Bremner Transformer Station - Toronto Hydro · Bremner Transformer Station Growing Grids...

Post on 27-Apr-2018

220 views 3 download

Transcript of Bremner Transformer Station - Toronto Hydro · Bremner Transformer Station Growing Grids...

The star design is a trade-mark of Toronto Hydro Corporation used under licence. „Toronto Hydro‟ means Toronto Hydro-Electric System Limited.

Bremner Transformer StationGrowing Grids Presentation, Nov 29th 2012

Presented by:

Shaun Pinard

Toronto Hydro2 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

• Background – Why is Bremner TS required?

• Scope of Work – What work will be done?

• Status – Where are we now?

Agenda

Toronto Hydro3 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Why is Bremner TS required?

• Immediate Need – Windsor TS upgrades

• Short term need – Avoid overload at key stations

• Mid term Need - Load growth to 2030

Toronto Hydro4 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Immediate Need – Windsor TS Upgrades

Windsor TS: - Built in 1954

- Supplies key customers in

downtown core

Toronto Hydro5 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Windsor Transformer Station

Toronto Hydro6 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Short Term Need – Avoid Overload at 5 downtown Stations

UNITS OF MEASURE - MVA

Toronto Hydro7 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

WHITE = the project has had preliminary renders, but

no application has been submitted.

RED = the project has submitted an application to the

city

GREEN = the project has been approved, but has yet

to start construction

YELLOW = the project is currently in sales

BLUE = the project is currently under construction

As reported in Canadian Business Magazine

Short Term Need – Avoid Overload at 5 downtown Stations

Toronto Hydro8 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Long Term Need – Address Continuing Projected Load

Growth

Capacity

Toronto Hydro9 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Scope of entire Project

Work Why?

1. Cable Tunnel High Voltage Connection from Hydro

One at Front St & Simcoe St

2. Transformer Station High Voltage to Medium Voltage

Conversion

3. Duct Banks Medium Voltage Supply to Customers

Toronto Hydro10 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

1) Cable Tunnel

Toronto Hydro11 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Bremner Transformer Station

2) Transformer Station

• Site preparation

• Disassembly & Storage of the

Machine Shop

• Construction of the new

underground building

• Reassembly of Machine Shop

• Installation of electrical

equipment

• Site landscaping work

Toronto Hydro12 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Building Layout – TS Basement

Roundhouse

Lakeshore Blvd

Toronto Hydro13 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Building Layout – TS Main Floor

Roundhouse

Lakeshore Blvd

Toronto Hydro14 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Building Layout – TS Mezzanine

Roundhouse

Lakeshore Blvd

Toronto Hydro15 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Building Layout – TS Roof

Roundhouse

Lakeshore Blvd

Toronto Hydro16 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Bremner Transformer StationBremner Transform-r StationTransformer Station – Post-Construction (Architectural Rendering)

Toronto Hydro17 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Bremner Transformer StationTransformer Station – Post-Construction Concept

Toronto Hydro18 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Transformer Station – Post-Construction Concept

Toronto Hydro19 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Transformer Station – Post-Construction

Toronto Hydro20 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Bremner Transformer StationOther examples of site-integrated TS‟s

Location Utility Station Year

Completed

New York City, USA Con Edison Mott Haven

Substation

2012

Sydney, Australia Transgrid Haymarket

Substation

2004

Nagoya, Japan Chubu Electric

Company

Meijo Substation 1999

London, England EDF Energy Leicester Square

Substation

1989

Vancouver, British

Columbia

BC Hydro Cathedral Square

Station

1984

Toronto Hydro21 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Project Rees St:

- Civil infrastructure for underground distribution lines and feeders

- Work anticipated to be completed in November 2012

3. Duct Banks – Distribution to Customers

Toronto Hydro22 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Project Schedule

Sept – Dec 2012:

- Relocation of existing services, roadway

- Hazmat work within Machine Shop

2013 – 2014:

- Main Contract – building, equipment, etc

Toronto Hydro23 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

– Temporary Road

– Site Services (water and

sanitary relocation)

– Bell Line Relocation

– Machine Shop

environmental clean up

– Tree Relocation

Site Preparation / Hazmat

Work

Sep – Dec 2012

Toronto Hydro24 | Bremner TS, Growing Grids Presentation, Nov 29th 2012

Where are we right now

Pre-construction phase:

Work Status

Land Acquisition Complete

Detailed Design Complete

Environmental

Assessment

Complete

City Approvals In Progress

Funding Application In Progress

Site Preparation In Progress

Toronto Hydro25 | Bremner TS, Presentation to Bidders December 4, 2012

Disclaimer

The information in these materials is based on information currently available to Toronto Hydro Corporation and its affiliates

(together hereinafter referred to as “Toronto Hydro”), and is provided for information purposes only. Toronto Hydro does not

warrant the accuracy, reliability, completeness or timeliness of the information and undertakes no obligation to revise or update

these materials. Toronto Hydro (including its directors, officers, employees, agents and subcontractors) hereby waives any and

all liability for damages of whatever kind and nature which may occur or be suffered as a result of the use of these materials or

reliance on the information therein. These materials may also contain forward-looking information within the meaning of

applicable securities laws in Canada ("Forward-Looking Information"). The purpose of the Forward-Looking Information is to

provide Toronto Hydro‟s expectations about future results of operations, performance, business prospects and opportunities and

may not be appropriate for other purposes. All Forward-Looking Information is given pursuant to the "safe harbour" provisions of

applicable Canadian securities legislation. The words "anticipates", "believes", "budgets", "could", "estimates", "expects",

"forecasts", "intends", "may", "might", "plans", "projects", "schedule", "should", "will", "would" and similar expressions are often

intended to identify Forward-Looking Information, although not all Forward-Looking Information contains these identifying words.

The Forward-Looking Information reflects the current beliefs of, and is based on information currently available to, Toronto

Hydro‟s management. The Forward-Looking Information in these materials includes, but is not limited to, statements regarding

Toronto Hydro‟s future results of operations, performance, business prospects and opportunities. The statements that make up

the Forward-Looking Information are based on assumptions that include, but are not limited to, the future course of the economy

and financial markets, the receipt of applicable regulatory approvals and requested rate orders, the receipt of favourable

judgments, the level of interest rates, Toronto Hydro‟s ability to borrow, and the fair market value of Toronto Hydro‟s investments.

The Forward-Looking Information is subject to risks, uncertainties and other factors that could cause actual results to differ

materially from historical results or results anticipated by the Forward-Looking Information. The factors which could cause results

or events to differ from current expectations include, but are not limited to, the timing and amount of future cash flows generated

by Toronto Hydro's investments, market liquidity and the quality of the underlying assets and financial instruments, the timing and

extent of changes in prevailing interest rates, inflation levels, legislative, judicial and regulatory developments that could affect

revenues, and the results of borrowing efforts. Toronto Hydro cautions that this list of factors is not exclusive. All Forward-

Looking Information in these materials is qualified in its entirety by the above cautionary statements and, except as required by

law, Toronto Hydro undertakes no obligation to revise or update any Forward-Looking Information as a result of new information,

future events or otherwise after the date hereof.