Call Center HVAC Installation

Post on 13-Apr-2017

465 views 0 download

Transcript of Call Center HVAC Installation

Project NameBuild-to-Suit Call Center HVAC Installation

Project LocationMidland, Georgia

Project TeamOwner: Managed Health Care CompanyGeneral Contractor: Batson-Cook

Specializations

Architect: Hecht Burdeshaw Architects, Inc.Engineer: PEACH Engineering, LLCContractor: McKenney’s, Inc.

Design/Assist

Pipe Shop PrefabPlumbing Shop Prefab

Sheet Metal Shop Prefab

Commercial OfficesMarkets

Mission Critical

McKenney’s installed a nontraditional HVAC system for a newthree-story call center in Midland, Georgia.

The ChallengeOwners of the 250,000-square-foot building had an aggressive schedule—eleven months from groundbreaking to tenant occupancy.Instead of a traditional overhead air distribution system, the project was based on an underfloor design. On each floor, the HVACductwork and distribution equipment had to be installed beneath an 18-inch raised floor.

The SolutionWith such a short timeline, there was no room for error. To ensure the project’s success, the McKenney’s team participated in the early stages of preplanning, providing design review and design assist services to the construction team. Together, the team developed an innovative design for the underfloor air distribution system. By working through the design assist process, McKenney delivered cost saving options for the owner.

The content of this document is not intended as an endorsement.

The ResultsPreplanning within the role as design assist mechanical subcontractor paid off and McKenney’s was able to stay on schedule and on budget for the owner—allowing the building to be occupied on time.

1056 Moreland Industrial BoulevardAtlanta, Georgia 30316P: 404-622-5000

sales@mckenneys.com

3601 Performance RoadCharlotte, North Carolina 28214P: 704-357-1200

Atlanta Office:

Charlotte Office:

www.mckenneys.com