Beamline Readiness Review - Hutch Beamline 12.3.2 Microdiffraction March 28, 2006.

Post on 18-Jan-2016

226 views 0 download

Tags:

Transcript of Beamline Readiness Review - Hutch Beamline 12.3.2 Microdiffraction March 28, 2006.

Beamline Readiness Review - HutchBeamline 12.3.2

Microdiffraction

March 28, 2006

Floor Plan, Sector 12 25L760C

Sector 12 superbend beamlines 12.2.2, 12.3.1 & 12.3.2

Hutch Assembly Details

Hutch construction drawing from vendor

Wall panel construction

2mm sheet lead

1” thick - 4# mineral wool insulation

14 gauge steel

Prior to assembly, interior materials have combined thickness of 52.8mm

After assembly, the interior components havebeen compressed to 47.6mm from 52.8mm

Wall panel construction

Wall panel connection detail

Typical Wall Panel with Pb sheet installed

Panel with second layer of insulation installed

Front wall prior to second layer of insulation

Window

2nd front wall panel with opening for 12.3.2 beampipe

Typical wall corner with Pb bent along vertical edge

Different corner with 2nd layer of insulation

H- channel with Pb captured

Pb

Pb visible in all of these H-channel units

bottomside

Pb

Framed opening detail – labyrinths, beampipe opening

Labyrinth Pb detail prior to insulation

Pb in track prior to steel cap

Labyrinth detail

Labyrinths after Pb shielding applied

Labyrinth with detail of how Pb is doubled over

Overview of back wall construction

1” overlap from Backwall to flashing

Roof to back wall connection detail

Back wall Pb overlap detail

Fastening tabs to secure to structural brace

Pb overlap

Back wall right side

Back wall detail

Lead laminatedto steel

Steel

Back wall detail 2

Lead overlap for next panel

Roof – Wall panel connection