New Audenried High School

Originally Opened in 1931 New School Opened in 2008

Project Specifics

• School District Capital Improvements Project• Multi-Prime Contract• 211,515 s.f. Building Budgeted at $62.5 Million

Dollars• Project included the demolition of the existing

structure, land enhancement, construction of two gyms, cafeteria, auditorium, three story classroom wing, library, diesel academy, six science labs, music academy, and a culinary school.

Earth Works/ Reconditioning the Land

Architectural Plans

Steel and Foundation Work

Concrete Progress and Steel Erection Process

Concrete Arch Work Main Gym

Exterior Façade Work

Interior Finish Work

Project Responsibilities

• QA/QC throughout the design, shop drawing, and construction process

• RFI, COR, and RFP recommendations and review.• Overall Coordination of the Project• Maintaining all project correspondences• Ensured Site Safety with owner supplied policy• Ensured schedule compliance• Reviewed and processed payment applications• Ensured Contact compliance throughout the projects

duration.• Provided monthly reports on progress.