Transcript of Building for Learning Project Photo Progress Report 3 October 2009 – November 2009 Project...
Building for Learning ProjectPhoto Progress Report 3
October 2009 – November 2009
Project commencement 21st September 2009
Internal Demolition Begins 6th Oct 2009
Classrooms 6-9 Demolition continues Oct 2009
Rooms emptied, carpets, ceilings, all electrics wiring removed ready for 1st storey construction and concrete slab floor
Racking construction for refurbishment storage 14th Oct 2009
Demolition continues Oct 2009
Corporate Services area refurbishment 19th Oct 2009
Windows removed Ceiling Fans replaced
Floor demolition 19th Oct 2009
Graeme Connelly supervising wall demolition 21st Oct 2009
Internal framing and windows being cut in 27th Oct 2009
Framing and floors added 28th Oct 2009
Staff inspections of works
Outside area demolition ready for major works to begin 29th Oct 2009
1st Storey works commences November 09
Scaffolding up early November
Room demolition – mid November
Some of the removed materials 24th November
Roof on – Roof Off (29th November 2009)
Over a period of about 2 weeks the roof and all timber roof trusses, wiring, air-conditioners, chimneys and a satellite dish were removed and prepared for a new 1st storey floor slab to be created.
This change meant that the possums who had taken residence in the ceiling over the last 100+ years have now moved on!!!