-iron columns of the Parker Building in New York City were protected with three-inch terra cotta tiles, but still burned and failed
10
Errors in Encasement
• Leaving the bottom web of beams unprotected
• Skewbacks, which are tiles shaped to fit around steel, corrects this error
• Skewbacks, however, often are removed for other reasons
10
Limitations of Encasement Method
• Fireproofing that is easily removed is a hazard
• Case example: A contractor removed the fireproofing protection from a major column. About a hundred cylinders of propane gas were stored adjacent to the column
10
Concrete Encasement
• Concrete became quite popular as a protective covering for steel
• Wood falsework provides a high fuel load
• Has been involved in a number of serious construction fires
10
Fireproofing of Steel and Concrete Beams
• Fireproofing is integral; accomplished by a specified mix of concrete in a specified thickness
• Some concrete is necessary for fireproofing
10
Disadvantage of Concrete
• Its weight
• Fireproofing is often a tempting target for cutting back
• Case example: Builders replace concrete with wire laths covered with cement plaster or gypsum, both of which are lighter
10
Sprayed-on Fireproofing
• Sprayed concrete spalls badly when exposed to fire
• Other sprayed-on fireproofing can pass laboratory tests, but questions exist about their reliability in the field
10
Issues with Sprayed-on Material(1 of 2)
• Importance not understood by other trades
• Case example: A building with fireproofing stripped from the columns by plasterers
10
Issues with Sprayed-on Material(2 of 2)
• Case example: A state office building in California had poorly applied fireproofing material
• If properly applied, can be very effective
• Case example: First Interstate Bank of Los Angeles
10
Asbestos Fiber Fireproofing
• Serious health hazard in its use
• Difficult to sell a building with asbestos fireproofing
• Asbestos is being removed from existing buildings
10
Signs of Trouble
• Deteriorated concrete
• Spalling that exposes reinforcing rods
• Cracks in concrete
10
Parking Garages
• When salt is used to melt snow and ice, corrosion is prevalent
• Damage is often difficult to determine
10
Calcium Chloride
• Added to concrete
• Has caused problems
• Preventive measures include sealing the concrete, providing adequate drainage, and flushing surfaces with fresh water in the spring
10
Concrete Rehabilitation
• Includes removal and replacement
• Installation of cathodic protection
• Using additional steel beams
10
Unprotected Steel (1 of 4)
• Concrete structures
• Often repaired with steel
• Steel cables fail even below 800°F
10
Unprotected Steel (2 of 4)
• Fire fighters’ role
• Should watch what is being done to buildings
• Almost none of what is done to a building after it is completed benefits the fire suppression effort
10
Unprotected Steel (3 of 4)
• Case example: Fire fighter student saw structural problem with mall roof: owner did not want building department to know of problem
10
Unprotected Steel (4 of 4)
• Steel designed into the structure
• Proper degree of fireproofing is usually specified
• If it is not designed into a structure, it is usually unprotected
10
Ceiling Finish and Voids
• Concrete construction has no inherent voids
• Finish stages of the building can create voids
10
Waffle Slab Concrete
• Imitation plastic waffle concrete is often suspended below the structural slab
• Problem: Combustible tile with a high fire-hazard rating is often used for ceilings
• Interconnected voids make it possible for the tile to burn on both sides
10
Suspended Ceilings
• When installed as part of initial construction, more likely to have satisfactory fire hazard characteristics
• Tile usually as safe as the law requires
10
Combustible Tile
• Need not be suspended to create a serious hazard
• Flammable adhesive create problems
• Installing new ceilings below old combustible tile ceilings presents a serious hazard
• Case example: John Sevier Retirement Center fire
10
Combustible Voids
• Can be created in a variety of ways
• Case example: A wooden suspended ceiling installed in an otherwise concrete construction. Sprinklers are below the ceiling. Fire could burn unchecked in the void
10
Modern Office Building
• Has huge communications and other utility requirements
• As much as one third of the height from floor to ceiling may be in-ceiling or under-floor voids
10
Noncombustible Voids
• Combustible thermal or electrical insulation and combustible plastic service piping may be in ceiling void
• Hung ceilings are generally not required for the structural integrity of the building
10
The Integrity of Floors
• In fire-resistive buildings
• Floor will be a barrier to the extension of fire
• More codes are requiring sprinkler protection
• Compartmentation is rarely achieved
10
Building Use
• Requires floor be penetrated
• Often, such penetrations compromise the integrity of the floor
10
Enclosures Around Ducts
• May be inadequate
• Can permit transmission of fire and/or smoke to other floors
• Poke-throughs are holes provided to draw utility services up to a floor from the void below
10
Penetrations of Floors for Services
• Are increasing
• Floor may be unable to resist the passage of fire adequately.
• Suspended ceiling hopefully will develop the necessary fire resistance
• Owner is not free to modify the ceiling
10
Concrete Floors
• Require expansion joints
• Case examples: Steel expansion joints transmitted fire from floor to floor in a huge postal building; molten aluminum expansion joints extended fire at McCormick place
• Concrete shrinks and creates cracks, which allows fire to pass
10
Imitation Materials
• Imitation concrete panels
• Commonly used, particularly on the exterior of buildings
• Fasteners that hold the panels on the building are made of plastic
• If the plastic burns or melts, the panels will drop off the building
10
Energy Conservation
• Has brought about the use of exterior insulation and finish systems (EIFS)
• Buildings can be finished in this manner when constructed or modified later
• Case example: Fort Worth, Texas Courthouse
10
Concrete’s Behavior in Fires
• Concrete in fire-resistive construction
• Resists compressive stresses
• Protects the tensile strength of steel from fire
• The concrete provides time to extinguish a fire
10
Impact Loads
• Will damage concrete
• When spoiling has reached reinforcing steel, shoring should be done
• Concrete floors may give no clue to the distress on the other side
10
Cutting Tensioned Concrete (1 of 2)
• Fire tactics
• Can include cutting through a concrete floor for accessibility
• Hole cutter can cut a hole in conventional reinforced concrete and reinforcing rods
10
Cutting Tensioned Concrete (2 of 2)
• Tensioned concrete structures
• Steel cables are under tremendous tension
• Cutting tension cables creates a potential whip
10
Precast Concrete (1 of 2)
• Cast-in-place, monolithic concrete buildings
• Resistant to collapse
• The loss of a column does not necessarily cause collapse.
• Load will be redistributed
10
Precast Concrete (2 of 2)
• Precast concrete buildings
• Individual columns, floors, girders, and wall panels are pinned by connectors
• No protective covering is provided for the connectors
• Fire load must be severe to cause failure
10
Explosions in a Precast, Pinned building
• Such buildings have none of the redundancies of a rigid-framed monolithic concrete building
• Case example: Ronan Point collapse, which involved a 24-story apartment building
10
Concrete Trusses
• Not common
• Exist in the Tampa, Florida, and Dallas/Fort Worth, Texas, airports
• Exist in the American Airlines hanger at Dallas/Fort Worth
10
Fires in Concrete Buildings: Case Example 1
• Los Angeles Central Library Fire in 1986
• Loss was immense
• 200,000 books and numerous periodical collections were destroyed
• The book stacks provided an estimated 93 pounds per square foot (psf) of fuel
10
Fires in Concrete Buildings: Case Example 2
• High-rise apartment building in Dallas, Texas
• $340,000 in damage
• Utility and vent pipes had been punched through the ceilings
10
Fires in Concrete Buildings: Case Example 3
• Military Records Center near St. Louis, Missouri
• Severely damaged in a fire in 1973
• The incredible fire load included over 21 million military personnel files in cardboard boxes on metal shelves
10
Know Your Buildings
• When building rate is high, difficult for fire departments to keep pace
• Slowdowns present an opportunity to get current on the hazards of specific buildings
• “Experience keeps a dear school, but fools will learn in no other.”
10
Summary ( 1 of 2)• Concrete is a cementatious material
produced by a chemical reaction
• There are two basic types of in-concrete construction: cast-in-place concrete and precast concrete
• Prestressing places engineered stresses in architectural and structural concrete
10
Summary ( 2 of 2)
• Concrete buildings under construction can present serious fire problems
• The concrete in fire-resistive construction serves two purposes—it resists compressive stresses and protects the tensile strength of steel from fire
10