Case Study: University of Southampton Dr Neil Smith Environment Manager 16 th October 2007.

Post on 15-Dec-2015

213 views 1 download

Tags:

Transcript of Case Study: University of Southampton Dr Neil Smith Environment Manager 16 th October 2007.

Case Study:University of Southampton

Dr Neil SmithEnvironment Manager

16th October 2007

Aims

Resource v waste management

Big v small projects

Share experience to date

What’s next

Resource v waste

Key project phases

Pre-design Design & procurement

Pre-construction

Construction

Post-construction

Estates & Facilities

Kevin Monaghan

Neil Smith PMU Steve Parker Ian Carroll(Environment (Buildings Programmes (H&S Manager)Manager) manager)

Capital programme Programme Management Unit £234M programme

Mountbatten Boldrewood IfLS Faraday

Sustainable Buildings Policy Sustainable Buildings Briefing note Guidance to Project Managers on waste Route map

Framework

Sustainable Buildings Policy:

5.2 Promote and adopt best practice:

5.2.2 Ensure the specification for new build, refurbishment and maintenance projects… sets targets for key performance indicators, such as energy and water use and waste production.

5.2.7 Ensure waste produced during building projects is minimised and

that all projects have a site waste management plan that incorporates the requirements of the Demolition Protocol.

5.2.8 Ensure materials have a minimal impact on the environment and set a target of at least 10% of the materials value of projects is derived from recycled content.

5.2.9 Set a target for all new buildings and major refurbishments to achieve an “Excellent” BREEAM rating with a minimum rating of “Very Good” where there are good and explicit reasons why an excellent rating could not be achieved.

Framework

Sustainable Buildings Policy:

5.3 Maintain and develop the University in a sustainable manner:

5.3.4 Ensure there are sufficient recycling facilities available and they are clearly marked.

5.3.5 Ensure there are adequate storage and collection facilities for other wastes,

such as chemicals, and clinical, radioactive and other hazardous wastes.

Case Study: Mountbatten

• ECS/ORC• Major fire (Nov 05)• Completion date:

Summer 2008

Site management:• Costain

Demolition (about 5,000 t reused on site)

• Bovis Environment management plan Environmental Aspects & Impacts Register KPIs Considerate Contractors Scheme Site audit

Mountbatten

Purpose KPI Target Score

Waste To measure the amount of waste removed from site during the construction processso that we can target reductions in wastage

Construction: Waste Removed (m3) / £100k spent

<10 7.6

KPI

Targets also for:• Energy use (Amount of CO2 Produced (kg) / £100k spent)

• Water use (Amount of Water Used (m3) / £100k spent)

• Timber use (% FSC Timber Used)

• Commercial vehicle movement (Total Number Commercial Vehicle Movements / £100k spent)

• CCS (Average Score)

Mountbatten

Score per section

Score references Score per section

Score references

1 Major non-compliance

4 High level beyond compliance

2 Minor non-compliance

5 Exceptional measures taken

3 Compliance

Environment (4/5)• Noise restriction• Hoarding• Risk assessments & induction• Waste monitored & segregated• Environmental policy working well• No energy saving measures on site (although corporately

energy use is well controlled)

Considerate contractor scheme audit

Case study: Faraday

• 1950s iconic building

• £20M refurbishment

• School of Civil Engineering & Environment

• BREEAM ‘Excellent’

Faraday

Gentle Associates• Decant

• Asbestos strip out(Windsor waste mgmt)

LA Moore• Enabling works(?)

Morgan Ashurst• Main contractor(?)

Faraday

Faraday: BREEAM

Management Commissioning (9):

M4 – Considerate Contractors (2)M5 – Construction site impacts (4)

- monitor construction waste- Sort & recycle construction waste

M12 – Users guide (1)

Materials (12):

MWI – Material spec (4)MW5 – Reuse of façade (1)MW6 – Reuse of structure (1)MW7 – Recycled aggregate (1)MW8 – Responsible sourcing of materials (3)MW12 – Storage of recyclable waste (1)

BREEAM rating % benchmark

Unclassified <25

Pass ≥25 - <40

Good ≥ 40 - <55

Very Good ≥ 55 - <70

Excellent ≥ 70

Faraday

Post completion recycling:

• Heelis Building• George Thomas Building

Small(er) projects Faculty Building Managers Annual budget: £5M (LTM & Client projects)

Distribution of FPM project budgets, 2006/07

0

20

40

60

80

100

120

140

160

180

200

Value (£)

Nu

mb

er o

f p

roje

cts

Preliminary feasibility report Guidance to contractors Selection (approved contractor database)

Framework

Guidance to contractors:

Selection of contractors Environment policy, EMS etc

Sustainable buildings Planning, design etc

On-site management Site RA, waste etc

SU Shop refit

£150k refit in summer 2007 Flair shopfittings Ltd Select-A-Skip UK Ltd

SU Shop refitTotal Waste & Recycling Summary for Southampton University (SUSU)

All weights are approximate.

Weight (Tonnes)

% Materials

Incineration (Flair)

0.8 6 Timber, MDF

Landfill 2.7 20.3 Flooring materials, rubble

Recycling (re-condition & Re-use)

6.5 48.9 Card racks, Refrigeration, Shelving

Recycling (Environmental disposal)

3.3 24.8 Refrigeration, metalwork

13.3 100

University Road car park £230k Demolish building & provide 65 car park

spaces PT Contractors

Pollution prevention procedureSite environmental risk assessmentWaste management procedureSWMP

University Road Car Park

Type of Waste Quantities Haulier

Carrier Licence No. Location

Waste Licence No.

Green Waste (compost) 30m3 PTC HAM/406524

Eco @ Hurn WML/296

Excavated Material 320m3 R&W HAM/409392

Marchwood Aggregates W01024/05

Marchwood Quarry Exempt

% to be recycled

House No. 37

90% Recycled

Comley & Son

HAM/406449 Transfer station

HR078

10% WasteComley & Son

SWMP

Sources of information

• WRAP www.wrap.org.uk/construction/index.html www.wrap.org.uk/construction/materials_recycling/index.html

• Netregs www.netregs.gov.uk www.netregs.wastedirectory.org.uk/Index.aspx

• Considerate contractor www.ccscheme.org.uk/

• BRE www.bre.co.uk/

• Smartwaste www.smartwaste.co.uk/ www.bremap.co.uk/bremap/about.jsp

What’s next?

Influence capital/FPM colleagues Audit & verification FPM workshop Finalise FPM SWMP Work with term contractors Review guidance

Review & Any questions?

Resource v waste management

Big v small projects

Share experience to date

What’s next

Any questions?