Guide to Cement-Based Integrated Pavement Solutions
August 2011
Cement-Based Integrated Pavement Solutions
Heavy Industrial Airports Highways Country RoadsArterials CommercialInterstatesLight Industrial
Residential
1 41 4 1 4
1 2 4
1 4 6
1 2 41 4 6
** The use of 7 & 8 applies to all uses depending on quality of soil and need for stabiliaztion
1 2 31 2 4 7
Heavy Industrial Light Industrial Airports Commercial Residential Recreation
LAND USE
CEMENT-BASED INTEGRATED PAVEMENT SOLUTIONS
1 2 3 4 5 6 7 8
Conventional Overlays CRCP
VIBRATORY COMPACTION
Pervious Concrete
Full-Depth Reclamation
Cement- Treat-ed Base
Cement- Modified
Soils
Roller- Com-pacted Con-
crete
EXTERNAL COMPACTION
Concrete Recycling Full-Depth Repair Partial-Depth Repair Dowel Bar Retrofit Slab Stabilization Diamond Grinding
SUSTAINABLE PRACTICE - PRESERVATION OF THE SYSTEM’S EQUITY
This page illustrates the land-use applications for the cement-based integrated pavement solutions described in this guide.
For more information on these applications, please see the table of contents to locate page numbers for each application.
Technical Report Documentation Page
1. Report No. 2. Government Accession No. 3. Recipient’s Catalog No.
4. Title and Subtitle 5. Report Date
Guide to Cement-Based Integrated Pavement Solutions August 2011
6. Performing Organization Code
7. Author(s) 8. Performing Organization Report No.
Sabrina Garber, Robert Otto Rasmussen, and Dale Harrington
9. Performing Organization Name and Address 10. Work Unit No. (TRAIS)
Institute for Transportation
Iowa State University
2711 South Loop Drive, Suite 4700
Ames, IA 50010-8664
11. Contract or Grant No.
12. Sponsoring Organization Name and Address 13. Type of Report and Period Covered
Portland Cement Association
5420 Old Orchard Road
Skokie, IL 60077
14. Sponsoring Agency Code
15. Supplementary Notes
16. Abstract
This guide provides a clear, concise, and cohesive presentation of cement-bound materials options for 10 specific engineering pavement applications: new concrete pavements, concrete overlays, pervious concrete, precast pavements, roller-compacted concrete, cement-treated base, full-depth reclamation with cement, cement-modified soils, recycled concrete aggregates, and repair and restoration. Each application is presented as a method for meeting specific design and construction objectives that today’s pavement practitioners must accomplish. The benefits, considerations, brief description, and summary of materials, design, and construction requirements, as well as a list of sustainable attributes, are provided for every solution. This guide is intended to be short, simple, and easy to understand. It was designed so that the most up-to-date and relevant information is easily extractable. It is not intended to be used as a design guide for any of the applications identified herein. Recommendations for additional information that can provide such details are given at the end of each solution discussion. The intended audience is practitioners, including engineers and managers who face decisions regarding what materials to specify in the pavement systems they design or manage. The audience also includes city and county engineers, along with the A/E firms that often represent them, and state DOT engineers at all levels who are seeking alternatives in this era of changing markets.
17. Key Words 18. Distribution Statement
pavement solutions, portland cement concrete, overlays, pervious pavement, roller-compacted concrete, full-depth reclamation, cement-treated base, cement-modified soils, pavement repair, pavement restoration
No restrictions.
19. Security Classification (of this report)
20. Security Classification (of this page)
21. No. of Pages 22. Price
Unclassified. Unclassified. 92
Form DOT F 1700.7 (8-72) Reproduction of completed page authorized
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
iii
Guide to Cement-Based Integrated Pavement Solutions
AuthorsSabrina Garber, The Transtec Group, Inc.
Robert Otto Rasmussen, The Transtec Group, Inc.
Contributing AuthorDale Harrington, Snyder and Associates
Editorial StaffSabrina Shields-Cook, Managing Editor
Carol Gostele, Copyeditor
Mina Shin, Graphic Designer
Technical Advisory CommitteeWayne Adaska, Portland Cement Association
Tom Cackler, National Concrete Pavement Technology Center
Greg Dean, American Concrete Pavement Association, Southeast Chapter
Gary Fick, Trinity Construction Management Services
Jerry Reece, North Carolina Concrete Pavement Association
Matt Singel, Cement Council of Texas
Gordon Smith, Iowa Concrete Paving Association
Leif Wathne, American Concrete Pavement Association
August 2011
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
iv
About This GuideThis Guide to Cement-Based Integrated Pavement Solu-tions is a product of the National Concrete Pavement Technology Center (National CP Tech Center) at Iowa State University’s Institute for Transportation, with funding from the Portland Cement Association. It provides a clear, concise, and cohesive presentation of cement-bound materials options for specific engineer-ing pavement applications. Each application identified in this guide is presented as a method for meeting specific design and construction objectives that today’s pavement practitioners must accomplish.
AcknowledgmentsThe authors and co-authors, the National CP Tech Center, and the Portland Cement Association are grateful to the knowledgeable and experienced profes-sionals, public and private, who contributed to the development of this guide. While the authors gener-ated the overall content, it was the technical advisory committee’s and technical reviewers’ careful reviews of drafts, thoughtful discussions, and suggestions for revisions and refinements that make this guide a com-prehensive resource for practitioners. The National CP Tech Center and the Portland Cement Association appreciate the committee’s and reviewers’ invaluable assistance.
Photo CreditsThe photographs on the cover and throughout this guide were provided by the following individuals and organizations:
•American Concrete Pavement Association
•American Concrete Pavement Association, Southeast Chapter
•California Nevada Cement Association
•Cement Council of Texas
•Charger Enterprises
•Chicago Department of Transportation
•Illinois Tollway
•Iowa Concrete Paving Association
•John Kevern, University of Missouri-Kansas City
•National Concrete Pavement Technology Center
•Portland Cement Association
•The Transtec Group, Inc.
For More InformationFor technical assistance regarding cement-based concrete paving, contact the Portland Cement Association or the National CP Tech Center:
Wayne Adaska, Director, PavementsPortland Cement Association5420 Old Orchard Rd.Skokie, IL 60077847-966-6200, info@cement.org, www.cement.org/
Tom Cackler, DirectorSabrina Shields-Cook, Managing EditorNational CP Tech CenterInstitute for Transportation, Iowa State University2711 S. Loop Drive, Suite 4700Ames, IA 50010-8664515-294-7124, shieldsc@iastate.edu, www.cptechcenter.org/
DisclaimersNeither Iowa State University nor this document’s authors, editors, designers, illustrators, distributors, or technical advisors make any representations or warranties, expressed or implied, as to the accuracy of information herein and disclaim liability for any inaccuracies.
Iowa State University does not discriminate on the basis of race, color, age, religion, national origin, sexual orientation, gender identity, sex, marital status, disability, genetic testing, or status as a U.S. veteran. Inquiries can be directed to the Director of Equal Opportunity and Diversity, Iowa State University, 3680 Beardshear Hall, 515-294-7612.
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
v
Contents
About This Guide ............................................................................iv
Acknowledgments .........................................................................iv
Photo Credits ...................................................................................iv
Contents .............................................................................................v
List of Figures ................................................................................. vii
List of Tables ......................................................................................x
Preface ................................................................................................xi
Important Defi nitions ..................................................................xii
Table of Solutions ........................................................................ xiv
1. New Concrete Pavements ....................................................1-1Objectives ......................................................... 1-1Solution ............................................................ 1-1Benefi ts ............................................................. 1-1Considerations .................................................. 1-1Typical Applications .......................................... 1-1Description ....................................................... 1-1Materials ........................................................... 1-3Design .............................................................. 1-4Construction ..................................................... 1-5Sustainability .................................................... 1-7For More Information ....................................... 1-7
2. Concrete Overlays ...................................................................2-1Objectives ......................................................... 2-1Solution ............................................................ 2-1Benefi ts ............................................................. 2-1Considerations .................................................. 2-1Typical Applications .......................................... 2-1Description ....................................................... 2-1Materials ........................................................... 2-2Design .............................................................. 2-3Construction ..................................................... 2-5Sustainability .................................................... 2-6For More Information ....................................... 2-7
3. Pervious Concrete ...................................................................3-1Objectives ......................................................... 3-1Solution ............................................................ 3-1Benefi ts ............................................................. 3-1Considerations .................................................. 3-1Typical Applications .......................................... 3-1Description ....................................................... 3-2Materials ........................................................... 3-3Design .............................................................. 3-4Construction ..................................................... 3-5Sustainability .................................................... 3-6For More Information ....................................... 3-6
4. Precast Pavements..................................................................4-1Objectives ......................................................... 4-1Solution ............................................................ 4-1Benefi ts ............................................................. 4-1Considerations .................................................. 4-1Typical Applications .......................................... 4-1Description ....................................................... 4-1Materials ........................................................... 4-2Design .............................................................. 4-3Construction ..................................................... 4-3Sustainability .................................................... 4-5For More Information ....................................... 4-5
5. Roller-Compacted Concrete ...............................................5-1Objectives .......................................................... 5-1Solution ............................................................. 5-1Benefi ts .............................................................. 5-1Considerations .................................................. 5-1Typical Applications ........................................... 5-1Description ........................................................ 5-2Materials ............................................................ 5-3Design ............................................................... 5-3Construction ..................................................... 5-5Sustainability ..................................................... 5-6For More Information ........................................ 5-7
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
vi
6. Cement-Treated Base ............................................................6-1Objectives ......................................................... 6-1Solution ............................................................ 6-1Benefi ts ............................................................. 6-1Considerations .................................................. 6-1Typical Applications .......................................... 6-1Description ....................................................... 6-1Materials ........................................................... 6-2Design .............................................................. 6-3Construction ..................................................... 6-3Sustainability .................................................... 6-5For More Information ....................................... 6-5
7. Full-Depth Reclamation with Cement (FDR) .................7-1Objectives ......................................................... 7-1Solution ............................................................ 7-1Benefi ts ............................................................. 7-1Considerations .................................................. 7-1Typical Applications .......................................... 7-1Description ....................................................... 7-1Materials ........................................................... 7-2Design .............................................................. 7-2Construction ..................................................... 7-2Sustainability .................................................... 7-3For More Information ....................................... 7-3
8. Cement-Modifi ed Soils (CMS) .............................................8-1Objectives ......................................................... 8-1Solution ............................................................ 8-1Benefi ts ............................................................. 8-1Considerations .................................................. 8-1Typical Applications .......................................... 8-1
Description ....................................................... 8-1Materials ........................................................... 8-2Design .............................................................. 8-2Construction ..................................................... 8-2Sustainability .................................................... 8-3For More Information ....................................... 8-3
9. Recycled Concrete Aggregates ..........................................9-1Objectives ......................................................... 9-1Solution ............................................................ 9-1Benefi ts ............................................................. 9-1Considerations .................................................. 9-1Typical Applications .......................................... 9-1Description ....................................................... 9-1Materials ........................................................... 9-2Design ............................................................... 9-2Construction ..................................................... 9-3Sustainability ..................................................... 9-4For More Information ....................................... 9-4
10. Repair and Restoration .................................................... 10-1Description .................................................... 10-1Full-Depth Repairs ........................................ 10-1Partial-Depth Repairs ..................................... 10-2Stitching ........................................................ 10-2Slab Stabilization ........................................... 10-2Slab Jacking ................................................... 10-3Joint Resealing ............................................... 10-3Dowel Bar Retrofi t ......................................... 10-3Diamond Grooving and Grinding .................. 10-4For More Information .................................... 10-5
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
vii
List of Figures
Figure 1-1. Schematic of typical concrete pavement cross-section ..................................................................... 1-1
Figure 1-2. Schematic of the various types of new concrete pavements ............................................................. 1-2
Figure 1-3. Concrete mixture constituents ......................................................................................................... 1-3
Figure 1-4. Sawcutting JPCP.............................................................................................................................. 1-5
Figure 1-5. Concrete placed over dowel baskets ................................................................................................ 1-6
Figure 1-6. Dowel-bar inserter .......................................................................................................................... 1-6
Figure 1-7. JRCP reinforcement in place before paving ...................................................................................... 1-6
Figure 1-8. CRCP reinforcement placed before paving....................................................................................... 1-6
Figure 1-9. Burlap drag on fresh concrete .......................................................................................................... 1-7
Figure 1-10. Curing compound applied by spray nozzles on a cure cart ........................................................... 1-7
Figure 2-1. Unbonded overlay ........................................................................................................................... 2-2
Figure 2-2 Overlay applications ......................................................................................................................... 2-2
Figure 2-3. Typical cross-section of unbonded overlay ....................................................................................... 2-3
Figure 2-4. Unbonded concrete overlay construction over a nonwoven geotextile interlayer ............................. 2-5
Figure 2-5. Bonded overlay construction ........................................................................................................... 2-6
Figure 3-1. Miller Park in Fair Oaks, California ................................................................................................. 3-1
Figure 3-2. Imperial Beach Sports Park, California ............................................................................................ 3-1
Figure 3-3. Pervious concrete for alley in Chicago, Illinois ................................................................................ 3-2
Figure 3-4. Pervious concrete ............................................................................................................................ 3-2
Figure 3-5. Pervious concrete pavement parking lot .......................................................................................... 3-2
Figure 3-6. Fresh pervious concrete .................................................................................................................. 3-3
Figure 3-7. Pervious concrete pavement in the rain ........................................................................................... 3-4
Figure 3-8. Schematic of pervious full exfiltration pavement design .................................................................. 3-5
Figure 3-9. Schematic of pervious partial exfiltration pavement design ............................................................. 3-5
Figure 3-10. Schematic of pervious no exfiltration pavement design ................................................................. 3-5
Figure 3-11. Compacting the placed pervious concrete ..................................................................................... 3-5
Figure 3-12. Curing pervious concrete with plastic sheeting ............................................................................. 3-6
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
viii
Figure 4-1. Precast pavement system cross-section ............................................................................................ 4-1
Figure 4-2. Nighttime placement of precast panels in Virginia ........................................................................... 4-2
Figure 4-3. Precast pavement system in Indonesia ............................................................................................. 4-2
Figure 4-4. Concrete poured into form for precast panel ................................................................................... 4-4
Figure 4-5. Vibrators for consolidation of concrete around reinforcement in precast prestressed panel .............. 4-4
Figure 4-6. Placement of precast panel for precast JCP system ........................................................................... 4-4
Figure 4-7. Placement of a prestressed precast panel ......................................................................................... 4-4
Figure 5-1. Typical RCC versus PCC surface ...................................................................................................... 5-2
Figure 5-2. Pavement cross-section with RCC surface ....................................................................................... 5-2
Figure 5-3. Pavement cross-section with RCC base ............................................................................................ 5-2
Figure 5-4. RCC construction for commercial and heavy industrial applications ............................................... 5-2
Figure 5-5. Typical mix design constituents ....................................................................................................... 5-3
Figure 5-6. RCC material looks drier than conventional concrete ...................................................................... 5-3
Figure 5-7. Flexural beam testing ...................................................................................................................... 5-4
Figure 5-8. Typical RCC design relies on aggregate interlock at cracks ............................................................... 5-4
Figure 5-9. RCC delivered to jobsite .................................................................................................................. 5-5
Figure 5-10. Tilt-drum mixer ............................................................................................................................ 5-5
Figure 5-11. Ready-mix transit trucks dumping into haul trucks ....................................................................... 5-5
Figure 5-12. Mobile RCC pugmill mixing plant and mixing chamber ................................................................ 5-6
Figure 5-13. RCC placement ............................................................................................................................. 5-6
Figure 5-14. Compacting RCC using both vibratory and pneumatic-tired rollers .............................................. 5-6
Figure 5-15. RCC in-place density measurement ............................................................................................... 5-7
Figure 5-16. Curing RCC .................................................................................................................................. 5-7
Figure 6-1. Load distribution of CTB compared to unstabilized granular base ................................................... 6-2
Figure 6-2. Typical pavement cross-sections showing CTB layers....................................................................... 6-2
Figure 6-3. Completed CTB for new pavement construction in Oklahoma ........................................................ 6-2
Figure 6-4. Spreading dry cement on grade prior to mixing .............................................................................. 6-4
Figure 6-5. Applying cement slurry on grade prior to mixing (cement slurry is applied the same way for FDR and CMS applications) ......................................... 6-4
Figure 6-6. Constructing CTB using mixed-in-place method ............................................................................. 6-4
Figure 6-7. Placement of plant-mixed CTB on prepared subgrade ..................................................................... 6-4
Figure 7-1. Schematic of the mixing chamber of a reclaimer machine ............................................................... 7-2
Figure 7-2. Reclaimer pulverizing existing asphalt pavement and base material ................................................. 7-2
Figure 7-3. Dry cement placed on pulverized material ...................................................................................... 7-3
Figure 7-4. Applying cement slurry on grade prior to mixing (cement slurry is applied the same way for CTB applications) ......................................................... 7-3
Figure 7-5. Mixing the cement into the pulverized material ............................................................................... 7-3
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
ix
Figure 7-6. Equipment for compaction and finishing ........................................................................................ 7-3
Figure 8-1. Typical cross-section with CMS ....................................................................................................... 8-2
Figure 8-2. Cement slurry added to subgrade material (cement slurry is applied the same way for CTB and FDR applications) ......................................... 8-2
Figure 8-3. Pulvermizer used for in-place mixing of CMS ................................................................................. 8-3
Figure 8-4. Sheepsfoot roller used for compaction ............................................................................................. 8-3
Figure 9-1. Recycled concrete aggregates ........................................................................................................... 9-2
Figure 9-2. Example of equipment used to break existing concrete ................................................................... 9-3
Figure 9-3. Broken concrete pavement is removed for recycling ........................................................................ 9-3
Figure 9-4. Existing concrete recycled in-place and reused for base material on the Tri-State Tollway in Illinois ........................................................................ 9-3
Figure 10-1. Full-depth repair of a concrete pavement slab ............................................................................. 10-1
Figure 10-2. Partial-depth repair process at joint ............................................................................................. 10-2
Figure 10-3. Cross-section of concrete pavement showing stitching. ............................................................... 10-2
Figure 10-4. Drilling operation as part of slab stabilization .............................................................................. 10-3
Figure 10-5. Application of joint sealant .......................................................................................................... 10-4
Figure 10-6. Contiguous concrete slabs prepared for dowel bar retrofitting ..................................................... 10-4
Figure 10-7. Diamond grinding concrete pavement for surface restoration ...................................................... 10-4
Figure 10-8. Longitudinal grooving of a concrete pavement to restore macrotexture ....................................... 10-5
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
x
List of Tables
Table 1. Table of solutions ...................................................................................................................................xv
Table 2-1. Current state-of-the-practice overlay design methodologies .............................................................. 2-3
Table 2-2. Joint pattern for bonded concrete overlays ........................................................................................ 2-4
Table 2-3. Joint pattern for unbonded concrete overlays of concrete pavements ................................................ 2-5
Table 2-4. Joint pattern for unbonded concrete overlays of HMA and composite pavements ............................. 2-5
Table 3-1. Typical values for material properties ................................................................................................ 3-3
Table 5-1. List of design methodologies ............................................................................................................. 5-4
Table 6-1. Typical CTB properties ...................................................................................................................... 6-3
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
xi
How is this guide unique?Portland cement is the fundamental ingredient in con-crete. When you think of cement, it may be automatic to think of concrete; when you think of cement and pavements, you probably think of cement in conven-tional concrete used for pavement surface layers. But did you know that cement can be used in other pave-ment layers and for other applications? In fact, cement can be used in many other applications for pavement systems.
Pavement systems containing cement-bound layers have been used worldwide for over a century, with great success. Portland cement can be used in virtually every layer in a pavement system. Typical applica-tions include improving the quality of subgrade soils and stabilizing base materials. Integrating multiple cement-based layers into a pavement design may pro-vide a cost-effective method for achieving a stronger, more durable, sustainable pavement. For instance, using a cement-modified soil and cement-treated base as opposed to an unbound granular base placed on an unprepared subgrade can reduce the required thickness of the base material. In addition, a cement-treated base may decrease the thickness needed for the concrete or asphalt surface, resulting in less materials and overall reduced cost.
In addition to being the key constituent of new con-crete pavement and concrete overlay surfaces, other unique surface applications of cement include roller-compacted concrete (RCC), precast pavements, and pervious concrete pavements. Cement is also used in numerous pavement repair techniques, as well as an array of pavement recycling and reclamation applications.
A great deal of research and effort by many sources has gone into developing literature about the indi-vidual pavement applications using cement. With so
many applications, engineers and other practitioners could benefit from one publication that integrates and summarizes all cement-based pavement applications and helps them select and apply appropriate solutions for specific needs. This publication fills that need.
The Guide to Cement-Based Integrated Pavement Solutions provides a clear, concise, and cohesive discussion of 10 cement-bound material options for specific engineering pavement applications, or solutions: new concrete pave-ments, concrete overlays, pervious concrete, precast pavements, roller-compacted concrete, cement-treated base, full-depth reclamation with cement, cement- modified soils, recycled concrete aggregates, and repair and restoration. Each application is presented as a method for meeting specific design and construction objectives that today’s pavement practitioners must accomplish. The benefits, considerations, brief descrip-tion, and summary of materials, design, and construc-tion requirements, as well as a list of sustainable attri-butes, are provided for every solution.
This guide is intended to be short, simple, and easy to understand. It was designed so that the most up-to-date and relevant information is easily extractable. It is not intended to be used as a design guide for any of the applications identified herein. Recommendations for additional information that can provide such details are given at the end of each solution discussion.
Who is this guide for?It was developed for practitioners, including engineers and managers who face decisions regarding what mate-rials to specify in the pavement systems they design or manage. The audience also includes city and county engineers, along with the A/E firms that often represent them, and state DOT engineers at all levels who are seeking alternatives in this era of changing markets.
Preface
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
xii
Important Definitions
This symbol represents applications of highly traf-ficked roadways that experience high volumes of heavy truck traffic such as major highways and interstates.
This symbol represents applications for city streets and local roads that experience moderate levels of passenger vehicle traffic and maybe some heavy truck traffic.
This symbol represents roadway shoulder applications.
This symbol represents applications including com-mercial parking lots, driveways, and residential roadways.
This symbol represents applications for general-pur-pose aviation and/or commercial or military airfield facilities.
This symbol represents applications for facilities that experience high volumes of heavy truck traffic and/or storage facilities, such as shipping yards, where heavy containers are stored for long periods of time.
Highways Commercial / Lightweight
Airfields
Heavy Industrial
Streets & Local Roads
Shoulders
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
xiii
ASTM
ASTM International, originally known as the Ameri-can Society for Testing and Materials, is an interna-tional standards setting organization.
Base
The pavement layer constructed immediately beneath a hot-mix asphalt (HMA) surface and sometimes beneath a concrete surface. Material requirements for this layer are more stringent than those for most sub-base and subgrade layers.
Concrete
An initially plastic (slumpable) mixture created by the combination of cement, coarse and fine aggregates, water, and various chemical admixtures that hardens to a solid material over time.
Concrete pavement
A pavement system in which the surface layer is concrete. Typical concrete pavement systems include a concrete surface over a subbase and subgrade layers.
Fine aggregate
Defined by ASTM C33 as sand with 95–100 percent of the total material passing a No. 4 (4.75 mm) sieve.
Fines
Portion of the soil finer than a No. 200 (75 µm) sieve.
Flexible pavement
A pavement system in which the surface layer is hot-mix asphalt (HMA). Typical flexible pavement systems include an HMA surface over a base, subbase, and subgrade layers.
Pavement system
The combination of surface, base/subbase, and improved subgrade layers constructed for the purpose of supporting traffic.
Portland cement
A commercial product that, when combined with water, forms a paste that over time becomes a hard-ened solid. It is typically combined with fine aggre-gates to form mortar or a combination of fine and coarse aggregates to form concrete.
Subbase
The pavement layer constructed between the base and subgrade in a flexible pavement system, or the layer often found beneath a concrete surface in a concrete pavement system.
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
xiv
Table of Solutions
Within an integrated pavement solutions system, numerous alternative paving materials and techniques are available. While their common link is the use of portland cement, there remain notable differences that must be recognized. To assist in the selection of the most appropriate solutions for a given project, Table 1 should be referenced.
Within this table, the various solutions are shown in the left column, along with a brief description of each. To assist in the selection of the most appropriate solutions, the challenges that a user might be facing are in the adjacent columns. This cross-referencing is intended to help narrow the selection of the available solutions. Complementing the table are both the ben-efits and typical applications. These too are intended to refine the selection of possible solutions.
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
xv
Table 1. Table of solutions
Solution / Definition Objectives BenefitsTypicalApplications
New Concrete Pavements
New concrete pavements include both jointed and continuously reinforced concrete pavements. Thicknesses can range from 6 to 15 inches, depending on traffic, environment, and soils.
• Provide long life and reduced maintenance.
• Improve the surface.
• Provide high load-carrying capacity.
• Expedite construction/renewal.
• Reduce urban heat island effect.
• Increase light reflectance.
• Provide a sustainable option.
• Concrete pavements can withstand many environments.
• Concrete pavements typically last much longer than their original design life.
• Concrete pavement surfaces reflect light and reduce the urban heat island effect.
• Vehicle fuel consumption for the driving public is reduced on concrete surfaces.
• Highways
• Streets and Local Roads
• Shoulders
• Commercial/ Lightweight
• Airfields
• Heavy Industrial
Concrete Overlays
Overlays are a method of rehabilitating and/or increasing the structural capacity of existing pavements. Bonded overlays are thin (2- to 6-in.) layers of concrete bonded directly to a sound underlying pavement in order to increase structural capacity. Unbonded overlays are used principally when the underlying pavement is in fair to poor condition and are thick (4 to 11 in.) enough to support the traffic loads but recognizing the structural capacity of the underlying pavement.
• Extend pavement life.
• Improve the surface.
• Increase load-carrying capacity.
• Expedite construction/renewal.
• Reduce urban heat island effect.
• Increase light reflectance.
• Provide a sustainable option.
• Reconstruction costs are avoided.
• Construction of an overlay is much faster than reconstruction.
• Concrete pavement surfaces reflect light and reduce the urban heat island effect.
• Highways
• Streets and Local Roads
• Shoulders
• Commercial/ Lightweight
• Airfields
• Heavy Industrial
Pervious Concrete
Pervious concrete is a paving material consisting of almost exclusively coarse aggregate, but with sufficient cement paste to bind the mixture into a strong but open (porous) material with exceptional drainage properties.
• Satisfy EPA Storm Water Phase II regulations.
• Earn LEED credits.
• Improve safety.
• Reduce tire-pavement noise.
• Provide a sustainable option.
• Pervious concrete is an EPA Best Management Practice.
• Stormwater runoff and flash flooding is minimized.
• Hydroplaning and splash and spray are minimized.
• Noise from the tire-pavement interaction is reduced.
• Pervious concrete surfaces reflect light and help reduce the urban heat island effect.
• Streets and Local Roads
• Shoulders
• Commercial/ Lightweight
Precast Pavements
Precast pavements are a technique for constructing or repairing a concrete pavement surface where casting and curing of panels are done in advance. Precast pavements are a highly durable finished pavement and not just a temporary fix. They are a repair option for jointed concrete pavements (JCP) or reconstruction option for both JCP and HMA pavements. Rapid placement of the hardened panels can then be conducted within short traffic closure windows.
• Provide long life.
• Improve the surface.
• Provide high load-carrying capacity.
• Expedite construction/renewal.
• Provide a sustainable option.
• Construction can be completed during short (overnight or weekend) closures.
• Lane closures and associated user delays during construction are minimized.
• Precast pavements are a highly durable finished pavement and not just a temporary fix.
• Precast pavement surfaces reflect light and help reduce the urban heat island effect.
• Highways
• Airfields
• Heavy Industrial
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
xvi
Table 1. Table of solutions (Continued)
Solution / Definition Objectives BenefitsTypicalApplications
Roller-Compacted Concrete
Roller-compacted concrete (RCC) is a stiff and strong concrete mixture that is typically placed with asphalt pavers as either a surface or a support layer. Roller-compacted concrete surfaces can be used for low-speed or industrial applications. Roller-compacted concrete layers can also serve as a support layer to a thin (1.5- to 2-in.) HMA (or occasionally concrete) surface.
• Provide low-cost option.
• Provide high load-carrying capacity.
• Expedite construction.
• Allow early opening to traffic.
• Provide a sustainable option.
• Roller-compacted concrete provides a strong, dense, and durable material that can be quickly constructed.
• Construction is fast with no forms or finishing.
• No steel reinforcement and minimum labor make RCC economical.
• For many applications, joint sawing is optional for aesthetic purposes resulting in additional cost savings.
• Roller-compacted concrete pavement surfaces reflect light and help reduce the urban heat island effect.
• Highways
• Streets and Local Roads
• Shoulders
• Airfields
• Commercial/ Lightweight
• Heavy Industrial
Cement-Treated Base
Cement-treated base (CTB) is a mixture of aggregate material and/or granular soils combined with engineered amounts of portland cement and water that hardens after compaction and curing to form a stronger, stiffer, and more durable paving material. Cement-treated base is used as a pavement base for flexible pavements or a subbase for concrete pavements.
• Provide a strong, uniform base/subbase for current and future loading conditions using in-place or locally available marginal soils and granular material.
• Reduce stresses on the subgrade.
• Stabilize a variety of soils with a single stabilizer.
• Reduce rutting and deflections in a flexible pavement surface.
• Improve the structural capacity of the existing soil.
• Provide a sustainable option.
• A stiffer base reduces deflections due to traffic loads, thereby extending pavement life.
• Subgrade failures, pumping, rutting, joint faulting, and road roughness are reduced.
• Base thickness is reduced compared to unbound granular base thicknesses.
• Marginal aggregates, including recycled materials, can be used, thus reducing the need for virgin, high-quality aggregates.
• Highways
• Streets and Local Roads
• Shoulders
• Airfields
• Commercial/ Lightweight
• Heavy Industrial
Full-Depth Reclamation
Full-depth reclamation (FDR) is a technique in which hot-mixed asphalt (HMA) material from the existing pavement is removed, combined with portland cement, and used to create a new and improved base. The FDR base is then topped with a new HMA or concrete surface layer.
• Provide a strong, uniform base/subbase for current and future loading conditions using existing failed asphalt surface and base material.
• Maintain existing grade with minimum material removal or addition.
• Reduce or totally eliminate the need for virgin aggregates.
• Reduce stresses on the subgrade.
• Reduce rutting and deflections in a flexible pavement surface.
• Improve the structural capacity of stabilized base over unstabilized base material.
• Provide pavement reconstruction method that is fast and minimizes traffic disruption.
• Provide a sustainable option.
• The performance of the base layer is improved over an unbound granular base.
• Little, if any, material is hauled off or onto the site, resulting in less truck traffic, lower emissions, and less damage to local roads. Work can be completed quickly compared to removal and replacement techniques.
• Full-depth reclamation process is economical compared to removal and replacement and thick overlays.
• Highways
• Streets and Local Roads
• Airfields
• Commercial/ Lightweight
• Heavy Industrial
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
xvii
Solution / Definition Objectives BenefitsTypicalApplications
Cement-Modified Soils
Cement-modified soils (CMS) are soils and/or manufactured aggregates mixed with a small proportion of portland cement. Cement-modified soils exhibit reduced plasticity, minimized volumetric changes due to moisture changes, increased bearing strength, and improved stability.
• Reduce the plasticity and high-volume change characteristics of clay soils due to moisture variations.
• Improve stability of a poorly graded sandy soil. Improve the properties of a sandy soil containing a high-plasticity clay.
• Provide a method to dry out a wet subgrade.
• Provide a firm construction platform to work on.
• Provide a sustainable option.
• Cement-modified soils provide a weather-resistant work platform for construction operations.
• Fatigue failures caused by repeated high deflections are controlled.
• There is a reduction in moisture sensitivity and subgrade seasonal load restrictions.
• No mellowing period is needed as required by other stabilizing agents.
• Highways
• Streets and Local Roads
• Shoulders
• Airfields
• Commercial/ Lightweight
• Heavy Industrial
Recycled Concrete Aggregates
Recycled concrete aggregates (RCA) are aggregates produced from the recycling of existing concrete. Existing concrete is removed, processed into appropriate aggregate sizes, and reused in various pavement applications.
• Recycle excavated concrete pavement.
• Minimize construction cost.
• Reduce dependence on good quality virgin aggregates, which may be hard to find or expensive to bring in.
• Provide a sustainable option.
• Recycled concrete aggregates are versatile because they can be used in any pavement layer.
• Material costs are reduced.
• Construction time can be expedited with on-site recycling plants.
• Pavement suffering from ASR or D-cracking can be recycled instead of discarded.
• The need for old concrete disposal is reduced.
• Highways
• Streets and Local Roads
• Shoulders
• Airfields
• Commercial/ Lightweight
• Heavy Industrial
Repair and Restoration
Repair and restoration is a series of techniques including diamond grinding, dowel bar retrofit, full and partial depth repairs, joint sealing, patching, and slab stabilization that extend the life of a concrete pavement. These techniques can often be used in lieu of resurfacing or reconstructing.
• Extend life.
• Improve the surface.
• Expedite construction/renewal.
• Repair and restoration fixes distressed concrete pavement (Comment—areas may not be isolated, i.e., diamond grinding an entire roadway).
• These are options for low-cost concrete pavement life extensions.
• Highways
• Airfield
• Streets and Local Roads
Table 1. Table of solutions (Continued)
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
xviii
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
1-1
New Concrete Pavements
Objectives•Providelonglifeandreducedmaintenance.
•Improvethesurface.
•Providehighload-carryingcapacity.
•Expediteconstruction/renewal.
•Reduceurbanheatislandeffect.
•Increaselightreflectance.
•Provideasustainableoption.
Solution•Constructanewconcretepavement.
Benefits•Concretepavementscanwithstandmanyenvironments.
•Concretepavementstypicallylastmuchlongerthantheiroriginaldesignlife.
•Concretepavementsurfacesreflectlightandreducetheurbanheatislandeffect.
•Vehiclefuelconsumptionforthedrivingpublicisreducedonconcretesurfaces.
Considerations•Theconcretemixturemustbedesignedproperlyfortheenvironment.
•Properconstructionpracticesareessentialtolong-termperformance.
Typical ApplicationsConcretepavementapplicationsincludehighways(mainline,shoulders,frontageroads),streetsandlocal
roads,aswellasheavyindustrialapplications,airfields(runways,taxiways,roadways,aprons,parkingfacili-ties),andcommercial/lightweightindustrialapplica-tionssuchasdrivewaysandparkinglots.
Highways
Commercial / Lightweight
Airfields
Heavy Industrial
Streets & Local Roads
Shoulders
DescriptionApavementstructureisacombinationofasurfacecourseandbase/subbasecoursesplacedonapreparedsubgrade.Anewconcretepavementisonewherethesurfacecourseismadeofconcrete(Figure1-1).
Prepared Subgrade
Concrete Surface
Subbase
Prepared Subgrade
Concrete Surface
Subbase
Figure 1-1. Schematic of typical concrete pavement cross-section
1 Guide to Cement-Based Integrated Pavement Solutions
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
NEW
CON
CRET
E PA
VEM
ENTS
1-2
ConcretepavementshavebeenbuiltintheUnitedStatessincethefirstconcretestreetwasbuiltinBelle-fontaine,Ohio,in1891.Thispavementisstillinser-vicetoday.Concretepavementscanbeveryversatile;theycanbedesignedtohandlethefreezingwintersofMichigan’sUpperPeninsulaorthescorchingheatofNewMexicointheSouthwest.Concretepavementscanbeadurable,economical,andsustainablesolutionformanyapplicationsifpropermaterialmixturesareusedandthepavementstructureisbothdesignedandconstructedproperly.
TherearedifferenttypesofconcretepavementsbuiltintheUnitedStates;however,thetwomostcom-mononesarejointedconcretepavements(JCP)andcontinuouslyreinforcedconcretepavements(CRCP).Eachtypeissuitablefornewconstruction,reconstruc-tion,andoverlaysofexistingroads.
Jointedconcretepavementcanbeeitherplain(JPCP)orreinforced(JRCP).Bothhaveregularlyspacedtransversecontractionjointswithdowelsforloadtransferandlongitudinalconstructionjointsheldtogetherwithtiebars.Concretewillcrack;jointsaredesignedtocontrolwherethesecracksoccur.Theideaistodesignajointspacingthatensuresthatcracksoccurunderthejointsinsteadofrandomlyacrossthepavement.Jointedreinforcedconcretepavementincludeswiremeshand/ordeformedsteelbarrein-forcementthroughouteachslab(theareaboundedbytransverseandlongitudinaljoints).Thereinforcementisintendedtoholdtightanycracksthatmayformwithintheslab.
Continuouslyreinforcedconcretepavementsdonotrequiretransversecontractionjoints,butdoincludetransverseandlongitudinalconstructionjoints.Continuouslyreinforcedconcretepavementscontaincontinuouslongitudinalandtransversereinforcementthroughtheentirepavement(morethanJRCP).Rein-forcementinCRCPisdesignedtocontroltransversecrackwidths;reinforcementkeepscracksheldtightlytogetherandisnotdesignedtohelpcarrytrafficloads.StandardCRCPdesignsareoftenchosenbystates(likeTexas,Virginia,andIllinois)toaccommodatehightrafficandheavyloads.
Figure1-2illustratestypicaljointingandreinforce-mentforJPCP,JRCP,andCRCPdesigns.
Concretepavementsareoftendesignedspecificallyforagivenproject;however,someagencieshaveadoptedstandardvaluesforthegeometriccharacteristicsof
Figure 1-2. Schematic of the various types of new concrete pavements (from IMCP manual, Iowa State University, 2006)
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s NEW
CONCRETE PAVEMENTS
1-3
pavementsaswellasforthematerials’specificationssothatdesignsbecomemorepractical.
Theexcellentperformanceofconcretepavementsreliesontheuseofsuitablematerials,anadequatedesign,andsoundconstructionpractices.Bothstruc-turalandfunctionalperformanceisenhancedwhenalloftheseaspectsarecarefullyidentifiedandaccountedfor.Themostinfluentialdesign-relatedvariablesforstructuralperformance(atagivenleveloftraffic)areslabthickness,jointspacing,reinforcement,concretestrength,andsupportconditions.Functionalperfor-manceofthepavementisoftenrelatedtofeatureslikesmoothness,texture,andnoise.Theseareaffected—inpart—bytheconcretepavementtexturealongwiththeconcretematerialusedand,inparticular,itsdurability.
MaterialsMixturesforconcretepavementstypicallyincorporatethefollowingconstituents:ablendofcoarseandfineaggregates,portlandcement,water,andsometimesothercementitiousmaterialssuchasflyashandslagcement,and/orchemicaladmixtures(seeFigure1-3).Thecompatibilityofmaterialsinconcretepavementsisimportantbecauseitwillaffectlong-termpavementperformance.
Ablendofcoarseandfineaggregatesistypicallyusedinconcretepavingmixtures.Theaggregatesareoftennaturalbutcanalsobemanufactured.Coarseaggregatesmayevenincludeapercentageofrecycledaggregates.AfineaggregateisdefinedbyASTMC33ashaving95percentormorematerialparticlespassingthe#4(4.75mm)sieve.ASTMC33alsoprovidesguidelinesontypicalaggregategradationsforconcrete.Moststateshavestandardsandspecifica-tionsthatidentifycertaingradationlimitsforspecificapplicationsandfurtheridentifyalimitforrecycledaggregatecontent.Aggregatesstronglyinfluencecon-crete’sfreshproperties(particularlyworkability)andlong-termdurability.Awell-gradedblendofaggre-gateswillfurtherensurelong-termpavementperfor-mance.Achievingawell-gradedaggregatesupplycanoftenbeattainedbyaddinganintermediate(#8to3/8in.[2.36to9.5mm])aggregate.
Portlandcementgivesthematerialitsstrengthandbindstheaggregatestogether.Therearedifferenttypesofcement,butthemostcommonforpavingincludeTypesI,II,I/II,andIII.TypeIiscommonlyusedinnormalconcretemixtures.TypeIIissimilartoTypeIbutgivesofflessheatandismoderatelysulfateresis-tant.ItiscommontouseaTypeI/IIcementinpavingapplications,whichmeetstherequirementsasbothaTypeIandaTypeII.TypeIIIcementsgainstrength
Figure 1-3. Concrete mixture constituents (from IMCP Manual, Iowa State University, 2006)
9–15% Cement
15–16% Water
25–35% Fine aggregate
30–45% Coarse aggregate
Paste (cement + water)
Mortar (paste + fine aggregate)
Concrete (mortar + coarse aggregate)
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
NEW
CON
CRET
E PA
VEM
ENTS
1-4
quicklyandareoftenusedinfast-trackpavingorrepair.BlendedcementssuchasTypeIP(portland-pozzolancement)orTypeIS(portlandblast-furnaceslag)cementsincludeothercementitiousmaterialsandareoptionsforuseinpavingmixtures.
Itiscommonforpavingmixturestoincludesupple-mentarycementitiousmaterials(SCMs)thatareaddedtothemixturebyreplacingapercentage(eithermassorvolumetric)oftheportlandcementcontent.Thesemayincludeindustrialbyproductslikeflyashorslagcement.Theproportionsinwhichthematerialsareusedusuallyvaryineverydesignandaretypicallyselectedtobalancecost,strengthrequirements,work-ability,anddurability.
Waterforconcreteshouldbepotable(fitforhumanconsumption).Somewaterrecycledfromreturnedconcreteandplantwashingcanbeacceptable.Speci-ficationsformixingwaterinconcretemixturescanbefoundinASTMC1602.Typicalwater-to-cementitiousmaterials(w/cm)ratiosfornormalconcretepav-ingmixturesrangefrom0.40to0.45.Higherw/cmratioswillresultinincreasedworkabilitybutalsolowerstrengthanddecreasedlong-termpavementperformance.
Admixturescommonlyusedinconcretemixturesincludeair-entrainingadmixtures,water-reducingadmixtures,retarders,andaccelerators.Air-entrainingadmixturesareusedtodevelopanairvoidsystemthatisnecessaryforconcretedurability,particularlyinfreeze-thawenvironments.Water-reducingadmixturesareusedtoreducew/cmratioswhileimprovingwork-ability.Retardersdecreasesettimeandaregenerallyusedinhotweatherplacements.Acceleratorsincreasesettimesforcoldweatherconcreting.Theamountofadmixturerequiredforeachdependsontheamountandtypeofcementitiousmaterialused.Itisagoodpracticetofollowthemanufacturer’srecommenda-tionsfordosage.Severaladmixturescanbeusedinonemixture,buttrialbatchesmustberuninordertoensurecompatibility.
Ifdesignedproperlyfortheenvironmentinwhichtheywillbeplaced,concretepavementswilllastalongtime.VariousAmericanConcreteInstitute(ACI)internationaldocuments,theNationalConcretePave-mentTechnologyCenter’s(CPTechCenter)Integrated
Materials and Construction Practices for Concrete Pave-ment (IMCP) Manual,andthePortlandCementAsso-ciation’s(PCA)Design and Control of Concrete Mixturesprovidedetailedrecommendationsofhowtopropor-tionamixtureandensuregoodperformanceinavari-etyofenvironments.Ingeneral,compatiblematerialscoupledwithlowpermeability(i.e.,loww/cmratiosandtheuseofSCMs)andaproperairvoidsystemwillresultingoodlong-termconcreteperformance.
DesignAconcretepavementdesignincludescalculatingarequiredpavementthickness,determiningajointlayout,andidentifyingtherequiredsteelcontent(ifapplicable).ThemostnationallyacceptedmethodforconcretepavementdesignistheAmerican Association of State Highway and Transportation Officials (AASHTO) Design Guide(1993).Amajoreffortiscurrentlyunder-waytoregionallycalibrateandshifttothenewAASHTOMechanistic-EmpiricalPavementDesignGuide(M-EPDG).
OtherdesigntoolssuchastablesfromtheACICom-mittee330reportGuide for the Design and Construction of Concrete Parking Lots, the Continuously Reinforced Concrete Pavement Design and Construction Guidelines(Rasmussen,Rogers,andFerragut2009),andtheAmericanConcretePavementAssociation’sStreetPavesoftwareprogramcanbeusedtoprovidesatisfactoryresults.
Aconcretepavementneedstobethickenoughtowithstandthestressandfatiguecausedbytheenvi-ronmentinwhichitisconstructedandtheloadsunderwhichitmustperformoverananticipatedlifetime.Somecriticaldesigninputsforcalculatingthicknessincludetheestimatedtrafficloadingduringthedesignlife,failurecriteria,concretestrength,andstiffnessanddrainagecharacterizationofsupportinglayers.
ForJCP,thespacingofcontractionjointsisdesignedatintervalssuchthatpotentialvolumetricchangesoftheconcretedonotresultinunintendeddamagetothepavement(i.e.,uncontrolledcracking).TheFederalHighwayAdministration’sHighPerformanceConcretePaving(HIPERPAV)softwarecanbeusedasaneffectivetoolfordesigningproperjointspacing.
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s NEW
CONCRETE PAVEMENTS
1-5
Jointedplainconcretepavementtransversecontrac-tionjointsaretypicallyspacedat15to20ft(5to6.1m)inordertocontrolcracking.TransversecontractionjointsinJRCPcanbespacedfartherapart(typicallyabout30to40ft[9to12m])becauseofthesteelcontent.ContractionjointsarenotrequiredinCRCP.Continuouslyreinforcedconcretepavementisdesignedtohaverandomtransversecracksthatareheldtightlytogetherbythereinforcingsteel.Inallconcretepavements,longitudinalconstructionjointsareplacedbetweenlanesandtransverseconstructionjointsareconstructedattheendofeachday’spaving.
Reinforcementusedinconcretepavementsincludesdowels,tiebars,andcontinuoussteelbarsthroughouttheslab.Dowelsprovideloadtransferandverticalsupportforjointedpavementsatthetransversejoints.Tiebarspromoteaggregateinterlockandaremostoftenusedalonglongitudinaljoints.WireordeformedsteelbarreinforcementinJRCPkeepsrandomcracksheldtightlytogether.Designingthereinforcementincludesidentifyingthetype,size,andspacing.Moststatesalreadyhavestandardsandspecificationsforthedesignofpavementreinforcement.Thecriticaldesignfactorsforreinforcementincludepavementthickness,concretematerialproperties,andtypeofsupport.
Asubbaseisusuallyadvisableforheaviertraffickedpavements.Asubbaseinlightdutypavements(e.g.,residentialandcollectorstreetsandparkinglots)isnotalwaysnecessaryanddependsonunderlyingsoils,drainageneeds,andloads.
ConstructionTheconstructionofaconcretepavementinvolvesobtainingthematerials,batchingandmixing,placing,texturing,andcuring.
Batchingistheprocessofmeasuringtheconstituentsbymassorvolumeaccordingtoamixturedesignandintroducingthemintoamixer.Thesizeofthebatchdependsonthecapacityofthemixer.Inmostcases,eitherastationaryoraready-mixplantisusedformixingpavingconcrete,whichisthentypicallytrans-portedtothejobindumptrucksforslipformpaving.Truckmixerscanalsotransportpavingconcretebutareusedmoreoftenforfixed-formplacements.Whenplanningforequipment,itisimportanttoconsider
theproductioncapacityandtypicalhaultimes.Proj-ectsincongestedareas,whichdonotallowforon-siteproduction,mayrequireamixdesignthatpermitsextendedhaulingandplacementtimes.
Concreteisplacedusingslipformorfixed-formpav-ingmethods,dependinguponthenatureoftheproj-ect.Theconcretemixturesrequiredbyeitherplace-mentmethodcanvarysignificantly.Slipformpavingoperationsrequirealow-slumpmixturethatwillnotsloughafterextrusionbythepavingmachine,whilefixed-formpavingoperationsrelyonahigherslumpmixturethatwillfloweasilytofilltheforms.Slipformpavingisgenerallyforplacementsthatrequirehighproductionrates,suchasmainlinepaving.Fixed-formpavingisadaptabletonearlyanyplacementcircum-stance,butbecauseitrequiressettingupsideformstoholdtheconcrete,itisgenerallyusedinirregularsectionswhereslipformpavingisnotpractical.
Contractionjointsshouldbeformedorsawcutassoonaspossibleandaretypicallysawedtoadepthofone-thirdthatofthepavementthickness.Figure1-4depictsthisprocess.ContractorexperienceandtoolssuchastheFederalHighwayAdministrationHIPER-PAVcomputersoftwareprogramcanhelpidentifypropersawcuttimesbasedonmaterials,design,andconstructionmethods.Jointsshouldbesealedwithanappropriatematerial,althoughsomestatesare
Figure 1-4. Sawcutting JPCP
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
NEW
CON
CRET
E PA
VEM
ENTS
1-6
experimentingwithunsealedcontractionjoints.Localpracticeshouldgovernaccordingly.
Whenused,dowelscanbeplacedinprefabricateddowelbasketsandsecuredinplacepriortopaving.Figure1-5showsfreshconcreteplacedoverdowelbarssecuredindowelbarbaskets.Alternatively,dowelscanbeinsertedintothefreshconcreteduringplacementusingadowel-barinserter(seeFigure1-6).
Thereareseveraloptionsforplacingtiebarsaswell.Atie-barinserteriscommonlyusedtoplacetiebarsbetweenlaneswhentwolanesareconstructedatthesametime.Forlaneadditions,single-piecetiebarscanbedrilledandinsertedintotheexistinghardenedconcreteandepoxiedintoplace.Benttiebarscanalsobeinsertedduringpavingandpulledstraightafterthepavementhashardened.Finally,two-piecetiebars
canbeused,whereone-halfofthetiebarisinsertedduringplacementandlaterthesecondhalfisscrewedintothefirsthalf.
ReinforcingsteelforJRCPandCRCPisplacedbeforepavingbeginsasseeninFigure1-7andFigure1-8.
Textureisappliedtothesurfaceoftheconcreteafterplacementandbeforecuring.Thepurposeistoincreasefrictionandimprovewetweatherdrivingconditions.Twocommonlyusedwettexturetech-
Figure 1-5. Concrete placed over dowel baskets
Figure 1-6. Dowel-bar inserter
Figure 1-7. JRCP reinforcement in place before paving
Figure 1-8. CRCP reinforcement placed before paving
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s NEW
CONCRETE PAVEMENTS
1-7
niquesincludetininganddrag.Tinedsurfacesareappliedusingasteelrakeandcanbeappliedlongitu-dinallyorinthetransversedirection.Dragtexturesareappliedbydraggingapieceofartificialturforheavyburlaponthesurface(seeFigure1-9).Additionaltexturesincludediamondgrindingandgrooving.Ifused,grindingandgroovingaredoneaftercuringandoncethepavementisabletowithstandtheweightofthemachinethatmustbeused.
Propercuringmeasurespreventrapidwaterlossfromthemixtureandallowmorethoroughcementhydra-tion.Itisessentialtoapplycuringasearlyaspossibleafterplacingconcreteandtocontinueuntilenoughhydrationhastakenplaceandtherequiredhardenedpropertieshavebeenachieved.Avarietyofcuringmethodsandmaterialsisavailableforconcretepave-ment,includingwatersprayorfog,wetburlapsheets,plasticsheets,andinsulatingblankets.Mostcom-monlyused,however,istheapplicationofaliquidmembrane-formingcompound(seeFigure1-10).
Sustainability•Concretepavementshavelongevity.
•Industrialby-products(e.g.,flyash,slagcement,silicafume)canbeusedinmixturedesign.
•Concretepavementsurfacesarehighlyreflective,makingthemmorevisibleatnight.Bettervisibilityimprovessafety.Brighterstreetsrequirelesslighting;therefore,energyrequirementsarereduced.
Figure 1-9. Burlap drag on fresh concreteFigure 1-10. Curing compound applied by spray nozzles on a cure cart
•Concrete’slightsurfacereducestheurbanheatislandeffect.
•Studiessuggestconcretesurfacesreducevehiclefuelconsumptionforthedrivingpublic.
For More InformationAmericanAssociationofStateHighwayandTrans-portationOfficials.1993.American Association of State Highway and Transportation Officials (AASHTO) Design Guide.
AmericanConcreteInstitute.2008.Guide for the Design and Construction of Concrete Parking Lots.ACIReport330R-08.
AmericanConcretePavementAssociation.2002.Concrete Pavement for General-Aviation, Business and Commuter Aircraft.ConcreteInformation,IS202.
AmericanConcretePavementAssociation.2005.StreetPave Computer Program.SW03.
AmericanConcretePavementAssociation.2006.Design of Concrete Pavement for Streets and Roads. Con-creteInformation,EB237.
FederalHighwayAdministration.1990.Concrete Pave-ment Joints.TechnicalAdvisory,T5040.30.
FederalHighwayAdministration.2007.HIPERPAVsoftware,www.HIPERPAV.com,www.fhwa.dot.gov/pavement/pub_details.cfm?id=660.
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
NEW
CON
CRET
E PA
VEM
ENTS
1-8
Novak,L.andD.Bilow.2009.A Sustainable Approach to Outdoor Lighting Utilizing Concrete Pavement. SP393.
PortlandCementAssociation.2011.Design and Con-trol of Concrete Mixtures.15thedition.
PortlandCementAssociation.2010.Integrated Paving Solutions—Concrete Pavements.http://www.integrated-pavingsolutions.org/concretepavements.html.
Rasmussen,R.O.,S.I.Garber,G.Fick,T.R.Ferragut,andP.D.Wiegand.2008. How to Reduce Tire-Pavement Noise: Interim Better Practices for Constructing and Texturing Concrete Pavement Surfaces.PooledFundTPF-5(139).
Rasmussen,Rogers,andFerragut.2009.Continuously Reinforced Concrete Pavement Design and Construction Guidelines.Draft,FederalHighwayAdministrationandContinuouslyReinforcedConcreteInstitute,May.
Taylor,G.andJ.Patten.2006.Effects of Pavement Structure on Vehicle Fuel Consumption—Phase III.Proj-ect54-HV775,TechnicalReportCSTT-HVC-TR-068,NRC-CNRC,January27.
Taylor,P.,S.Kosmatka,G.Voigt,etal.2006.Integrated Materials and Construction Practices for Concrete Pave-ment: A State-of-the-Practice Manual.NationalConcretePavementTechnologyCenter/CenterforTransporta-tionResearchandEducation,IowaStateUniversity,December.
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
2-1
Concrete Overlays
Objectives•Extendpavementlife.
•Improvethesurface.
•Increaseload-carryingcapacity.
•Expediteconstruction/renewal.
•Reduceurbanheatislandeffect.
•Increaselightreflectance.
•Provideasustainableoption.
Solution•Constructaconcreteoverlay.
Benefits•Reconstructioncostsareavoided.
•Constructionofanoverlayismuchfasterthanreconstruction.
•Concretepavementsurfacesreflectlightandreducetheurbanheatislandeffect.
Considerations•Properassessmentofexistingpavementconditionsisnecessarytodeterminefeasibility.
•Anylossofsubgradesupportordrainageproblemsmustbecorrected.
Typical ApplicationsConcreteoverlayscanbeusedfortherehabilitationofavarietyofsurfaces.However,variousfactorsneedtobetakenintoaccountbeforeselectingtheappropri-ateoverlaysystemincludingtheexistingpavement
condition,overlaydesigndetails,pre-overlaywork,constructionmaterials,andfuturemaintenanceandrehabilitation.
Highways
Commercial / Lightweight
Airfields
Heavy Industrial
Streets & Local Roads
Shoulders
DescriptionConcreteoverlaysareadurableandcost-effectivemaintenanceandrehabilitationalternativewhenproperlydesignedandconstructed.Rehabilitationoftheexistingpavementissimplifiedbythefactthatitdoesnotneedtoberemoved,andquiteoften,fewpre-overlayrepairsneedtobecarriedout.Overlayspreservepavementserviceabilityforseveraldecadesbeyondtheoriginaldesignlife.
Overlaysareconstructedusingconventionalconcretepavingprocedures.Jointspacing,loadtransferdesign,andreinforcementmethodsaresimilartonewpave-ments.Inaddition,typicalconcretemixturesareused,whichcanbeadjustedtoallowforhigherstrengthsoranexpeditedconstructionprocess.
2 Guide to Cement-Based Integrated Pavement Solutions
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
CONC
RETE
OVE
RLAY
S
2-2
Concreteoverlaysareabletorestorethefunctionofafacilityveryeffectively.Theconstructionofanewsurfaceresultsinsubstantiallyimprovedsurfacechar-acteristicsincludingrideability,improvednoiselevels,andincreasedfriction.Beforeplacementofanoverlaycanoccur,theexistingpavementmustbesufficientlyevaluatedinordertoensureitisagoodcandidateforoverlayconstruction.Therearetwomaintypesofcon-creteoverlays:bondedandunbonded(seeFigure2-1).
Bothoverlaytypescanbeconstructedoverconcrete,flexible,andcompositepavements(seeFigure2-2).
Bondedoverlaysarerelativelythinandconstructeddirectlyontopofexistingpavements.Bondedover-laysrestorethesurfaceandaddsomestructuralcapacitytoroadwaysthataresomewhattomoderatelydistressed.
Unbondedconcreteoverlaysaretypicallythickerthanbondedoverlaysandrequireaseparationlayer(i.e.,bondbreaker).Unbondedoverlaysrestorethestruc-turalcapacityofexistingpavementsthataremoder-atelytosignificantlydeteriorated.
MaterialsThetypeofprojectandtheconstructionscheduledictatetheconcretemixturematerials.Conventionalmixturesshouldbecarefullyselectedtoallowtheresultingmixturetobedense,relativelyimpermeable,andresistanttoenvironmentaleffectsoverthelengthofitsservicelife.Mostagenciesspecifya28-dayunconfinedcompressivestrengthrequirementof4,000psi(28MPa)fortheirpavements.OntheotherFigure 2-1. Unbonded overlay
Figure 2-2. Overlay applications
Bonded Overlay Systems Unbonded Overlay Systems
Bonded Concrete Overlays of Concrete Pavements–previously called bonded overlays–
Bonded Concrete Overlays of Asphalt Pavements–previously called ultra-thin whitetopping–
Bonded Concrete Overlays of Composite Pavements
Unbonded Concrete Overlays of Concrete Pavements–previously called unbonded overlays–
Unbonded Concrete Overlays of Asphalt Pavements–previously called conventional whitetopping–
Unbonded Concrete Overlays of Composite Pavements
In general, bonded overlays are used to add structural capacity and/or eliminate surface distress when the existing pavement is in good structural condition.
Bonding is essential, so thorough surface preparation is necessary before resurfacing.
In general, unbonded overlays are used to rehabilitate pavement with some structural deterioration.
They are basically new pavements constructed on an existing, stable platform (the existing pavement).
(Resurfacing/Minor Rehabilitation) (Minor/Major Rehabilitation)
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s CONCRETE OVERLAYS
2-3
hand,somestatesuserapid-strengthconcretemix-turesthathaveahighcementitiousmaterialcontent,alowwater-to-cementitiousmaterials(w/cm)ratio,andsmallertopsizeaggregate.Thesetypesofmixturescanbeusedwithacceleratingadmixturestoallowforfasteropeningtimes.
TypeIandTypeIIcementsarenormallyusedincon-cretemixturesforconcreteoverlays.TypeIIIcementcanbeusedwhenhighearlystrengthisdesired.Vari-ousadmixturesarecommonlyintroducedaswellandincludewaterreducers,airentrainment,andSCMs.Supplementarycementingmaterialssuchasflyashandslagcementimprovetheworkabilityofthecon-crete,increasedurabilityandlong-termstrength,andextendplacementtimeduringhotweather.Amaxi-mumw/cmratioof0.45iscommonforpavementsinamoistenvironmentwithmanyfreeze-thawcycles,althoughlowervaluesareusedtominimizedryingshrinkage.
Aggregatesusedinoverlaysrangefromcrushedstonesandrivergravelstorecycledconcreteaggregateandshouldpossessadequatestrengthandbephysicallyandchemicallystablewithintheconcretemixture.Themaximumcoarseaggregatesizeshouldbeusedinordertominimizepasterequirements,reduceshrink-age,minimizecosts,andimprovemechanicalinter-lockpropertiesatjointsandcracks.
Theseparationlayerinunbondedoverlaysiscriticaltotheirlong-termperformance(seeFigure2-3).A1-in.(25mm)thickconventionalHMAsurfacemix-tureismostcommonlyused.However,theuseofanonwovengeotextileinterlayerhasbeenshowntobeapromisingalternative.Researchandprojectexperi-encehasshownthatnonwovengeotextilesprovide
Figure 2-3. Typical cross-section of unbonded overlay
Separation Layer
Prepared/Untreated Subgrade
Overlay
Base/Subbase
Existing Pavement
Prepared/Untreated Subgrade
Overlay
Base/Subbase
Existing Pavement
uniform,elasticsupportoftheconcreteslab,reducepumpingprocesses,andpreventreflectivecracking.
Concreteoverlayshavebeenshowntoadd15to30yearsofservicelifetoaroadway.Long-termdurabilitywillresultfrompropermaterialsselection,sufficientpre-overlaywork,effectivedesignmethods,andsuc-cessfulconstructionpractices.Pavementmanagementandpreservationactivitiessuchasroutineandpre-ventivemaintenanceandminorrehabilitationshouldbecarefullyconsideredaswellinordertofurtherincreasetheservicelifeofaconcreteoverlay.
DesignThedesignofanoverlayincludescalculatingathick-ness,establishingajointlayout,anddeterminingreinforcementcontent.Thereareseveralstate-of-the-practicedesignmethodsthatarelistedinTable2-1.Inthecaseofanunbondedoverlay,theoverlaydesignmustincludeaninterlayer.
Bonded OverlaysThedesignofabondedconcreteoverlaydependsontheassumptionthattheoverlayandexistingpavementwillbeonemonolithicstructure.
Forbondedoverlays,typicalthicknessesrangefrom2to5in.(50to125mm).Forhigh-trafficroads,a6in.(150mm)bondedoverlayorgreatercanbeconstructed.
Table 2-1. Current state-of-the-practice overlay design methodologies
State-of-the-Practice Concrete Overlay
Design Methods
Bonded concrete overlay of concrete pavements
• 1993 AASHTO Guide
• M-E PDG
Bonded concrete overlay of HMA and composite pavements
• 1993 AASHTO Guide
• M-E PDG
• Modified ACPA method
Unbonded concrete overlay of all types
• 1993 AASHTO Guide
• M-E PDG
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
CONC
RETE
OVE
RLAY
S
2-4
TypicaljointdesignpatternsarelistedinTable2-2.Recommendationsforjointdepthdependonthetypeofjointandexistingpavement,aswellastheequip-mentusedforconstruction.
Overlayjointwidthsforbondedconcretepavementsareequaltoexistingpavementjoints.Forconven-tionalsaws,transversejointsinbondedoverlaysofconcretepavementsshouldbefulldepthplus0.50in.(13mm).Similarly,longitudinaljointsarecuteitherfulldepthornolessthanhalfofthepavementthick-ness.TransversejointsinbondedoverlaysofHMAandcompositepavementsconstructedusingacon-ventionalsawshouldbecuttoadepthofone-fourthofthepavementthickness(T/4);longitudinaljointsshouldbesawcuttoadepthofone-thirdofthepave-mentthickness(T/3).
Reinforcementsuchastiebars,dowelbars,andotherembeddedsteelproductsaretypicallynotusedforoverlayslessthan6in.(150mm)thick.
Continuouslyreinforcedbondedoverlayshavebeenconstructedbysomeagencies,andinthesecasessteelisplacedatsufficientdepthtoprovideaminimumof3in.(75mm)ofconcretecover.Thesteelcanbeposi-tioneddirectlyontopoftheoldpavement,whichhastheaddedbenefitofeffectivelyrestrainingconcretevolumechangesattheinterface.
Table 2-2. Joint pattern for bonded concrete overlays
Joint Pattern for Bonded Overlays
Bonded Overlay of JPCP Match joints with existing pavement joints.
Bonded Overlay of CRCPMatch longitudinal joints with existing pavement joints.
Bonded Overlay of HMA and Composites
Use small square patterns in the range of 3 to 8 ft. (0.9 to 2.4 m).
Maximum dimensions of the square panels should be no greater than 1.5 times the thickness of the overlay.
Avoid longitudinal joints in the wheel paths.
Unbonded OverlaysThedesignofanunbondedoverlayissimilartodesigninganewconcretepavementoverastabilizedsubbase.Anunbondedoverlaydesignassumesthereisnobondbetweenthebottomsurfaceoftheoverlayandthetopsurfaceoftheexistingpavement.
Thedesignthicknessofanunbondedoverlaytypicallyrangesfrom6to11in.(150to280mm)butcanbeasthinas4in.(100mm)forlower-volumeroadsorwhenoverheadclearanceisanissueandloadingislight.
Unbondedoverlaysofconcretepavementsrequireaninterlayerasaseparationlayer.Thedesignofthesepa-rationlayeriscriticaltothelong-termperformanceoftheoverlaybecauseithelpspreventreflectivecrackingandallowstheoverlayandexistingpavementstruc-turetomoveindependentlyofoneanother.Drainagemustbeconsideredduringdesignofthisinterlayer.
Themostcommonseparationlayerisa1-in.(25-mm)HMAsurfacemixture;however,anonwovengeotex-tilespecificallymanufacturedforuseasaninterlayerbetweencementitiouslayershasalsobeenusedasanalternative.ThethicknessoftheHMAinterlayerissometimesincreasedslightlyforunbondedoverlaysofCRCP.Anincreaseininterlayerthicknessmayalsoberequirediftheexistingpavementexperienceslargerdegreesoffaulting.Ageotextileisnotagoodalterna-tiveinsuchcases.
ItshouldbenotedthatwhileunbondedoverlaysofHMAorcompositepavementsdonotrequireaninterlayer,ifafull-depthconcretepatchhasbeencon-structedintheexistingpavementitmustbeisolated.Onetechniqueforisolatingthepatchistoapplyadebondingagentormaterial(e.g.,asphaltemulsioncoating)tothesurfaceofthepatchbeforethecon-structionoftheoverlay.
Foranunbondedoverlayofconcrete,manystatestrytomatchthetransversejointsintheoverlaywiththoseintheexistingpavement.However,somestatesintentionallydesigntransversejointsintheoverlayatanoffsetfromthoseintheexistingpavement.Jointspacingsaredesignedbasedonthethicknessoftheoverlay.TypicaljointpatternsforunbondedoverlaysarelistedinTable2-3andTable2-4.Jointdepthsdependonthetypeofsawusedforconstruction.
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s CONCRETE OVERLAYS
2-5
Unbondedoverlaysofconcrete,HMA,orcompositepavementsshouldincludetransversejointsthat,whencutwithconventionalsaws,areconstructedatdepthsofT/4toT/3.LongitudinaljointsshouldbeatdepthsofT/3.
Dowelsareusedinjointswhentheoverlay’sdesignthicknessisgreaterthan8in.(200mm)andexpectedtocarryheavytrucktraffic.Tiebarsmaybeappropri-ateinopen-ditch(orshoulder)sectionsifthedesignthicknessisgreaterthan5in.(125mm).Tiedshoul-dersaretheapprovedmethodforprovidingoverlayedgesupport.Tiebarsatconfinedcurb-and-guttersectionsshouldbeconsiderediftheoverlaydesignthicknessisgreaterthan6in.(150mm).
ConstructionTheconstructionofanoverlay(seeFigure2-4)isaprocesssimilartoconventionalconcretepavement
Unbonded Overlays of Concrete Pavements
Design Thickness Joint Pattern
<5 in. (125 mm) Use square panels measuring 6 x 6 ft (1.8 x 1.8 m) panels
5 – 7 in. (125 – 175 mm)
Maximum joint spacing in feet = 2 times thickness in inches
> 7 in. (175 mm) Maximum joint spacing =15 ft. (4.6 m)
Table 2-3. Joint pattern for unbonded concrete overlays of concrete pavements
Unbonded Overlays of Concrete Pavements
Design Thickness Joint Pattern
<6 in. (150 mm) Maximum joint spacing in feet = 1.5 times thickness in inches
6 – 15 in. (150 – 380 mm)
Maximum joint spacing in feet = 2 times thickness in inches
> 15 in. (380 mm) Maximum joint spacing =15 ft. (4.6 m)
Table 2-4. Joint pattern for unbonded concrete overlays of HMA and composite pavements
andincludesconcreteproduction,preparationoftheexistingsurface,andtheplacement,curing,andsaw-cuttingofnewconcrete.
Whilemixingandplacingarethesameforbothbondedandunbondedoverlays,therearesubtledif-ferencesintheotherstepsoftheprocessbasedonthetypeofoverlaytobeconstructedandthetypeofexistingpavement.
Bonded Overlays Forbondedoverlaysofanykind,repairsneedtobemadetoplacetheexistingpavementingoodcondi-tionoratleastinfaircondition.Forexistingconcretepavement,thatwouldincluderepairingwidecracksandsubsurfacevoids.ForexistingHMAandcompos-itepavements,repairsincludeaddressingpotholes,moderatetoseverealligatorcracking,andlossofsubgradesupport.Methodsforaddressingtheverti-calmovementofconcreteincompositepavementsareexplainedintheNationalConcretePavementTech-nologyCenter’sGuide to Concrete Overlays.
Afterrepair,thesurfaceofanexistingpavementispreparedandcleanedofanyloosedebris.Surfacepreparationandcleaningpromotesabondbetweentheoverlayandexistingpavement.Themostcom-monmethodusedtoprepareaconcretesurfaceisshotblasting.Thesurfaceisthencleanedbysweepingand/orusingcompressedair.MillingHMAand/orcompositesurfacescanalsobeanappropriatemethodofrepair;however,toomuchmilling(foreitherrepairorpreparation)willreducestructuralcapacity.The
Figure 2-4. Unbonded concrete overlay construction over a nonwoven geotextile interlayer
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
CONC
RETE
OVE
RLAY
S
2-6
minimumremainingHMAneedstobeatleast3in.(75mm),preferably4in.(100mm)MillingneedstobedonetothetopofthenearestHMAliftlinetopreventfracturingoftheHMA.Hot-mixasphaltandcompositepavementsarethensweptcleanorblownwithcompressedair.
Placementofconcreteoverexistingpavementsshouldfollowstandardconventionalconcretepavingprac-tices(seeFigure2-5).PlacementoverHMAorcom-positepavementscanbeaccomplishedusingfixed-formorslipformconstructiontechniques.WhenHMAsurfacetemperaturesaregreaterthan120°F(49°C),thesurfaceshouldbecooledbyapplyingwaterinfrontofthepaver;however,nostandingwatershouldbeallowedatthetimeofpaving.Ifthesurfacecan-notbecooledsufficiently,placementmayneedtoberescheduledforanotherpartoftheday.
Curingabondedoverlayandproperlytimedsawcutsarecriticalfactorsnomatterwhattypeofexistingpavementliesbeneathit.Thenewconcretelayerhasahighsurface-to-volumeratiothatmakesitvulnerabletorapidmoistureloss.Curingcompoundsshouldbeappliedattwicetheratetypicalforconventionalcon-cretepracticesandshouldcoatthesurfaceandedgesevenly.Jointsmustbecutassoonaspossibleandcanbeconstructedwithconventionalorearly-entrysaws.Itmaybenecessarytohavemultiplesawsonhandinordertosawcutjointsfastenoughtopreventuncon-trolledcracking.Jointsealantsmaynotberequired.
Unbonded Overlays Beforeanunbondedoverlayisconstructedoveranyexistingpavementtype(i.e.,concrete,HMA,orcom-posite),distressesthatcauseamajorlossofstructuralintegritywillrequirerepair.Hot-mixasphaltandcompositepavementsmaybemilledtocorrectsurfacedefectsthatare2in.(50mm)ordeeper.Aminimumof3to4in.(75to100mm)ofHMAmustremaininplaceaftermillingiftheoverlaydesignthicknessis6in.(150mm)orgreater.Iflessthan6in.(150mm),anoverlayofatleast6in.(150mm)ofremainingHMAisrecommended;otherwise,abondedoverlayshouldbedesigned.
Afterrepair,ifanyarenecessary,thesurfaceissweptorairblown.Iftheexistingpavementisconcrete,thesurfacemustbevoidofanyloosedebrisbeforethebond-breakerinterlayerisconstructed.Hot-mixasphaltandcompositesurfacescanbesimplysweptclean;smallremainingdebrisisnotanissue.
Likebondedoverlays,placementofunbondedover-laysoverexistingconcreteshouldfollowstandardconventionalconcretepavingpractices.PlacementoverHMAorcompositepavementscanbeaccom-plishedusingfixed-formorslipformconstructiontechniques.Thepavementneedstobecooledpriortopaving,whensurfacetemperaturesaregreaterthan120°F(49°C).Dowelbasketsmustbesecuredproperlytotheexistingpavementunlessadowelbarinserterisused.
Curingandsawcuttingfollowsthesamelogicasthatforbondedoverlays:quick,thorough,evenapplica-tionofcuringandproperlytimedsawcutsarecriticaltolong-termperformance.
Sustainability•Concreteoverlaysmakeuseoftheexistingpave-ment,eliminatingtheneedforremovalanddisposal.
•Concreteoverlayscanbeconstructedandopenedtotrafficwithinaday,reducingusercostsanddriverfrustration.
•Concreteoverlayspossessalowlife-cyclecost,withlonglivesandminimalmaintenancecosts.
Figure 2-5. Bonded overlay construction
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s CONCRETE OVERLAYS
2-7
•Industrialby-products(e.g.,flyash,slagcement,silicafume)canbeusedinmixturedesign.
•Concretepavementsurfacesarehighlyreflective,makingthemmorevisibleatnight.Bettervisibilityimprovessafety.
•Concrete’slightsurfacereducestheurbanheatislandeffect.
For More InformationAmericanConcreteInstitute.2006.Concrete Overlays for Pavement Rehabilitation.ReportNo.ACI325.13R-06.
Harrington,D.,etal.2008.Guide to Concrete Overlays—Sustainable Solutions for Resurfacing and Rehabilitating Existing Pavements.SecondEdition.NationalConcretePavementTechnologyCenter.September.
NationalConcretePavementTechnologyCenter.2010.Guide for the Design of Concrete Overlays Using Existing Methodologies (Draft).Fall.
PortlandCementAssociation.2010.Integrated Paving Solutions—Concrete Overlays.http://www.integrated-pavingsolutions.org/ConcreteOverlays.html.
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
3-1
Pervious Concrete
Objectives•SatisfyEPAStormWaterPhaseIIregulations.
•EarnLEEDcredits.
•Improvesafety.
•Reducetire-pavementnoise.
•Provideasustainableoption.
Solution•Useperviousconcrete.
Benefits•PerviousconcreteisanEPABestManagementPractice.
•Stormwaterrunoffandflashfloodingisminimized.
•Hydroplaningandsplashandsprayareminimized.
•Noisefromthetire-pavementinteractionisreduced.
•Perviousconcretesurfacesreflectlightandhelpreducetheurbanheatislandeffect.
Considerations•Perviousconcretemayrequireperiodicmaintenancetopreventclogging.
•Perviousconcretemaycauseravelingandabrasionproblemsonhigher-speedroadways.
Typical Applications
Commercial / Lightweight
Streets & Local Roads
Shoulders
OrganizationssuchastheGreenHighwaysPartner-shipareactivelyfacilitatingtheredevelopmentofmanyinner-citylandscapesinanefforttomakethemmoresustainable.Perviousconcretepavementsarebecomingmoreattractivealternativesforavarietyofnewconstructionandurbanretrofitapplications.Figure3-1showsperviousconcreteinstalledataparktomeetAmericanswithDisabilitiesAct(ADA)accessibilityrequirements.Figure3-2showsperviousconcreteinstalledataparktominimizeimpervious
Figure 3-1. Miller Park in Fair Oaks, California
Figure 3-2. Imperial Beach Sports Park, California
3 Guide to Cement-Based Integrated Pavement Solutions
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
PERV
IOUS
CON
CRET
E
3-2
surfacerunoff.Figure3-3showsaChicago,Illinois,neighborhoodalleyconstructedofperviousconcretetominimizerunoff.Theabilitytomanagestormwaterrunoffmakesperviousconcreteacommonchoiceforapplications,includingcitystreetsandlocalroads,shoulders,pedestrianwalkways,alleys,andparkinglots.
Perviouspavementcanalsobeusedasasubbaseforconventionalconcrete,atlow-watercrossings,andforrecreationalareassuchastenniscourtsandgreenhouses.
Figure 3-3. Pervious concrete for alley in Chicago, Illinois
storageandretentiontimeforegressandpercolationofwaterintothesubgrade.Themixdesigniscom-posedofnarrowspeciallygradedcoarseaggregate,cement,water,andasmallamountoffineaggregate.Theresultisamaterialwithinterconnectedairvoidsofbetween15to25percent,dependingonthemixdesign.Whencomparedtoconventionalconcretepavements,theexposedaggregatesurfaceofpervi-ousconcretecanprovideenhancedtractionforbothpedestriansandvehicles.Thepotentialforvehicleshydroplaningduringwetweatherconditionsisalsoreduced.Ifnotcuredproperly,surfaceparticlesmaybecomelooseorravel.Withpropercompactionandcuring,ravelingcanbeprevented.
Figure 3-4. Pervious concrete
Figure 3-5. Pervious concrete pavement parking lot
DescriptionPerviousconcrete(seeFigure3-4)isusedinahighlypermeablepavementthatcapturesrainwaterandallowsittopassthroughthesurfaceandpercolateintotheunderlyinglayer.Perviousconcretepavementsminimizestormwaterrunoff,flashflooding,andstandingwater;theycanreduceoreveneliminatetheneedforon-siteholdingpondsorburiedstormwaterretentionstructures.Figure3-5showsaparkinglotmadeofperviousconcrete.
Perviousconcretecanbeplaceddirectlyonadrain-ableaggregatebase,abovesand,oronsoilswithsuf-ficientdrainageproperties.Perviousconcretemayalsobeplacedoverimpermeablesoilssuchasclay;how-ever,provisionsneedtobemadeforadequatewater
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s PERVIOUS CONCRETE
3-3
Perviousconcretepavementscanlastformorethan20yearswithnominalmaintenance.Toensureadequatedrainage,routinemaintenanceistypicallyrequired.Theamountofroutinemaintenancedependsontherateofsoilloading.Sweeping,vacuuming,orpowersprayingcanbeusedtomitigatecloggingandrestorepermeability.Thesepavementshavebeensuccessfulinfreeze-thawandsulfateenvironmentswhendesignedandconstructedproperly.Theabilityforperviousconcretepavementstodrainwaterquicklyminimizesthesaturationwithinthevoidsthatcouldotherwisefreezeandcausedamage.Perviousconcreteismoresusceptibletosulfateenvironments;however,ifkeptisolatedfromsulfaterichsoilsorproducedwithSCMs,perviouspavementscanperformsatisfactorily.
MaterialsSeeTable3-1fortypicalvaluesofmaterialpropertiesforperviousconcrete.
Perviousconcreteusesbasicallythesamematerialsasconventionalconcrete.Oneexceptionisthatthefineaggregatecontentislimitedandthecoarseaggregateiskepttoanarrowgradation(seeFigure3-6).Com-monlyusedgradationsofcoarseaggregateincludeASTMC33No.67,No.8,orNo.89.Number89istypicallyusedinmixturesforparkinglotsandpedes-trianwalkways.Roundedorangular(i.e.,crushed)aggregatescanbeusedforperviousconcretemixtures.Maximumaggregatesizeandthetypeofaggregatewillaffectthefinalsurfacetexture.
Figure 3-6. Fresh pervious concrete
Table 3-1. Typical values for material properties
Property Typical Values
Unit Weight 70-80% of conventional concrete mixtures
Density100-125 lb/ft3 (1600-2000 kg/m3) – this is dependent on mix design and construction procedures
Percent Voids 15-25%
Permeability 100 in./hr – over 2000 in/hr (2.5-50 m/hr)
Compressive Strength
2500 psi (17 MPa) but this can range from 500 – 4000 psi (3.5 – 28 MPa)
Perviousconcretemixescontainminimalamountsofwater,withwater-to-cementitiousmaterials(w/cm)ratiosaround0.30;however,ratiosashighas0.34to0.40havebeenusedsuccessfullywiththeproperinclusionofchemicaladmixtures,suchasretarders.
Portlandcementsandblendedcementsmaybeusedinperviousconcreteapplications.Inaddition,SCMssuchasflyash,pozzolans,andslagcementcanbeusedtoimprovematerialpropertiessuchasworkabil-ityandstrength.Infreeze-thawenvironments,air-entrainingadmixturesarerecommended.
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
PERV
IOUS
CON
CRET
E
3-4
DesignAperviouspavementisdesignedaseitheranactiveorapassivesystem.Anactivesystemisdesignedtohandlemuchmorerainfallthanisexpectedtofallonjustthepavementitself.Apassivesystemisapervi-ousconcretepavementthathandlesrainfallthatfallsdirectlyonthepavementsurface.Apassivemitiga-tionsystemcancapturemuch,ifnotall,ofthe“firstflush,”butitisnotintendedtooffsetexcessrunofffromadjacentimpervioussurfaces.Anactivemitiga-tionsystemisdesignedtomaintainrunoffatasiteatspecificlevels.Foreithersystem(activeorpassive),aproperthicknessmustbedesigned.Perviouspave-mentthicknessisdesignedbasedonthecalculationofhydrologicandmechanicalpropertiesincludingtheamountofexpectedrainfall,pavementcharacter-istics,andunderlyingsoilproperties.StandarddesignproceduresincludeACI522R,ACI325.9R,orACI330R.SeeFigure3-7forperviousconcretesubjectedtorainfall.
Designsforperviousconcretepavementsurfacesmustconsiderpermeabilityandstoragecapacity.
Figure 3-7. Pervious concrete pavement in the rain
Designersshouldensurethatpermeabilityissufficienttoaccommodateallrainfallingonthesurfaceoforrunningontoperviousconcrete.Whilethepermeabil-ityofperviousconcretesisafactorindesign,theflowratethroughthesubbaseandsubgrademaybemorerestrictiveandcontroltheamountofwaterleavingthesystem.Thetotalstoragecapacityoftheperviousconcretesystemincludesthecapacityoftheperviousconcretepavement,thecapacityofanysubbaseused,andtheamountofwaterthatleavesthesystembyinfiltrationintotheunderlyingsoil.
Infreeze-thawclimates,perviousconcretesystemsshouldnotbedesignedtostorewaterintheconcreteitselfbecauseoftheexpansivenatureofwaterwhenitfreezes.Fortypicaldesigns,thestoragecapacityandinfiltrationrateofthesubbaseandsubgradesaresignificant.
Typicaldesignthicknessesinclude5-to6-in.(125-to150-mm)thickperviousconcretewithadrainableaggregatebasegenerally6-to12-in.(150-to300-mm)thick.Thebaselayershouldallowapercolationrateof0.5in./hr(13mm/hr)ifnooverflowpipingis
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s PERVIOUS CONCRETE
3-5
installed.Infreeze-thawenvironments,aminimumof12in.(300mm)ofadrainableaggregatebase,suchas1-in.(25-mm)crushedstone,istypicallyconstructed.Athickerpavementsystemmayneedtobeusedifheavierloadsandhighertrafficareanticipated,orifthepercolationrateofthebaselayerisinadequate.
Figure3-8,Figure3-9,andFigure3-10showtypicalschematicsofperviouspavementdesigns.Fullexfil-trationdesignsareonlyusedwherethenaturalsoilhasahighinfiltrationrateorgoodlateralpermeability.Partialexfiltrationdesignsarethemostcommonandtypicallyusedtocontrolthewaterqualityvolume.Noexfiltrationdesignsareusedwhereproblemsoilsareaconcernorwhereitisnotdesirabletointroducewaterintoadjacentlocations.
Figure 3-8. Schematic of pervious full exfiltration pavement design
Precast Pavement
Drainable Base
Untreated Subgrade
Pervious Pavement
Drainable Base
Untreated Subgrade
Friction Reducing Medium
Figure 3-9. Schematic of pervious partial exfiltration pavement design
Figure 3-10. Schematic of pervious no exfiltration pavement design
Precast Pavement
Drainable Base
Untreated Subgrade
Pervious Pavement
Drainable Base
Untreated Subgrade
Tile Drain w/ Up-Turned ElbowFriction Reducing Medium
Precast Pavement
Drainable Base
Untreated Subgrade
Pervious Pavement
Drainable Base
Untreated Subgrade
Friction Reducing Medium
Tile Drain
ConstructionTheconstructionofperviousconcretepavementincludesproductionofconcrete,placement,compac-tion,andcuring.
Perviousconcreteproductionrequirestightercon-trolofmixtureproportioning.Itisalsoimportanttomaintainaggregatemoistureatsaturatedsurfacedrymoisturecontentduringproduction.Waterabsorbedbythemixturefromaggregatesthataretoodrywillresultinamixthatistoodryforplacementandcom-paction.Toomuchwaterinaggregateswillincreasew/cmanddecreasestrengthanddurability.
Alowslumpandstifferconsistencymaydischargeslowerfromtransitmixersthanconventionalconcrete.Waterreducersandviscosity-modifiedadmixturescanbeusedtoincreaseflowabilityandmaintainstabilityoftheconcreteduringdischargeandplacement.Unitweightorbulkdensitytestsprovidethebestroutinetesttomonitorquality,aswellasseven-daycorestoevaluatethicknessandstrength.
Conventionalformworkistypicallyusedtoplaceperviousconcrete,andplacementshouldbecontinu-ouswithspreadingandstrikeoffactivitiesperformedinarapidmanner.Compactionandfinishingisgenerallyaccomplishedbyaweightedroller-screedthatspinsasitispulledacrossthefreshconcrete.Thespinningtubeprovidessomesurfacecompactionandcreatesasmoothuniformsurface(Figure3-11).Recommendedjointspacingsof20ft(6m)havebeensuggested,althoughsomeinstallationshavehadjointspacingsof45ft(13.5m)ormorewithout
Figure 3-11. Compacting the placed pervious concrete
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
PERV
IOUS
CON
CRET
E
3-6
uncontrolledcracking.Becausesettingtimeandshrinkageareacceleratedinperviousconcretecon-struction,jointsareusuallytooledintotheconcretesoonafterconsolidationwitharollingjointtool.
Theopenstructureandrelativelyroughsurfaceofperviousconcreteexposemoresurfaceareaofthecementpastetoevaporation,makingcuringextremelyimportant.Curingforperviousslabsandpavementsbeginsbeforetheconcreteisplaced—thesubgrademustbemoistenedtopreventitfromabsorbingmoisturefromtheconcrete.Afterplacement,fogmist-ingfollowedbyplasticsheetingistherecommendedcuringprocedure,andsheetingshouldremaininplaceuntiltheconcreteachievesadequatestrengthtosupportthetrafficloadwithoutdamagingthesurface(seeFigure3-12).Curingshouldbestartedassoonaspracticallypossibleafterplacing,compacting,andjointing.
Sustainability•Heatandlightisreflectedduetoitslightercolorandlowerdensity,decreasingtheimpactofheatislandeffects.
Figure 3-12. Curing pervious concrete with plastic sheeting
•Perviousconcretereducesrunoffandthushelpspreventpollutionofnaturalbodiesofwater.
•Theneedforon-siteholdingpondsorexpensiveirrigationsystemsisreducedoreliminated,resultingindecreasedcostsandmoreuseablelandspace.
•Safetyisimprovedbecausethepotentialforhydro-planingisreducedsincewaterisabletoescapefromthesurface.
•Noiseisreduced,improvingtravelingexperience.
For More InformationAmericanConcretePavementAssociation.2006.Stormwater Management with Pervious Concrete Pave-ment.ConcreteInformation,IS334P.
AmericanConcretePavementAssociation.2007.Green Highways.ConcretePavementResearchandTechnologySpecialReport,SR385P.
AmericanConcreteInstitute.2010.Pervious Concrete.ACICommittee522,522R.
GreenHighwaysPartnership.www.greenhighway-spartnership.org.
NationalReadyMixedConcreteAssociation.Pervious Concrete.www.perviouspavement.org.
Obla,K.2007.Perviousconcreteforsustainabledevelopment.InRecent Advances in Concrete Technol-ogy.Washington,D.C.
PortlandCementAssociation.2010.Integrated Paving Solutions—Pervious Concrete.http://www.integrated-pavingsolutions.org/perviousconcrete.html.
Tennis,P.D.,M.Leming,andD.J.Akers.2004.Pervi-ous Concrete Pavements.EB302.02.Skokie,Illinois:PortlandCementAssociation;SilverSpring,Maryland:NationalReadyMixedConcreteAssociation.
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
4-1
Precast Pavements
Objectives•Providelonglife.
•Improvethesurface.
•Providehighload-carryingcapacity.
•Expediteconstruction/renewal.
•Provideasustainableoption.
Solution•Useprecastconcretepavementsystems.
Benefits•Constructioncanbecompletedduringshort(over-nightorweekend)closures.
•Laneclosuresandassociateduserdelaysduringconstructionareminimized.
•Precastpavementsareahighlydurablefinishedpavementandnotjustatemporaryfix.
•Precastpavementsurfacesreflectlightandhelpreducetheurbanheatislandeffect.
Considerations•InitialcostsaregenerallyhigherthanconventionalPCCpavement.
•Thelearningcurveforproduction,placement,andtestingcanbesteep.
Typical ApplicationsPrecastconcretepavementsaretypicallyusedforhighway,airfield,andheavyindustrialapplications.
Highways
Airfields
Heavy Industrial
DescriptionPrecastpavementsareconstructedusingprefabricatedconcreteslabsinstalledoverapreparedsubbaseorexistingpavement(seeFigure4-1).Precastpanelsarefabricatedoffsiteatestablishedprecastconcretefacilitiespriortoconstruction,transportedtothejobsite,andtheninstalledonsiteandopenedtotraf-fic.PrecastpavementshavebeenusedprimarilyforreconstructionandrepairofJCP—buthavealsobeenusedfornewconstruction—andhavethepotentialtobeusedforreconstructionofHMApavements.Precastpavementsystemscanalsobeusedasanunbondedoverlay,acost-effectivesolutiontoaddstructuralcapacityandextendthelifeofanexistingroadway.
Thebenefitsofprecastpavementareprimarilyrealizedthroughreconstructionofexistingfacilities
Prepared Subgrade
Precast Pavement
Subbase
Prepared Subgrade
Precast Pavement
Subbase
Prepared Subgrade
Precast Pavement
Subbase
Friction Reducing Medium
Figure 4-1. Precast pavement system cross-section
4 Guide to Cement-Based Integrated Pavement Solutions
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
PREC
AST
PAVE
MEN
TS
4-2
duringshortclosures,asshowninFigure4-2dur-ingthenighttimereconstructionofInterstate66inVirginia.Precastpavementhasalsobeenusedsuc-cessfullyfornewconstructionofhighways,likethatshowninFigure4-3inIndonesia.Forthisproject,upto0.6miles(1.0km)ofprecastpavementwasplaceddaily.
RepairorreconstructionofJCPandHMApavementsusingprecastpavementsystemscanbeaccomplishedquickly,duringshortovernightorweekendclosures,thusreducinguserdelayandassociatedcosts.Precastpanelscanbeusedforisolatedfull-depthrepairs,suchasjointreplacements,forsingleormultipleconsecu-tiveslabreplacements,orfortotalreconstructionofanentiresection.
TherearetwoprimarytypesofprecastpavementsystemsusedintheUnitedStatestodate.Thefirst
Figure 4-2. Nighttime placement of precast panels in Virginia
Figure 4-3. Precast pavement system in Indonesia
typeofsystemusesprestressedconcretepanelsthatarepretensionedinonedirectionduringfabricationandposttensionedtogetherintheotherdirectionafterplacementonsite.Theothertypeofsystemisajointedsystem,whichreplicatesconventionalJCPusingprecastpanels.Fortheprestressedsystem,loadtransferbetweenpanelsisprovidedbyposttension-ing;dowelsareusedforthejointedsystem.Decidingonwhichsystemtousewilldependprimarilyonthetypeofapplicationbutalsoonissuessuchascostandcontractorexpertise.
Unlesstheyaretobeusedasatemporarypatch,precastpavementsaredesignedtoperformequaltoorbetterthannewconcretepavement.Whiletheridequalityofthesurfaceasinstalledisacceptableforopeningtotraffic,diamondgrindingcanbeusedtoensurethefinalridingsurfacemeetsthestringentrequirementsforhigh-speedroadways.
MaterialsPrecastconcretehasbeenprovenadurablehigh-performanceproductforbridgeandcommercialbuildingconstruction.Theconcretemixturesusedaresimilartothoseutilizedforotherprecastelementsandarenotrestrictedto“paving”mixtures.However,considerationmustbegiventopavement-specificrequirements,suchasrequirementsforskidresistanceanddurabilityinpotentiallyaggressiveenvironments.Highstrength,lowpermeabilityconcretemixtureswithaloww/cmratioanduniformaggregategrada-tionareusedroutinelybyprecastfabricationplantsandwillgenerallybesuitableforpavementpanelsaswell.
Strengthrequirementsaretypicallynotdifficulttoachieveduetotheneedforrapidproductionofprecastpanelsbyturningoverthecastingbedseverydayoreveryotherday.Typicalprecastpavementmixturesaredesignedforaverage28-daycompres-sivestrengthsbetween4,000and6,000psi(28–41MPa),andhigherstrengthsusuallyachieved.Forprestressedprecastpanels,strengthsof3,000to4,000psi(21–28MPa)aretypicallyrequiredforreleaseofpretensioning.Lowpermeabilitypreventschloridesandothercorrosiveagentsfrompenetratingthecon-creteandreachingthereinforcementandprestressing
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s PRECAST PAVEM
ENTS
4-3
steelinthepanels.Aggregatesmustmeetspecifiedskid-andabrasion-resistancerequirementstypicalforpavements.
DesignForprestressedprecastpavementsystems,thepremisefordesignistofirstcalculatethethicknessthatwouldberequiredforconventionalconcretepavement,thentoreducethatthickness,asmuchaspractical,byadjustingtheprestresslevelssuchthatstressesintheprecastpavementwillbeequivalenttotheconven-tionalconcretepavement.Additionalprestresscanbeaddedtofurtherincreasethedesignlifeofthepave-ment.Precastpanelsaretypicallyaminimumof8in.(200mm)thick,buttheycanbeadjustedasnecessarytomatchthethicknessandcross-sectionoftheexist-ingpavement.
JointedprecastpavementsystemsaretypicallydesignedtoreplicateconventionalJCP.Forrepairorreconstructionprojects,theprecastpanelsaredesignedtomatchthethicknessoftheslabbeingremovedminus1/4–1/2in.(6–13mm)toaccommo-dateirregularitiesinthebasebeneaththepavementslabbeingremoved.Fornewconstruction,thepanelsaredesignedtomatchthethicknessthatwouldbespecifiedforaconventionalconcretepavementdesignbasedonprojectconditions.
Forprestressedsystems,therearetwotypesofjoints:(1)theintermediatejointsbetweentheindividualpanels,and(2)theexpansionjointsattheendsofeachposttensionedsectionofprecastpanels.Theintermediatejointsare“nonworking”jointsthatareposttensionedtogetherandsealedwithepoxyappliedtotheabuttingfacesoftheprecastpanelsduringconstruction.Theexpansionjointsaredesignedtoaccommodateor“absorb”movementduetoexpan-sionandcontractionoftheposttensionedslabs.
Forjointedsystems,doweledjointsareusedsimilartoconventionalJCP.However,itshouldbenotedthatthereisnotanysignificantcontributiontoloadtransferfromaggregateinterlock,asisthecaseforconventionalJCP.Groutormortaristypicallyusedtoensurefullbeddingofthedowelbarsintheprecastpanelsafterinstallationandtofillthejointbetweenthepanels.
Prestressedpanelsaretypicallydesignedwithminimalnonprestressedreinforcement.Thisisbecausepre-stressinghelpstominimizeoreveneliminatecrack-ingthroughso-called“elasto-plastic”behavior,whichhelpskeepanycracksthatdoformtightlyclosed.Jointedprecastpanelsaretypicallyheavilyreinforcedwithtwomatsofmildsteelreinforcementtopreventanycracksthatmayformduringhandlingorfromwideningoverthelifeofthepavement.
Subbaselayers,ifincludedintheprecastpavementdesign,shouldbedesignedtoprovideuniformsup-port.TypicalbasematerialsincludeHMA,crushedstone,stonedust,andleanconcrete.
ConstructionPrecastpavementconstructionencompassesprefabri-cationoftheconcretepanelsandsubsequentplace-mentatthejobsite.
Theprefabricationprocessincludessettinguptheformstoverystricttolerances,securingreinforcement,prestressing,andaddingotherembedmentswithintheforms.Nextintheprefabricationprocessisplac-ingconcreteintotheforms(Figure4-4andFigure4-5),screeding,texturing,andcuringtheconcrete.Finally,removingthepanelsfromtheforms,complet-inganyadditionalstepsrequiredbeforeplacement,andstockpilingthepanelsforshipmenttotheprojectconcludestheprocess.
Aprimarybenefitofprefabricationisthehighdegreeofqualitycontrolthatexistsinprecastconcretefacili-tiesalongwiththecontrolledenvironmentunderwhichthepanelscanbeproduced.Thishelpstoensureuniformityofmaterials,workmanship,andadequatecuringfortheprecastpanels.Goodcon-structionpracticesrecommendthatanestablishedprefabricationfacilitybeused,asopposedtoatempo-raryplantsetupnearthejobsite.
Deliveryoftheprecastpanelstothesiteisacriti-calaspectoftheinstallationprocess,andcaremustbetakentoensurethatthepanelsarenotdamagedinanywayduringhandlingorshipping.Figure4-6andFigure4-7showtypicalplacementmethodsforprecastpavementsystems.Providingaflat,uniform,andstableplatformfortheprecastpanelstoreston
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
PREC
AST
PAVE
MEN
TS
4-4
Figure 4-4. Concrete poured into form for precast panel
Figure 4-5. Vibrators for consolidation of concrete around reinforcement in precast prestressed panel
isimportant,regardlessofthesubbasematerialused.Forprestressedprecastsystems,someformoffriction-reducingmaterialisneededbetweentheprecastpavementandunderlyingsubbasematerialtoreducefrictionalrestraintstressesthatcanaccumulateduringposttensioninganddailyexpansionandcontractioncycles.Tohelpensurefullsupportbeneaththepanels,groutorurethanefoamistypicallyinjectedbeneaththeslabsafterinstallationtofillanyvoidsthatmayexist.
Theconstructionprocessvarieswitheachjob,butbasedonthetypeofprecastpavementsystemused,commonstepsincludethefollowing:
•Sawcuttingandremovingexistingpavement(repair/reconstruction)orensuringthesubbaseisproperlyprepared(newconstruction)
Figure 4-6. Placement of precast panel for precast JCP system
Figure 4-7. Placement of a prestressed precast panel
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s PRECAST PAVEM
ENTS
4-5
•Sawcuttingandjackhammeringdowelslotsordrill-ingandepoxyingdowels(jointedsystems)
•Finallevelingandgradeadjustmentofthesubbase
•Installationoftheprecastpanel(s)
•Applyingtemporaryposttensioningtopulladjacentpanelstogether(prestressedsystem)
•Applyingfinalposttensioningafterafullsectionofpanelshavebeeninstalled(prestressedsystem)
•Backfillingofthedowelslots(jointedsystems)andposttensioningblockouts(prestressedsystem)
•Groutingofposttensioningtendons(prestressedsystem)
•Groutingorfoaminjectionbeneaththepanels
•Fillingjointsaroundtheperimeterofthepanels(jointedsystems)
•Sealingjoints
•Diamondgrindingforsmoothness(asnecessary)
Sustainability•Materialusageisoptimizedthroughminimizingthethicknessoftheprecastpanels.
•Constructionwasteisreducedbecausetheexactamountofnecessarycomponentsisdeliveredtothesite—thereisnoadditional“incidental”thicknesstotheslab.
•Thereissignificantusercostsavingsinclud-ingfuelconsumptionandlostworktimeduetodelays.
•Anysparecomponents/panelscanberecycled,andtheirmaterialsusedagaininanotherproduct.
•MixturesforprecastsystemsuselocallyderivedmaterialsandcanincorporaterecycledSCMslikeflyashandslagcement.
For More InformationBuch,N.2007.Precast Concrete Panel Systems for Full-Depth Pavement Repairs: Field Trials.ReportNo.
FHWA-IF-07-019,FederalHighwayAdministration,February.
FederalHighwayAdministration.2009.Precast Prestressed Concrete Pavement for Reconstruction and Rehabilitation of Existing Pavements.TechBrief,FHWA-IF-09-008,www.fhwa.dot.gov/pavement/pub_details.cfm?id=632.
Merritt,D.K.,B.F.McCullough,N.H.Burns,andA.K.Schindler.2000.The Feasibility of Using Precast Concrete Panels to Expedite Highway Pavement Construc-tion.ReportNo.FHWA/TX-01/1517-1,CenterforTransportationResearch,February.
Merritt,D.K.,B.F.McCullough,andN.H.Burns.2002.Construction and Preliminary Monitoring of the Georgetown, Texas Precast Prestressed Concrete Pave-ment.ResearchReport1517-01-IMP,CenterforTransportationResearch,UniversityofTexasatAustin,December.
Merritt,D.K.,A.J.Miron,R.B.Rogers,andR.O.Rasmussen.2007.ConstructionoftheIowaHighway60PrecastPrestressedConcretePavementBridgeApproachSlabDemonstrationProject.IowaHighwayResearchBoard(IHRB)ProjectHR-1085,TheTranstecGroup,July.
Nantung,T.,J.Firmansjah,E.Suwarto,andA.Karya.2010.DesignandconstructionofprecastprestressedconcretepavementinIndonesia.InProceedings,2010 fib International Congress and PCI Annual Convention/Bridge Conference,21May–2June,Washington,D.C.
PortlandCementAssociation.2010.Precast/Prestressed Concrete.www.cement.org/buildings/precast_splash,(15June2010).
Tayabji,S.andK.Hall,K.2010.Precast Concrete Panels for Repair and Rehabilitation of Jointed Concrete Pavements.ReportNo.FHWA-IF-09-003,FederalHighwayAdministration,April.
TheTranstecGroup.2010.PrecastPavement.TheTranstecGroup,www.precastpavement.com(15June2010).
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
5-1
Roller-Compacted Concrete
Objectives•Providealow-costpavementoption.
•Provideastrong,durablepavementthatwillsup-portheavyloads.
•Minimizetrafficdisruptionandprovideforrequiredearly-openingtotraffic.
•Widenalaneoraddashoulderinacost-effectivemanner.
•Provideasustainableoption.
Solution•Constructwithroller-compactedconcrete(RCC).
Benefits•Roller-compactedconcreteprovidesastrong,dense,anddurablematerialthatcanbequicklyconstructed.
•Constructionisfast,withnoformsorfinishing.
•NosteelreinforcementandminimumlabormakeRCCeconomical.
•Formanyapplications,jointsawingisoptionalforaestheticpurposesresultinginadditionalcostsavings.
•Roller-compactedconcretepavementsurfacesreflectlightandhelpreducetheurbanheatislandeffect.
Considerations•AmixerwithadequateenergyisrequiredtomixRCC.
•Typically,anasphalt-typepaverisusedforplacement.
•Surfacetypicallyisnotassmoothorconsistentinappearanceasconventionalconcrete.
•Forhighertrafficspeeds,thesurfacemayneedtobediamondgroundortoppedwithaconcreteorHMAoverlay.
Typical ApplicationsRoller-compactedconcretepavementapplicationsincludestreetsandlocalroads,highwaysandshoul-ders,airfields,heavyindustrial,andcommercial/lightindustrial.Roller-compactedconcreteisanidealcandidateinsituationswheresurfacesmoothnessandappearancearesecondarytohighdurability,lowmaintenance,earlytrafficking,andlowinitialcost.
Roller-compactedconcretewithasurfacetreatmentsuchasdiamondgrindingoranoverlaycanbeusedforpavementsthatexperiencehigh-speedtraffic,includinghighways.Insuchapplications,RCCactsasabaseorsubbase.
Highways
Commercial / Lightweight
Airfields
Heavy Industrial
Streets & Local Roads
Shoulders
5 Guide to Cement-Based Integrated Pavement Solutions
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
5-2
ROLL
ER-C
OMPA
CTED
CON
CRET
E DescriptionRoller-compactedconcretehasasimilarstrengthtoconventionalconcrete,yetitcanbemoreeconomi-cal.PavementswithRCCcanresistruttingandspansoftlocalizedsubgrades.Theywillnotdeformunderheavy,concentratedwheelloads,willresistdeteriora-tionfromfuelorhydraulicfuelspills,andwillremainrigidunderhightemperatures.ThecompressivestrengthofRCCiscomparabletothatofconventionalconcrete,rangingfrom4,000to6,000psi(28to41MPa),withflexuralstrengthranginginvaluesfrom500to1,000psi(3.4to6.9MPa).Thestrengthmakesitabletowithstandhighconcentratedloadsandimpactsfromheavyindustrial,military,andminingapplications,aswellassupportlightvehicletrafficshortlyafterplacement.
Roller-compactedconcretecanbeusedasapavementsurfacelayerforlow-speedroadsandindustrialfacili-tieswheresurfacesmoothnessandappearancearenotamajorconcernascomparedtohighdurability,lowmaintenance,andlowinitialcost(seeFigure5-1).Diamond-groundRCChadbeenusedsuccessfullyonurbanarterialswithoutanyadditionalsurfacetreat-ment.Roller-compactedconcretecanalsobeabaseorsubbaseforhighwaysandotherhigh-speedtrafficroadways(seeFigure5-2andFigure5-3).
Roller-compactedconcretecombinesvariousaspectsofconventionalconcretepavementmaterialspracticeswithsomeconstructionpracticestypicalofflex-iblepavements.Ithasthesamebasicingredientsasconventionalconcrete:cement,water,andaggregates(suchasgravelorcrushedstone),butitistypically
Figure 5-1. Typical RCC versus PCC surface
Figure 5-2. Pavement cross-section with RCC surface
Prepared Subgrade
Subbase
RCC
Prepared Subgrade
Subbase
RCC
Figure 5-3. Pavement cross-section with RCC base
Prepared Subgrade
RCC
Pavement Surface
Prepared Subgrade
RCC
Pavement Surface
placedwithasphalt-typepavingequipmentandcompactedbyvibratorysteeldrumrollerstoaspecificdensity(seeFigure5-4).
Unlikeconventionalconcrete,RCCisa“drier”mixandstiffenoughtobecompactedbyvibratoryrollers.SincethepastecontentinRCCislower,lessconcreteshrinkageandreducedcrackingfromshrinkage-relatedstressesresult.Inaddition,non-air-entrainedRCCpavementscanprovidereliableanddurableper-formanceinfreeze-thawenvironmentsaslongasthemixisproperlyproportionedwithadequatecementcontentandsoundaggregates.Theconcretemustalsobethoroughlymixed,adequatelycompacted,andproperlycured.
Figure 5-4. RCC construction for commercial and heavy industrial applications
RCC Pavement
PCC Pavement
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
5-3
ROLLER-COMPACTED CONCRETE
MaterialsThegoalinselectingtheappropriatequantityofmate-rialsforRCCistoproportionthemixsothatthereisenoughpastetocovertheaggregatesandfillthevoids(seeFigure5-5).PrimarydifferencesinproportionsbetweenRCCpavementmixturesandconventionalconcretepavementmixturesarethefollowing:
•Roller-compactedconcreteisgenerallynotairentrained.
•Roller-compactedconcretetypicallyhasalowerwatercontent.
•Roller-compactedconcretetypicallyhasalowerpastecontent.
•Roller-compactedconcretegenerallyrequiresalargerfineaggregatecontentinordertoproduceacombinedaggregatethatiswellgradedandstableundertheactionofavibratoryroller.
•Roller-compactedconcreteusuallyhasanominalmaximumsizeofaggregatenotgreaterthan3/4in.(19mm)inordertominimizesegregationandpro-ducearelativelysmoothsurfacetexture.
Aggregateselectionisveryimportant.Naturalorman-ufacturedaggregatescanbeused.Mineralaggregatesconstituteupto85percentofthevolumeofRCCandplayaninfluentialroleinachievingtherequiredworkability,specifieddensityinthefieldundervibra-torycompaction,compressiveandflexuralstrengths,thermalproperties,long-termperformance,anddurability.Aggregatefinesaretypicallyintherangeof2–8percent,passingthe#200(75μm)sieve.Siltsandclays,however,shouldbeavoided.
CementitiousmaterialsusedinRCCpavementmix-turesincludeportlandcementorblendedhydrauliccementandmayincludepozzolanssuchasflyashandslagcement.TypesIandIIcementsarecommonlyusedinRCCpavements.TypeIIIcanbeusedwhenearlystrengthgainisrequired,andTypeVcanbeusedinareasthathavespecificsoilconditionscallingforthistypeofcement.
Theuseofablendedcement,pozzolans,orslagcementmayhelpimproveworkability,reducethepotentialforalkali-aggregatereaction,extendthecom-pactiontime,andhelpinfreeze-thawconditions.TheuseofflyashinRCCisaneffectivemeansofprovid-ingadditionalfinematerialneededtoensureadequatecompaction,particularlyinthoseRCCmixturesthatcontainstandardgradedconcretefineaggregate.
Watercontentshouldbejustenoughtoensureevendistributionofthepastebutdryenoughtosupportthevibratoryroller(seeFigure5-6).Chemicaladmix-turescanbeused.Higherdosagesofchemicaladmix-turesthaninconventionalconcretemayberequired,andmaterialcompatibilityshouldbeestablishedthroughtrialbatches.
DesignRoller-compactedconcretepavementsfallintotwomaincategories:(1)heavy-dutyindustrialpavements(e.g.,portsandmultimodalterminals),and
Figure 5-6. RCC material looks drier than conventional concreteFigure 5-5. Typical mix design constituents
RCC
50
45
40
35
30
25
20
15
10
50
Percent Total Weight
Cement + Fly Ash
Coarse Aggregate
Fine Aggregate
Water
Conventionalconcrete
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
5-4
ROLL
ER-C
OMPA
CTED
CON
CRET
E (2)pavementscarryingmixed-vehicletraffic(e.g.,trucksandpassengervehicles).Table7showsalistofdesignmethodologies.ThicknessdesignforRCCpavementsemploysthesamebasicstrategyasforcon-ventionalconcretepavements;however,therearenodowelsorsteelreinforcementinRCCtoaccommodateloadtransfer.Thepavementshouldbethickenoughtoallowforflexuralstressesandfatiguedamagecausedbywheelloadswithinallowablelimits.Fatigueduetoflexuralstressisusedtocalculatetherequiredpavementthickness.TheminimumthicknessofanRCCpavementistypically4in.(100mm).Asingleliftshouldbenothickerthan10in.(250mm).
Baseandsubbaselayerrequirementsaresimilartothoserequiredforconventionalconcrete;however,RCCcanbemoresensitivetothemoisturecontentofgranularsubbases.
Historically,RCCisconstructedwithoutjoints.WhenRCCisallowedtocracknaturally,aggregateinterlockusuallyprovidesadequateloadtransferacrossthecracks.Crackstypicallyoccurat20-to60-ft(6.1-to18.3-m)intervals,dependingontheRCC’spropertiesandpavementthickness.TheprimaryreasonjointsareusedinRCCpavementsistoinitiatecrackloca-tionsortoimproveaestheticsinparkinglots,accessroads,orareasofchannelizedtrafficatspeedsgreaterthan30mph.Figure5-7showsflexuralbeamtesting.
WhenjointsareconstructedinRCC,theyarefewerinnumberandspacedfartherapartthaninconventionalconcretepavements.DowelsortiebarsarenotusedinRCCpavementsforloadtransferthewaytheyareusedinconventionalconcrete;therefore,thedesignerneedstoconsidertheabsenceofloadtransferdevicesinthedesign.Figure5-8showsatypicalRCCdesigncrack.
Whereconcentratedlanetrafficisnotcommon,jointscanbesawedinsquarepatternsusingthetransversespacingof15-to20-ft(4.6-to6.1-m)intervalsforpavementslessthan8in.(200mm)thickand3to4times(infeet)thepavementthickness(ininches)for
Figure 5-7. Flexural beam testing
Figure 5-8. Typical RCC design relies on aggregate interlock at cracks
Subbase
RCC
Subbase
Crack
Aggregate interlock
RCC
Table 5-1. List of design methodologies
PropertyHeavy Industrial Applications
Conventional Roadway Applications
RCC-Pave Computer Software (PCA) U.S. Army Corps of Engineers (USACE) StreetPave (ACPA) Guide for Design of Jointed Concrete Pavements for Streets and Local Roads (ACI 325.12R-02)
Guide for the Design and Construction of Concrete Parking Lots (ACI 330R-08)
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
5-5
ROLLER-COMPACTED CONCRETE
pavements8in.(200mm)thickorgreater.Inareaswithconcentratedlaneloading,thelongitudinalspac-ingshouldbe20ft(6.1m)forpavementslessthan8in.(200mm)thickand2.5times(infeet)thepave-mentthickness(ininches)forpavements8in.(200mm)thickorgreater.
ConstructionAcontinuoussupplyoffreshRCCmaterialtothepavementplacementmachineryisnecessaryforproducingaqualityproduct.Therefore,therateofRCCproductionandtransportationcapabilityshouldmatchthespeedofconstructionatthesite(seeFigure5-9).AnRCCmixingfacilitymusthavetheefficiencytoevenlydispersetherelativelysmallamountofwaterpresentinthestiff,drymix.Consequently,therela-tivelydryRCCrequiresrigorousmixingenergiesandbatchingtimestoprovideauniformmixture,whichcanreducetheplant’smixingcapacitywhencomparedtoconventionalconcrete.
Therightmixingequipmentisvitaltoensuringacontinuousandconsistentqualitysupplytothepaver.TherearetwotypesofmixersforRCC:batchtypeandcontinuousmixers.Mostconcretebatch-typemix-ersconsistofatilt(Figure5-10)orfixeddrumandtransitmixers(drybatchready-mixtrucks)(Figure5-11).Thesemixersaretypicallyusedforsmallerprojectsbecauseofthereducedmixingcapacityandlongermixingtime.ContinuousmixersaretypicallyusedforlargerprojectsbecausetheycanproduceRCCatafasterratethanbatchmixers.Typically,RCCisblendedincontinuoushorizontalshaftmixerssuchaspugmills.High-outputpugmillshavethemixingefficiencyneededtoevenlydispersethecementandrelativelysmallamountofwaterusedinthisdriermix(seeFigure5-12).Roller-compactedconcreteistypi-callydeliveredindumptrucks,buttransitmixerscansometimesbeusedforsmallprojects.
Duringplacement,itisimportantthatthesubbaseand/orsubgradebeuniformlymoist.Ingeneral,RCCpavementsareconstructedusingbothasphaltandconventionalconcretepavementconstructiontech-niques.Roller-compactedconcreteistypicallyplacedwithanasphalt-typepaver.Whenconfiguredwithahigh-densityscreed,rollingcompactionisreduced,thusminimizingvariationsinsurfacetoleranceand
Figure 5-9. RCC delivered to jobsite
Figure 5-11 Ready-mix transit trucks dumping into haul trucks
Figure 5-10. Tilt-drum mixer
improvingsurfacesmoothness.Ahigh-densitypaverisoftenusedtoaccommodatetherelativelylargeamountofmaterialmovingthroughthepaver.Forpavementthicknessesgreaterthan10in.(250mm),multipleliftsareused.
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
5-6
ROLL
ER-C
OMPA
CTED
CON
CRET
E Compactionisthemostimportantstageofconstruc-tion,asitplaysalargeroleindensity,strength,dura-bility,smoothness,andsurfacetexture.SinceRCCmixturesarerelativelydryandstiff(zeroslump),a10-ton(10.2-t)vibratorysteeldrumandrubber-tiredrollersaregenerallyusedduringplacementoperations(seeFigures5-13through5-16fortheRCCplace-mentthroughcuringprocess).Whenusinghigh-densitypavers,highercompactionisaccomplishedprimarilybythepaverandpavingscreeds.Rollingbeginssoonafterplacementandcontinuesuntilthedensityofthepavementmeetsaminimumof98per-centofthemodifiedProctordensity.Finalcompactionisgenerallyachievedwithinonehourofmixing.
PropercuringandhydrationoftheRCCmixtureiscriticaltothelong-termdurabilityofthepavement.BecauseRCChasalowwatercontentandexhibitsnobleedwater,propercuringtechniquesareimportant
Figure 5-12. Mobile RCC pugmill mixing plant and mixing chamber
topreventevaporationandprematuredryingofthesurface.Lackofadequatemoistureforcuringcanresultinscaling,dusting,andravelingofthehardenedsurface.
Formostprojects,awhiteconcretecuringcompoundconformingtoASTMC309(SpecificationforLiquidMembrane-FormingCompoundsforCuringCon-crete)isused.Awatercurecanalsobeimplemented,wherethepavementissprayedorirrigatedtokeepitmoist.However,moisturecuringofRCCrequiresacontinuousapplicationofwaterfortheentirecuringperiod.
Sustainability•Longservicelifewithminimalmaintenance,lowinitialcosts,incorporationofby-productmateri-als,andimprovedsafetymakeRCCasustainableoption.
Figure 5-13. RCC placement
Figure 5-14. Compacting RCC using both vibratory and pneumatic-tired rollers
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
5-7
ROLLER-COMPACTED CONCRETE
Figure 5-15. RCC in-place density measurement
•Roller-compactedconcretesurfacesreflectheat,whichreducestheheatislandeffect.
•Roller-compactedconcretehasahighalbedo,mak-ingforbetternightvisibilityandimprovedsafety.
For More InformationAdaska,W.2006.Roller-Compacted Concrete (RCC).ReportNo.SN2975,PortlandCementAssociation.
Adaska,W.2008.Applications and Design of RCC Pave-ments.PortlandCementAssociationSlidepresenta-tion,http://www.secement.org/rcc.htm.
AmericanConcreteInstitute.1999.State-of-the-Art Report on Roller-Compacted Concrete Pavements. ReportNo.ACI325.10R-99,FarmingtonHills,Michigan.
Gauthier,P.andJ.Marchand.2005.Design and Construction of Roller Compacted Concrete Pavements in Quebec.CementAssociationofCanada,Ottawa,Canada.
Harrington,D.,F.Abdo,W.Adaska,andC.Hazaree.2010.Guide for Roller-Compacted Concrete Pavements.SN298,PortlandCementAssociationandNationalConcretePavementTechnologyCenter,August.
Piggott,R.1999.Roller-Compacted Concrete Pave-ments—A Study of the Long Term Performance.RP366.Skokie,Illinois:PortlandCementAssociation.
PortlandCementAssociation.2010.Integrated Pav-ing Solutions—Roller-Compacted Concrete.http://www.integratedpavingsolutions.org/RCC.html.Figure 5-16. Curing RCC
•TheabilitytousesomefinesallowsRCCtoincorpo-ratematerialthatwouldotherwisenotbeacceptableforconventionalconcrete.
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
6-1
Cement-Treated Base
Objectives•Provideastrong,uniformbase/subbaseforcur-rentandfutureloadingconditionsusingin-placeorlocallyavailablemarginalsoilsandgranularmaterial.
•Reducestressesonthesubgrade.
•Stabilizeavarietyofsoilswithasinglestabilizer.
•Reduceruttinganddeflectionsinaflexiblepave-mentsurface.
•Improvethestructuralcapacityoftheexistingsoil.
•Provideasustainableoption.
Solution•Acement-treatedbase(CTB)usingexistingsoilsorlocallyavailableborrowmaterial.
Benefits•Astifferbasereducesdeflectionsduetotrafficloads,therebyextendingpavementlife.
•Subgradefailures,pumping,rutting,jointfaulting,androadroughnessarereduced.
•Basethicknessisreducedcomparedtounboundgranularbasethicknesses.
•Marginalaggregates,includingrecycledmaterials,canbeused,thusreducingtheneedforvirgin,high-qualityaggregates.
Considerations•ThepotentialforreflectivecrackingandincreasedfrictionbetweentheCTBandsurfaceneedtobeconsidered.
Typical ApplicationsCement-treatedbaseprovidesadurable,long-lastingbaseinalltypesofclimates.Itisoftenusedinhigh-way,streetandlocalroad,shoulder,commercial,andheavyindustrialapplications.Cement-treatedbaseisalsocommoninairfieldapplications,particularlylargeairportrunwayapplications.TheFederalAviationAdministrationrequiresCTBforrunwaysthatexperi-encehighvolumesofheavyaircrafttraffic.
Highways
Commercial / Lightweight
Airfields
Heavy Industrial
Streets & Local Roads
Shoulders
DescriptionCement-treatedbaseconsistsofnativesoils,gravels,ormanufacturedaggregatesblendedwithmeasuredamountsofportlandcementandwaterthathardensaftercuringtoformadurablepavingmaterial.Theversatilityofcementiscriticaltothesuccessofthestabilizationoperation,becausesiteconditionscaneasilychangeduringaprojectandthestabilizerneeds
6 Guide to Cement-Based Integrated Pavement Solutions
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
CEM
ENT-
TREA
TED
BASE
6-2
toadapttothechangingconditions.Cementisknownasa“universalstabilizer”becauseitworkswelloverawiderangeofdifferentsoiltypes.
PavementswithCTBwillbemuchstrongerthananunstabilized,granularbase.ThicknessesforCTBarelessthanthoserequiredforunstabilizedgranularbasescarryingthesametraffic.Cement-treatedbasecandistributeloadsoverawiderarea(seeFigure6-1),reducingthestressesonthesubgrade.Ithasahighload-carryingcapacity,doesnotconsolidatefurtherunderload,reducesruttinginHMApavements,andisresistanttofreeze-thawdeterioration.
Inapavementsystem,CTBisgenerallyconstructedoverthesubgrade(seeFigure6-2).AnHMAorcon-cretewearingsurfaceisplacedontheCTBtocom-pletethepavementstructure.Thedesignofaconcretesurfacelayermusttakeintoaccountincreasedfric-tionvaluesbetweenthelayers.Insomeinstances,aninterlayerisusedtoreducerestraintstressesandthepotentialforreflectivecracking.SeeFigure6-3foracompletedCTBsectionofroadway.
MaterialsCement-treatedbaseisamixtureofaggregatemate-rial,portlandcement,andwater.Themixtureshouldbedesignedbasedonstrengthandresistancetofreeze-thawandwetenvironments.
TheaggregatematerialusedinaCTBmixturecanbeavarietyofmaterialsorcombinationsthereof.Thesematerialsincludeexistingorborrowedstone,gravel,sand,silt,andcaliche.Recycledconcreteaggregates(RCA)andrecycledasphaltpavementcanalsobeincorporated.Awell-gradedsandyandgravellyaggre-gatematerialblendtypicallyrequirestheleastamountofcementforadequatehardening,whereasanaggre-gatematerialthatisclassifiedaseitherapoorlygradedsandymaterialdeficientinfinesorasiltyand/orclayeymaterialbothrequiremorecementforharden-ing.ManystatespecificationsrequirethataggregatesusedinCTBmeettypicalgradationandAtterberglimitrequirements.
Anyportlandcementtypecanbeused,butTypesIandIIarethemostcommon.Cementcontentdependsonthetypeofaggregatematerialused;
Figure 6-1. Load distribution of CTB compared to unstabilized granular base
Figure 6-2. Typical pavement cross-sections showing CTB layers
Prepared Subgrade
Concrete Surface
CTB Subbase
Prepared Subgrade
Concrete Surface
CTB Subbase
Prepared Subgrade
Concrete Surface
CTB Subbase
Prepared Subgrade
HMA Surface
CTB Subbase
Prepared Subgrade
HMA Surface
CTB Base
Friction Reducing Medium
Figure 6-3. Completed CTB for new pavement construction in Oklahoma
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s CEM
ENT-TREATED BASE
6-3
however,itusuallyrangesfrom3to8percentformostapplications.Ingeneral,acementcontentthatwillprovideaseven-dayunconfinedcompressivestrengthofbetween300and400psi(2.1and2.8MPa)issatisfactoryformostCTBapplications.
TheengineeringpropertiesoftheCTBmixturearedependentonindividualconstituentmaterialsthatmakeupthemixture(i.e.,aggregatematerialandcementtype),curingconditions,andage.Agemakesadifferencebecausecementwillcontinuetohydrateovertime,whichwillincreasestrength.Generalrangesforcompressivestrength,modulusofrupture,modulusofelasticity,andPoisson’sratioarelistedinTable6-1.
DesignACTBservesasanintegralcomponentofthepave-mentsystem.Itneedstobestrongenoughtowith-standthestressandfatiguecausedbytheenviron-mentinwhichitisconstructedandtheloadsunderwhichitmustperformoverananticipatedlifetime.SomecriticaldesigninputsforcalculatingCTBthick-nessincludetheestimatedtrafficloadingduringthedesignlife,subgradestrength,andCTBstrength.
ThemostcommonapproachfordeterminingCTBthicknessistofollowtheAmericanAssociationofStateHighwayandTransportationOfficials(AASHTO)DesignGuide(1993)procedureforpavementdesign,whichusesastructurallayercoefficienttomodelbasematerial.AmajoreffortiscurrentlyunderwaytoregionallycalibrateandshifttothenewAAS-HTOMechanistic-EmpiricalPavementDesignGuide(M-EPDG).AnotherapproachistousethePortlandCementAssociationproceduregiveninthePCApub-lication“Thickness Design for Soil-Cement Pavements.”
Theabilityofapavementbasetocarryloadsdependsonthestrengthofthebasematerialandthethicknessofthebaselayer.Althoughathin,strongbasecantheoreticallycarrythesameloadasathick,weakerbase,thethicker,weakerbaseisusuallypreferred.Thisisbecausethethin,strongerbaseismorebrittleandmorelikelytocrack,resultinginpotentialreflec-tivecrackinginthesurfacepavement.Onmajorhighways,typicalthicknessesrangefrom6to12in.(150to300mm).
ConstructionConstructionincludesinitialpreparation,process-ing,compaction,finishing,andcuring.ThefollowingparagraphsgiveabriefsummaryofCTBconstruction.
Initialpreparationincludesthefollowingsteps:(1)Shapeareatocrownandgrade;(2)Correctunstablesubgradeareas;(3)Ifnecessary,scarify,pulverize,andprewetthesoil(ingeneral,notmuchpulverizationisrequiredforCTB);and(4)Reshapecrownandgrade.
Processingiscontinuousandaccomplishedinoneday.TherearetwomethodsforprocessingCTB:mixed-in-placeorcentral-plant-mixed.
ForCTBmixed-in-place,cementisplaceddryontothesurfaceofthein-placeaggregateusingamechani-calspreaderattachedtoadumptruckorbulkcementtruck.Thecementmayalsobeplacedonthesurfaceinslurryform.Thein-placeaggregatecanbeeithertheexistingmaterialorborrowedmaterial.Asingle-shaftpulvermixercombinestheaggregateandcement.Ifnecessary,waterisappliedonthesurfaceordirectlyintothemixingchamber.Thesingle-shaftmixerthenmixesthecement,water,andaggregateuntilauniform,thoroughlymixedmaterialisachieved(seeFigure6-4,Figure6-5,andFigure6-6).
Thecentral-plant-mixedmethodrequiresmixingcement,aggregatematerial,andwaterinastationaryplant.Mixingatacentralplantisgenerallydonebypugmillsorrotary-drummixers.Rotary-drummix-ersworkwellformixingcoarse,nonplasticaggregatematerial.High-speedrotaryshaftpugmillsworkwellforcoarseaggregatematerialandnonplasticfine-grainedmateriallikesandsandsilts.Forplantswithrotary-drumorbatch-typepugmills,materialis
Table 6-1. Typical CTB properties
Property 7-Day Value
Compressive Strength300 – 800 psi (2.1 – 5.5 MPa)
Modulus of Rupture (Flexural Strength)
100 – 200 psi (0.7 – 1.4 MPa)
Modulus of Elasticity600,000 – 1,000.000 psi (4,100 – 6,900 MPa)
Poisson’s Ratio 0.15
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
CEM
ENT-
TREA
TED
BASE
6-4
batchedbyweight,mixed,dumpedintohaultrucks,anddeliveredtothesite.Atplantswithcontinuous-flow-typepugmills,themostcommontypeofcentralplant,materialsareindividuallymeteredbyweightorvolumeandfedintothemixerbyanaugerscrew,belt,orrotary-vanefeeder.Aftermixingattheplant,theCTBmaterialisdumpedintotrucks,hauledtothesite,andspreadevenlyoverthearea(seeFigure6-7).AnaggregatespreaderiscommonlyusedtoplacetheCTBmixtureoverthesubgrade.
TheCTBmixtureshouldbecompactedatoptimummoisturetomaximumdrydensityasdeterminedbypreliminarylaboratorytestingperAASHTOT134orASTMD558,orasdefinedbyprojectspecifications.Vibratory-steelrollers,sheepsfootrollers,orpneu-matic-tirerollersaretypicallyused,dependingonthetypeofaggregatematerialusedintheCTBmixture.
Thefinishingoperationsfollowimmediatelyafteradequatecompactionisobtained.Thegoalofthefin-ishingprocessistoproduceahigh-qualitysurfacethathasadequatecompactionandisvoidofanysoftareasorsurfacecompactionplanes.ThestepsforfinishingCTBalsodependonthetypeofaggregatematerialusedintheCTBmixture.Ingeneral,finishingaCTBmixtureincludesacombinationofshaping,scratchingthesurface,applyingabroomdrag,lightlyapplyingwater,androllingwithapneumaticsteelroller.
Afterfinishing,theCTBmustbeadequatelycured,allowingcementtohydrateandthecement-aggregate
Figure 6-4. Spreading dry cement on grade prior to mixing
Figure 6-5. Applying cement slurry on grade prior to mixing (cement slurry is applied the same way for FDR and CMS applications)
Figure 6-6. Constructing CTB using mixed-in-place method
Figure 6-7. Placement of plant-mixed CTB on prepared subgrade
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s CEM
ENT-TREATED BASE
6-5
mixturetoharden.Thenewlyconstructedbaseshouldbekeptcontinuouslymoist(bylightlywateringormisting)fora3-to7-dayperiod,oramoisture-retain-ingcoverorcuringcompoundcanbeplacedovertheCTBsoonaftercompletion.
Sustainability•In-situorlocalmarginalaggregatescanbeusedinCTB.Thiswillminimizetheneedtohaulincostlyselectgranularaggregates.
•Cement-treatedbasemayrequiretheuseofindus-trialby-productssuchasflyash.
•RecycledasphaltpavementmixedwithcementmakesanexcellentCTB.
•Cement-treatedbaseprovidesastrongerbasethanunboundgranularmaterial;therefore,forthesameload-carryingcapacity,lessmaterialisrequired.
•Haulinglessmaterialreducesthenumberoftrucksandpossibledamagetosurroundingroads,result-inginfuelsavings,loweremissions,andprematurefutureroadwaymaintenance.
For More InformationAmericanAssociationofStateHighwayandTranspor-tationOfficials(AASHTO).1993.American Association
of State Highway and Transportation Officials Design Guide.
AmericanConcreteInstitute.2009.State-of-the-Art Report on Soil CementReportNo.ACI-230.1R,Farm-ington,Hills,Michigan:AmericanConcreteInstitute.
AmericanConcretePavementAssociation.2007.Sub-grades and Subbases for Concrete Pavements.EB204P.
George,K.P.2002.Minimizing Cracking in Cement-Treated Materials for Improved PerformanceRD123.01.Skokie,Illinois:PortlandCementAssociation.
Guthrie,W.S.,S.Sebesta,andT.Scullion.2002.Selecting Optimum Cement Contents for Stabilizing Aggre-gate Base Material.TechnicalReport7-4920-2,TexasTransportationInstitute.
HalstedG.E.,D.R.Luhr,andW.S.Adaska.2006.Guide to Cement-Treated Base.EB236.Skokie,Illinois:PortlandCementAssociation.
PortlandCementAssociation.2001.Thickness Design of Soil-Cement Pavements.EB068.Skokie,Illinois:PortlandCementAssociation.
PortlandCementAssociation.2010.Integrated Paving Solutions—Cement-Treated Base.http://www.integrated-pavingsolutions.org/cement-treatedbase.html.
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
7-1
Full-Depth Reclamation with Cement (FDR)
Objectives•Provideastrong,uniformbase/subbaseforcurrentandfutureloadingconditionsusingexistingfailedasphaltsurfaceandbasematerial.
•Maintainexistinggradewithminimummaterialremovaloraddition.
•Reduceortotallyeliminatetheneedforvirginaggregates.
•Reducestressesonthesubgrade.
•Reduceruttinganddeflectionsinaflexiblepave-mentsurface.
•Improvethestructuralcapacityofstabilizedbaseoverunstabilizedbasematerial.
•Providepavementreconstructionmethodthatisfastandminimizestrafficdisruption.
•Provideasustainableoption.
Solution•Full-depthreclamationwithcementtorecycleandreusetheexistingpavementmaterialecycleandreusetheexistingpavementmaterial.
Benefits•Theperformanceofthebaselayerisimprovedoveranunboundgranularbase.
•Little,ifany,materialishauledofforontothesite,resultinginlesstrucktraffic,loweremissions,andlessdamagetolocalroads.Workcanbecompletedquicklycomparedtoremovalandreplacementtechniques.
•Full-depthreclamationprocessiseconomicalcomparedtoremovalandreplacementandthickoverlays.
Considerations•ThepotentialforreflectivecrackingandincreasedfrictionbetweentheFDRandsurfacepavementneedstobeconsidered.
•Undergroundutilitiesneedtobeconsideredduringthedesignandconstructionphase.
Typical ApplicationsRecycledmaterialsandrecyclingtechniquesareusedinhighway,streetandlocalroad,commercial/lightweightindustrial,airfield,andheavyindustrialapplications.
Description
Highways
Commercial / Lightweight
Airfields
Heavy Industrial
Streets & Local Roads
Full-depthreclamationwithcementisatechniqueinwhichanexistingHMApavementandbasematerialisreclaimed(pulverizedasnecessary),combinedwithportlandcement,andthenrecompactedtocreateanewandimprovedbase.TheFDRbaseisthentoppedwithanewHMAorconcretesurfacelayer.
7 Guide to Cement-Based Integrated Pavement Solutions
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
FULL
-DEP
TH R
ECLA
MAT
ION
WIT
H CE
MEN
T (F
DR)
7-2
Full-depthreclamationisappropriateunderthefol-lowingconditions:
•Thepavementisdamagedandcannotberehabili-tatedwithsimpleresurfacingmethods.
•Theexistingpavementdistressindicatesthataproblemlikelyexistsinthesurface,base,and/orsubgrade.
•Theexistingpavementdistresswouldotherwiserequirefull-depthpatchingovermorethan15–20percentofthesurfacearea.
•Thepavementstructureisinadequateforthecur-rentorfuturetraffic.
MaterialsMaterialsusedforFDRincludetheexistingHMAsurfacethathasbeenpulverizedandblendedwiththeunderlyingbase,subbase,and/orsubgrade,cement,andwater.Laboratorytestingandtrialmixesallowselectingthebestproportionsofcementforthejob.Theamountofwaterandcementrequiredinthemixwilldependupontheproject-specifiedstrengthandgradationofthefinalblendobtainedfrompulverizingtheHMAduringconstructionandmixingitwiththebasematerial.Typicalspecificationsforpulverizingcallforaminimumof100percentpassingthe3-in.(75-mm)sieve,95percentpassingthe2-in.(50-mm)sieve,and55percentpassingtheNo.4(4.75-mm)sieve.Ingeneral,acementcontentthatprovidesaseven-dayunconfinedcompressivestrengthbetween300to400psi(2.1to2.8MPa)issatisfactoryformostFDRapplications.
DesignFull-depthreclamationdesignisaprocessthatinvolves(1)determiningthetypeofexistingpavementlayersandtheirrespectivethicknesses,and(2)identi-fyingwhichmaterialwillbecombinedwithcementinordertocreateastablebaseforanewpavementstruc-ture.ThethicknessdesignissimilartoaCTBandiscalculatedbasedonstrengthofthematerial,strengthandstiffnesscharacterizationsofadditionallayers,anticipatedloads,andperformancerequirements(i.e.,life,serviceability,reliability).TheAASHTOprocedureforpavementdesignorPCAthicknessdesignproce-
durecanbeused.TypicalthicknessvaluesforFDRrangefrom6to12in.(150to300mm).
ConstructionFull-depthreclamationrequiresareclaimermixer,grader,cementspreader,watertruck,androller.Areclaimermachinetypicallymakesaninitialpassovertheexistingflexiblepavement,pulverizingtheHMAsurfaceandblendingitwiththebaseand/orsubgradematerial(seeFigure7-1andFigure7-2).Watermaybeaddedduringthismixingstagetobringthemate-rialuptooptimummoisturecontent.Thematerialisthengradedaccordingly.Next,cementisspreadeitherdryorinslurryforminacontrolledmannerontothesurface(seeFigure7-3andFigure7-4).Thereclaimerthenmixesthecementintothepulverizedmaterial.
Figure 7-1. Schematic of the mixing chamber of a reclaimer machine
Figure 7-2 Reclaimer pulverizing existing asphalt pavement and base material
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s FULL-DEPTH RECLAM
ATION WITH CEM
ENT (FDR)
7-3
Figure 7-6. Equipment for compaction and finishing
Figure 7-3. Dry cement placed on pulverized material
Figure 7-4. Applying cement slurry on grade prior to mixing (cement slurry is applied the same way for CTB applications)
Figure 7-5. Mixing the cement into the pulverized material
Mixingcontinuesuntilthematerialisthoroughlymixed.Thisisfollowedbycompaction,finalgrading,curing,andsurfacing.Smooth-wheeledrollersareusedforcompaction.TheFDRshouldbecuredforfromthreetosevendays.Surfacetreatmentsincludechipseals,HMA,orconcrete.Thewholeprocesscanbeperformedundertraffic(seeFigure7-5).Figure7-6showstheequipmentusedforcompactionandfinishing.
Sustainability•Existingmaterialsarereused,reducingtheexploita-tionofvirginmaterial.
•Damageisreducedtosurroundingroadsfromhaul-ingexistingbasematerialsoutandbringingvirginmaterialsin.
•Costsrelatedtotheprocessing,purchasing,andtransportationofvirginaggregatesareminimized.
•Trucktrafficisreduced,resultinginfuelsavingsandloweremissions.
For More InformationAsphaltRecycling&ReclaimingAssociation.2001.Basic Asphalt Recycling Manual.Annapolis,Maryland:AsphaltRecycling&ReclaimingAssociation.
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
FULL
-DEP
TH R
ECLA
MAT
ION
WIT
H CE
MEN
T (F
DR)
7-4
Brown,Ashley,andVannoy.2006.Cementstabiliza-tionofaggregatebasematerialblendedwithreclaimedasphaltpavement.Master’sthesis,DepartmentofCivilandEnvironmentalEngineering,BrighamYoungUni-versity,August.
EuropeanConcretePavementAssociation.2010.EUPAVE—In Situ Pavement Recycling.www.eupave.eu/documents/activity-areas/in-situ-pavement-recycling.xml?lang=en.
Luhr,D.R.,W.S.Adaska,andG.E.Halsted.2005.Guide to Full-Depth Reclamation (FDR) with Cement. EB234,PortlandCementAssociation.
PortlandCementAssociation.2001.Thickness Design for Soil-Cement Pavements.EB068.Skokie,Illinois:PortlandCementAssociation.
PortlandCementAssociation.2010.Integrated Paving Solutions—Full-Depth Reclamation with Cement.http://www.integratedpavingsolutions.org/FDR.html.
Syed,I.M.2007.Full-Depth Reclamation with Portland Cement: A Study of Long-Term Performance. SR016.Skokie,Illinois:PortlandCementAssociation.
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
8-1
Cement-Modified Soils (CMS)
Objectives•Reducetheplasticityandhigh-volumechangechar-acteristicsofclaysoilsduetomoisturevariations.
•Improvestabilityofapoorlygradedsandysoil.Improvethepropertiesofasandysoilcontainingahigh-plasticityclay.
•Provideamethodtodryoutawetsubgrade.
•Provideafirmconstructionplatformtoworkon.
•Provideasustainableoption.
Solution•Addasmallamountofcementtothesoiltocreateacement-modifiedsoil.
Benefits•Cement-modifiedsoilsprovideaweather-resistantworkplatformforconstructionoperations.
•Fatiguefailurescausedbyrepeatedhighdeflectionsarecontrolled.
•Thereisareductioninmoisturesensitivityandsub-gradeseasonalloadrestrictions.
•Nomellowingperiodisneededasrequiredbyotherstabilizingagents.
Considerations•Cement-modifiedsoilsarenotintendedtowith-standthesameCTBdurabilityandcompressivestrengthrequirements.
Typical ApplicationsCement-modifiedgranularsoilscanbeusedasatreatedsubgradeandworkingplatformbeneathabaseorsubbase.
Highways
Commercial / Lightweight
Airfields
Heavy Industrial
Streets & Local Roads
Shoulders
DescriptionCement-modifiedsoilsaresoilsand/ormanufacturedaggregatesmixedwithasmallproportionofportlandcement.Bycombiningsmallamountsofcementwithsoils,plasticityisreduced,volumetricchangesduetomoisturecontentareminimized,bearingstrengthisincreased,andstabilityisimproved.Asaresult,aweather-resistantworkplatformforconstructionoper-ationsandastronger,permanentpavementlayerforenhancedsupportandcapacitycanbeconstructed.
8 Guide to Cement-Based Integrated Pavement Solutions
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
CEM
ENT-
MOD
IFIE
D SO
ILS
(CM
S)
8-2
Cement-modifiedsoilsarenormallyusedtoimprovematerialpropertiesinthesubgrade.Theycanelimi-natetheneedforextensiveremovalandreplacementofexistingsoils,savingconsiderabletimeandmoney.ThemostcommonapplicationofCMSisasanoptionforsubgradematerialwhenexistingoravailablesoilsareofpoorquality(seeFigure8-1).
TheprimarydifferencebetweenCMSandCTBisthatCTBtypicallycontainsmorecementandisrequiredtomeetcertainstrengthvaluesperspecificationsandtoserveasadurable,freeze-thawresistantmaterial.Cement-modifiedsoilstypicallydonothavetomeetthesamerequirementsforstrengthanddurabil-ity;instead,smallamountsofcementareaddedtomitigateexpansionduetomoisturevariationsandimprovecohesioncausedbypoorsoils.Anadditionalbenefitisanimprovementinstrengthandstiffness.
Figure 8-1. Typical cross-section with CMS
DesignThedesignofaCMSlayerfocusesoncreatingawork-ingplatformfortheconstructionofbase/subbaseand,subsequently,thesurfacelayer.TheCMSlayer,however,doesnotcontributeappreciablytothestruc-turalcapacityofthepavement.Accordingtomoststateand/orjob-specificspecifications,aCMSlayerisdesignedtomeetcertainAtterberglimitrequirementsasdeterminedbyproperlaboratorytestingmethods.Cement-modifiedsoilsaretypicallynotdesignedtomeetacompressivestrengthrequirement,butratherdesignedtomeetreducedplasticityrequirementsandincreasedCBRvalues.Thedesignwillvary,dependingonexistingsoilproperties.Acommonthicknessof6in.(150mm)hasbeenshowntoprovideanadequateworkingplatformforconstructionofbaseorsubbaselayers.
ConstructionCement-modifiedsoilsareproducedinplaceusingexistingsoils.Cement-modifiedsoilsconstructionconsistsofmixingthecementintothesoilusingmixed-in-placemethods.However,becauseofthecohesivenessofthesoilsomeadditionaleffortmayberequiredforthepulverizationandmixingopera-tions.Wetsoilsmayrequiremultiplemixingpasses.Ifthesoilisdry,pre-wettingandallowingthewatertosoakinmayfacilitatepulverization(seeFigure8-2).IncontrasttonormalCTBconstruction,thetimelimitbetweenmixingandcompactingisnotasstringent,Materials
Cement-modifiedsoilsareprincipallyusedtomodifyfine-grainedsoilssuchassiltsandclaysandgranu-larsoilshavingahighplasticityand/orfinecontent.Cementcontentforeachistypicallybasedoniden-tifyingtheappropriateamountnecessarytomeetspecifications.
MostCMSinvolveshighplasticitysoilssuchasclays.Specificationswilloftenrequireenoughcementcontenttoreducetheplasticityindex(PI)towithinarangeof12to15.Typically,acementcontentof3to4percentwillreducethePIsufficientlyandincreasetheCaliforniabearingratio(CBR)andresistanceval-ues.Thecement-modifiedsoilshouldprovideafirmfoundationforcompactionofthebase/subbaselayeraboveit.
Figure 8-2. Cement slurry added to subgrade material (cement slurry is applied the same way for CTB and FDR applications)
Base/
-
Untreated Subgrade
Pavement Surface
Subbase
Cement- Modified Soil
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s CEM
ENT-MODIFIED SOILS (CM
S)
8-3
althoughalloperations,includingcompaction,shouldbecompletedinthesameday.
Ingeneral,in-placemixingandconstructionsequencefollowsthesesteps:
•Forinitialpreparation,shapetheareatocrownandgradeandcorrectanysoftorunsuitableareas.
•Ifnecessary,prewetdrysoilstoaidpulverizationordrybackwetsoilsbyaerationwithdischarroworrotarymixerwithitshoodopen.
•Distributecementindryformwithmechanicalspreaderorinslurryformfromdistributortruck.
•Mixwithpulvermixer,addingwaterifnecessary,untilahomogeneous,friablemixtureisobtainedthatwillmeetthespecifiedpulverizationrequire-ments(seeFigure8-3).
•Compactwithtamping(sheepsfoot)roller(seeFigure8-4).
•Completesurfacecompactionwithasteeldrum,pneumatictire,orotherappropriatetypeofroller.
•Withgrader,shapeareatofinalcrownandgrade.
•Sealsurfacewithpneumatic-tireroller.
Unlikecement-treatedbases,CMSisoftennotcured.However,curingwithalightwatersprayorbitumi-nouscoatingwillprovidethemaximumbenefitfromthecement.
Sustainability•CMSreduceswastebyallowingtheuseofexistingmaterial.
•In-situmarginalsubgradesoilscanbeimproved,minimizingtheneedtohaulincostlyselectgranularaggregates.
•CMSprovidesastrongermorestablesubgrade,whichmayreducethequantityofbasematerialneeded.
For More InformationBhattacharja,S.andJ.Bhatty.2003.Comparative Performance of Portland Cement and Lime Stabilization of Moderate to High Plasticity Clay Soils.RD125.Skokie,Illinois:PortlandCementAssociation.
Halsted,G.E.,W.S.Adaska,andW.T.McConnell.2008.Guide to Cement-Modified Soil (CMS).EB242.SkokieIllinois:PortlandCementAssociation.
PortlandCementAssociation.2010.Integrated Paving Solutions—Cement-Modified Soil.http://www.integrat-edpavingsolutions.org/CMS.html.
Scullion,T.,S.Sebesta,J.Harris,andI.Syed.2005.Evaluating the Performance of Soil-Cement and Cement-Modified Soil for Pavements: A Laboratory Investigation.RD120.Skokie,Illinois:PortlandCementAssociation.
Figure 8-3. Pulvermizer used for in-place mixing of CMS
Figure 8-4. Sheepsfoot roller used for compaction
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
9-1
Recycled Concrete Aggregates
Objectives•Recycleexcavatedconcretepavement.
•Minimizeconstructioncost.
•Reducedependenceongoodqualityvirginaggre-gates,whichmaybehardtofindorexpensivetobringin.
•Provideasustainableoption.
Solution•Useoldconcreteasaggregatesinnewpavementlayers.
Benefits•Recycledconcreteaggregates(RCA)areversatilebecausetheycanbeusedinanypavementlayer.
•Materialcostsarereduced.
•Constructiontimecanbeexpeditedwithon-siterecyclingplants.
•PavementsufferingfromASRorD-crackingcanberecycledinsteadofdiscarded.
•Theneedforoldconcretedisposalisreduced.
Considerations•IfASRorD-crackingexistsinrecycledpavementmaterial,specialattentionmustbegiventomixturedesign.
•RecycledconcreteaggregatesinHMAmayincreasebindercontentrequirements.
•Concretemixturedesignswillhavetobeadjustedforstrength.
•Additionalqualitycontrolmeasuresmaybeneces-sarytoensureconcreteworkability.
Typical ApplicationsRecycledconcreteaggregatesareusedinhighway,streetandlocalroad,shoulder,airfield,commer-cial/lightweightindustrial,andheavyindustrialapplications.
Highways
Commercial / Lightweight
Airfields
Heavy Industrial
Streets & Local Roads
Shoulders
DescriptionRecycledconcreteaggregatesareaggregatesproducedfromtherecyclingofexistingconcrete.Existingcon-creteisremoved,processedintoappropriateaggregatesizes,andreusedinvariouspavementapplications.ThebenefitsofusingRCAinpavementsincludereducedmaterialcosts,minimizeduseofdeplet-ingvirginaggregatesources,anddecreasedlandfillcontent.
Recycledconcreteaggregatesareprimarilyusedinbasesandsubbases.Accordingtoa2008FederalHighwayAdministrationnationalreview,84percentofstatesarerecyclingconcreteaggregate.Whilemost
9 Guide to Cement-Based Integrated Pavement Solutions
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
RECY
CLED
CON
CRET
E AG
GREG
ATES
9-2
statesuseRCAasabasematerial,22percentuseRCAasaggregatefornewconcretepavements.
Recycledconcreteaggregatesareidealforthebottomliftofatwo-liftpavingmixturedesign.Two-liftpav-ingisaconstructiontechniquethatinvolvesplac-ingaconcretesurfacelayerintwoconsecutivelifts.Theprocessissometimesreferredtoas“wet-on-wet”becausethetoplayerisplacedimmediatelyafterthebottomlayer,beforethebottomlayerhardens.Theadvantagetothiskindofconstructionisthatgoodqualityaggregatesareonlyrequiredinthetoplift,whereasaggregatessuchasRCAcanthenbeusedforthelowerlift.
ThequalityofRCAisverydependentonthequal-ityofthematerialfromwhichitwasprocessed.Oldconcretepavementisbrokendownin-place,removed,andcrushedtoproduceRCA.Recycledconcreteaggregatesproducedfromallbutthepoorestqualityoriginalconcretecanbeexpectedtopassthesametestsrequiredofvirginconventionalaggregates.
MaterialsRecycledconcreteaggregates(seeFigure9-1)pro-ducedfromconcretepavementrecyclingcontainsboththeoriginalaggregatesandhydratedcementpaste.Recycledconcreteaggregatescanbeprocessedtoexhibitpropertiesthatmeetthesamegradationrequirementsasvirginaggregatesusedforsimi-larapplications.Recycledconcreteaggregatesmayimproveearlystrengthpropertiesinsomeapplica-tionsbecauseofthecontinuedhydrationofexposed
cementparticlesintheRCA.TherearesomematerialcharacteristicsspecifictoRCAinsomeapplicationsthatshouldbeunderstoodandaccountedforineitherdesignorconstruction.
ConcretepavementscontainingRCAcanresultinincreasedporosityandabsorption,highercoefficientofthermalexpansionandshrinkage,lowerstrengths,andreducedspecificgravitywhencomparedtotheuseofonlyvirginaggregates.Thechloridecontentofrecycledaggregatesshouldbeinvestigatedifthemate-rialwillbeusedinreinforcedconcrete.Toachievethesameworkability,slump,andw/cmratioasinconven-tionalconcrete,mixturesincorporatingRCAtypicallyrequirehigherpastecontentand/orgreateramountsofwaterreducer.InanHMAsurfaceandasphalt-stabilizedbaseand/orsubbaselayers,RCAcanhelptoimprovestabilityandfrictionbuttypicallyrequiresanincreaseinbindercontent.
AsanaggregateinCTBlayers,RCArequiresnospecialconsiderationandperformssimilartovirginaggregate.Recycledconcreteaggregatescanbemoresusceptibletoabrasion.Therefore,whenusedasanaggregateinunboundbaseand/orsubbaselayers,theconstructionprocessshouldbeadjustedasneededforproperhandling.
PavementssufferingfromASRorD-crackingcanberecycled,butspecialattentionmustbegiventoconcretemixturedesign.SupplementarycementitiousmaterialsthatmitigateASRmustbeincorporatedintoconcretemixturedesignswhenASR-distressedRCAisused.D-crackedRCAmustbeprocessedtoproperaggregatesizesforthepreventionoffurtherD-crack-ingdistress.
Whendesignedandconstructedappropriately,pave-mentsbuiltwithrecycledmaterialscanbedurable.Thekeyistodesignamixturewithpropermaterialproportionsfortheintendedapplication.
DesignItiscommontocombineRCAwithvirginaggregateinmixturesfornewconcreteorHMAsurfacelayers.Inconcretesurfaceapplications,upto30percentofnaturalcrushedcoarseaggregatecanbereplacedwithcoarseRCAwithoutsignificantlyaffectinganyoftheFigure 9-1. Recycled concrete aggregates
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s RECYCLED CONCRETE AGGREGATES
9-3
mechanicalpropertiesoftheconcrete.Asreplacementamountsincrease,dryingshrinkageandcreepwillincreaseandtensilestrengthandmodulusofelastic-itywilldecrease;however,compressivestrengthandfreeze-thawresistancearenotsignificantlyaffected.SpecialcareisnecessarywhenusingfineRCAinconcretemixtures.Onlyamaximumof10to20percentfineRCAhasbeenshowntobebeneficial.RecycledconcreteaggregatescontentinHMAsurfacelayersisnotlimitedifthemixturedesignpropertiesadheretoallspecifiedperformancerequirements(e.g.,abrasion).
Recycledconcreteaggregatescontentforbaseandsubbaseapplicationsisnotasstrict.Ingeneral,awell-gradedRCAcanresultinaverystablesubbase,andRCAcontentinCTBshouldbesuchthatitstillmeetsallperformancerequirements.
ConstructionThestepsrequiredfortheRCAproductionprocessarecrushingandremovingexistingpavementmaterial,removinganyreinforcementand/orothercontami-nants,andprocessingthereclaimedmaterialdowntoappropriateaggregatesizes.Ingeneral,equipmentusedforRCAproductionincludesthefollowing:
•Hand-operatedorvehicle-mountedcrushingdevices(e.g.,hand-heldtools,drophammers/blades,impactbreakers/hammers,etc.)(seeFigure9-2)
•Abackhoeorbulldozerwitharhinohornattach-mentforlooseningthecrushedmaterialfromthelayerbeneathitandanyreinforcement
•Front-endloadersordumptrucksfortransporting(seeFigure9-3)
•Arecyclingplantthatcanbestationary,portable,ormobile
Figure9-4showsexistingconcreterecycledin-placeandreusedforbasematerial.
Whenusedinnewconcrete,itisrecommendedthatRCAbeprewettedandclosetoasaturatedsurfacedry
Figure 9-2. Example of equipment used to break existing concrete
Figure 9-3. Broken concrete pavement is removed for recycling
Figure 9-4. Existing concrete recycled in-place and reused for base material on the Tri-State Tollway in Illinois
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
RECY
CLED
CON
CRET
E AG
GREG
ATES
9-4
conditionbeforebatching.Additionalqualitycontrolmeasuresmaybenecessarytoensuregoodmoisturecontrol.ConcreteandHMAmixturescontainingRCAcanbetransported,placed,andcompactedinthesamemannerasconventionalmixtures.
TheconstructionofCTBandunboundbase/subbaselayersfollowstypicalstandardprocedures.IfRCAisusedinwhatisintendedtobeadrainablebaseorsubbaselayer,itisadvisedthathandling(i.e.,shap-ing)thematerialiskepttoaminimum;thetendencyforfineparticulatestobreakofffromthesurfaceoftheRCAisincreased,otherwise.
Inadrainablelayer,increasedfinesdecreasetheabil-ityforwatertoescapeoutofthelayer.Itisalsorec-ommendedthatRCAbaseandsubbasedrainagelayersaredaylightedforthisreason.
Recycledconcreteaggregatesusedinunboundbaseand/orsubbaselayerscancontainverysmallpercent-agesofcontaminants(suchasHMAbinder)withoutadverselyaffectingperformance.
Sustainability•Existingmaterialsarereused,reducingtheexploi-tationofvirginmaterialandminimizinglandfillmaterial.
•Costsrelatedtotheprocessing,purchasing,andtransportationofvirginaggregatesareminimized.
•In-placerecyclingreducestrucktrafficandfuelconsumption,andalsoreduceslocalroaddamagefromhaultrucks.
•UsingRCA,particularlyinapplicationsthatexposeittotheatmosphere(e.g.,embankmentfill,gravelroads,andrailroadballast),resultsinaprocesscalledcarbonsequestering.TheprocessessentiallyrecapturesCO2fromtheatmosphere.
For More InformationAmericanConcreteInstituteCommittee555.2001.Removal and Reuse of Hardened Concrete. ACI-555R-01.
AmericanConcretePavementAssociation.2009.Recy-cling Concrete Pavements.EB043P.
AmericanConcretePavementAssociation.2010.Recy-cled Concrete Aggregates Can Be Used in Any Application in Which Virgin Aggregate Can Be Used, and Even Some It Typically Is Not.TS043.4P.
ConstructionMaterialsRecyclingAssociation.2006–2010.Economical Good Sense.www.concreterecycling.org.
FederalHighwayAdministration.2008.Recycled Con-crete Aggregate.NationalReview,http://www.fhwa.dot.gov/pavement/recycling/rca.cfm.
FederalHighwayAdministration.2010.Use of Recycled Concrete Pavement as Aggregate in Hydrau-lic-Cement Concrete PavementTechnicalAdvisory,T5040.37,http://www.fhwa.dot.gov/pavement/t504037.cfm.
NationalConcretePavementTechnologyCenter.Resources on Two-Lift Concrete Paving.http://www.cptechcenter.org/projects/two-lift-paving(accessedJuly2010).
PortlandCementAssociation.2010.Integrated Paving Solutions—Recycled Concrete.http://www.integrated-pavingsolutions.org/RecycledConcrete.html
PortlandCementAssociation.Concrete Technology—Materials: Aggregates,www.cement.org/tech/cct_aggre-gates_recycled.asp
Taylor,P.,S.Kosmatka,G.Voigtetal.2006.Integrated Materials and Construction Practices for Concrete Pave-ment.NationalConcretePavementTechnologyCenter,IowaStateUniversity.
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s
10-1
Repair and Restoration
DescriptionTherepairandrestorationofconcretepavementsaretasksconductedtoimproveadistressedpavementbyrestoringbothfunctionandstructuralcapacity.Thevarioustechniquesthatfallintothiscategorycanbeconductedoneormoretimesduringthelifeofthepavement.Thetypeofrepairdependsontheconditionofthepavementatthetime.Quiteoften,promptrepairsaremoreeffectiveandlessexpensivethandelayedrepairsorrehabilitation.Thefollowingsummarizessomeofthemorecommonrepairsandrehabilitationtechniquesusedonconcretepavementsinordertoextendperformance.
Full-Depth RepairsFull-depthrepairsareusedtoaddressanareaofmajordistressinapavement.Thiscouldbealocalizedeventorextendedthroughoutthepavementsection.
Afull-depthrepaircanprovidegoodlong-termper-formance(morethan10to15years)ifthequalityoftherepairisgoodandtherightmaterialsareused.
Inconcretepavements,full-depthrepairsmostoftenconsistofcast-in-placeconcretethatreplacesthefulldepthoftheexistingslab.Figure10-1showstheprocessforfull-depthrepairofaJPCPpanel(fromtoptobottom):identifycandidateslabs,removeexistingpavement,andreplacewithnewconcrete.
Asimilartechniqueisusedforjointedpavements,wherepartorallofaslabpanelcanbereplacedwiththejointreinforcementbeingreplacedatthesametime.
Figure10-1. Full-depth repair of a concrete pavement slab
10 Guide to Cement-Based Integrated Pavement Solutions
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
REPA
IR A
ND R
ESTO
RATI
ON
10-2
Partial-Depth RepairsApartial-depthrepairconsistsoftheremovalandreplacementofsmall,shallowareasofdeterioratedconcretepavementatspalledordistressedjoints.Forapartial-depthrepairtobepractical,thedistresstypi-callyhadnotextendeddeeperthanone-thirdofthedepthoftheslab.However,duetotherecentavail-abilityofjointmillingmachinesasa“U”mill,partialdepthrepairshaveextendedtoT/2.Theloadtransferdevices,ifpresent,shouldbefullyfunctional.Figure10-2showsapavementshowingspalling.Spallingcancauserideandnoiseproblemsforthetravelingpublic,
andthuspartial-depthrepairscanremedyfunctionalperformance.Apartial-depthrepairbeginswiththeremovalofdistressedconcretebysawing,chip-ping,and/ormillinguntilsoundconcreteisexposed.Repairmaterialisthenappliedandthesurfacetexturerestored.Finally,curingshouldbeconductedpertherecommendationsspecificforthepatchmaterialused.
StitchingStitchingisarepairmethodforrestoringloadtransferatlongitudinalcracks(seeFigure10-3).Thistypeofrepairisanoptionwhenslabsarenotseverelydis-tressed.Holesaredrilledatadiagonalfromonesideofthecracktotheother.Theangleofthediagonalshouldbeconsistentandmeasurebetween35and45degrees.Epoxyfollowedbyatiebarfillthehole.Thetiebarshouldpassthroughthecrackatmid-depth.Itisimportantnottodamagethesurfaceoftheconcretewhileperformingthistypeofrepair.Surfacedam-agecanbeavoidedbychoosingappropriatedrillingequipmentsuchasahydraulic-powereddrillandabitthatis0.375in.(10mm)greaterthanthediameterofthetiebarthatwillbeinserted.Thesizeofthetiebardependsonslabthickness,angleofhole,andhole’sdistancefromthecrack.
Figure10-2. Partial-depth repair process at joint
Figure 10-3. Cross-section of concrete pavement showing stitching
Slab StabilizationSlabstabilizationisarepairtechniqueforconcretepavementinwhichaflowablematerialisinsertedbeneaththepavementslabsinordertorestoretheirsupport.Duringtheprocess,voidsarefilledthatliebetweentheslabandthesupportinglayer.Theseareoftencausedbywaterinfiltrationandsubsequent
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s REPAIR AND RESTORATION
10-3
pumpingoffinestothesurface.Voidsweakenthestructureandwithoutrepaircanleadtobreakingupoftheslabsduetotrafficloads.Thematerialthatisinsertedshouldfillthevoidsbutshouldnotlifttheslab.
Slabstabilizationrestoresslabsupport,reducespave-mentdeflections,andminimizestheprogressionoffurtherdistress.Thesuccessoftherepairdepends,inpart,onidentifyingtheareaswithlossofsupport.Furthermore,theinjectionofmaterialundertheslabmustbeperformedinsuchawaythatthevoidisadequatelyfilled,whichencouragestheuseofanexperiencedcontractor.Figure10-4showstypicaltasksduringaslabstabilizationrepair,whereholesaredrilledintotheconcreteslab,whichisthenfilledwithgroutmaterial.
Slab JackingSlabjackingisarepairprocedureinwhichaconcretepavementslabisraisedbyapplyingpressurizedgroutbeneaththeslab.Slabjackingisusedtofixlocalizedspotsofsettlementoftenfoundnearfillareas,culverts,andbridgeapproaches.Whendoneproperly,thistechniquecanrestoretheridequalityofapavement,althoughitdoesnotcorrectfaultedjoints.Thegroutmixtureorpolyurethaneusedintherepairshouldbecertifiedforthispurpose.Theprocedureissimilartoslabstabilizationinthatthelocationsshouldfirstbecarefullyidentified.Holesaredrilled,andapumpingsequenceisidentifiedtoachievethedesiredeffect.Materialistheninjected—insequence—sothatthe
Figure 10-4. Drilling operation as part of slab stabilization
slabisraisednomorethan0.25in.(6mm).Thispro-cesscontinuesuntiltheslabreachesthedesiredgrade.Successinslabjackingismorelikelywhenperformedonstructurallysoundpavementwithlocalizeddepres-sions.Aprovenprocessanddurablematerialsshouldbeused.
Joint ResealingJointresealingconsistsofplacingasealingmaterialinanexistingjointorcracktoreducemoistureinfiltra-tionandminimizeintrusionofincompressibles.Whencracksandjointsarenotproperlysealed,watercansometimesinfiltrateandsaturatethelowerlayersofthepavement.This,inturn,cancausevariouspave-mentdistresses.Sealingmaterialistypicallyaliquid(hotorcold)butcanalsobeanexpansionjointfiller(preformed).Thejointdesigntypicallydictatesthetypeofsealanttobeused.Thedesiredpropertiesofthesealantaredurabilitytotrafficandenvironment,extensibilitythatallowsjoint/crackmovementwithoutrupture,andadhesivenessthatpermitsadherencetothecrackorjointwalls.Ajointresealingprocedurefollowsfivebasicsteps:oldsealantremoval,jointrefacing,jointreservoircleaning,backerrodinstal-lation,andnewsealantinstallation.Thekeyfactorsforthesuccessofthisrepairaretheproperselectionofjoints/cracks,selectionofsealingmaterial,restora-tionofthejointreservoirandshapefactor,reservoirpreparation,andpropersealantapplication.Figure10-5showstheapplicationofjointsealant.
Dowel Bar RetrofitLoadtransferacrosstransversejointshasalwaysbeenafactorcontributingtothelifeofaconcretepave-ment.Steeldowelsareoftenusedtoensureloadtransfer.However,problemscansometimesariseovertime,includingcorrosionandhighbearingstressesthatcanerodethesurroundingconcrete.Onolderconcretepavements,orthosethatweredesignedforlowertraffic,loadtransfermaybeprovidedbyaggre-gateinterlockonly.Overtime,thelossofloadtransfercanmanifestitselfintojointfaultingandslabcrackingandthusshouldberemedied.
Loadtransferrestorationisdefinedastheinstallationofmechanicaldevicesinanexistingpavement.Along
Gu
ide
to C
em
en
t-Ba
sed
Inte
gra
ted
Pa
vem
en
t So
lutio
ns
REPA
IR A
ND R
ESTO
RATI
ON
10-4
transversejoints,theloadtransferisusuallyaccom-plishedbyinstallingdowelbars.Todefinewhetherornotloadtransferisadequate,afallingweightdeflec-tometercanbeusedtoassesstheloadtransfereffi-ciency.Agoodcandidateforrepairisapavementingoodstructuralconditionbutwithpoorloadtransfer(lessthan50to60percent).Pavementswithfaultingbetween0.12and0.5in.(3and13mm)arealsogoodcandidates,asarethosewithlessthan10percentofslabswithmultiplecracks.
Dowelbarretrofitbeginswithslotting,typicallybysawingandchipping.Thejointispreparedandthedowelbaraffixedtoajointinsert.Therepairmaterialisthenplacedandcuredasneeded.Quiteoften,dia-mondgrindingcanbeconductedafteralldowelbarretrofitsarecomplete.Figure10-6displaysaconcretepavementwhereslotshavebeencutandcleanedto
retrofitdowelbars.Notethatretrofittingisoftendoneinthewheelpathsonly.
Diamond Grooving and GrindingDiamondgroovingandgrindingaresurfacetreat-mentsperformedtoimprovethefunctionalcharac-teristicsofapavement.Diamondgrindingconsistsofremovingaverythinlayerofthesurfaceusingasetofcloselyspaceddiamondsawblades.Theresultofthistechniqueincludesimprovementstosmoothness,fric-tion,andnoise.Grindingisrecommendedwhenthepavementisstructurallysound,andbeforeconduct-ingthisrepairthehardnessoftheconcreteaggregateshouldbedeterminedsothatthediamondbladesareselected,sized,andspacedaccordingly.Theneedfor
Figure 10-5. Application of joint sealant
Figure 10-6. Contiguous concrete slabs prepared for dowel bar retrofitting
Figure 10-7 Diamond grinding concrete pavement for surface restoration
Gu
ide
to C
em
en
t-Base
d In
teg
rate
d Pa
vem
en
t Solu
tion
s REPAIR AND RESTORATION
10-5
associatedtreatments(e.g.,loadtransferrestoration)shouldalsobeconsideredpriortothistreatment.Fig-ure10-7displaysthetypicalappearanceofaconcretepavementthathasbeendiamondground.
Diamondgroovingisusuallydonetominimizethehydroplaningeffectinapavement.Channelsaregroovedontothesurfacetoaccomplishthisgoal.Dia-mondsawbladesareusedtocuttheseparallelgroovesineitherlongitudinal(morecommon)ortransversepatterns.Otherbenefitsofthisrepairareimprovedwetweatherfrictionandthereductioninsplashandspraywhenthepavementiswet.
Candidatepavementsfordiamondgroovingareoftenbasedonhistoricalcrashrates.Thissurfacetreat-mentisgenerallyperformedatlocalizedareasandonpavementsthatarestructurallysound.Thesuc-cessofthisrepairdependsontheselectionofpropercandidateprojectsandtheproperselectionofgroovedimensions.
Figure10-8illustratesaconcretepavementwherediamondgroovingisbeingperformed.Inthiscase,thegroovingpatternislongitudinal.
For More InformationAmericanConcretePavementAssociation.2008.Con-crete Pavement Field Reference: Preservation and Repair.EB239P.Skokie,Illinois:AmericanConcretePavementAssociation.
Fanous,F.S.,J.K.Cable.etal.2006.Laboratory Study of Structural Behavior of Alternative Dowel Bars (Proj. 7).Researchproject,NationalConcretePavementTech-nologyCenter,IowaStateUniversity,April.
FederalHighwayAdministration.2008.Concrete Pave-ment Preservation Workshop.Draftinstructorguide.
Taylor,P.C.,S.H.Kosmatka,G.F.Voigt,etal.2007.Integrated Materials and Construction Practices for Con-crete Pavement: A State-of-the-Practice Manual.NationalConcretePavementTechnologyCenter,IowaStateUniversity,October.
TexasDepartmentofTransportation.2008.Pave-ment Design Guide.TxDOTConstructionDivision.November.
Figure 10-8. Longitudinal grooving of a concrete pavement to restore macrotexture
National Concrete Pavement Technology CenterInstitute for Transportation
Iowa State University
2711 South Loop Drive, Suite 4700Ames, IA 50010-8664