Post on 16-Apr-2017
Planning and Scheduling Construction Projects Guideline to develop and review baseline schedules Part 2: Schedule Assurance Review
Prepared by Alberto Sanchez
1
Alberto Sanchez BEng, MsCLog, MIntBus, GradCertEnSt
Alberto has over 20 years of experience delivering capital projects with values from $100 million to over $10 billion in Asia-Pacific, Middle East, Europe and Central Asia and Latin America in the private and public sector. He has worked across different industries including oil and gas, chemicals, utilities and infrastructure throughout all project phases (feasibility studies through to commissioning) as project controls manager, head of project controls, planning manager and head of capital projects for international oil companies, E&C contractors and consulting firms
2
Alberto holds a bachelor degree in civil engineering, master degree in logistics and operations, master degree in business and postgraduate in energy studies from recognised Australian universities. He is often requested as a keynote speaker at major companies and industry conferences worldwide on planning/scheduling, risk management and modular construction. He is always interested in hearing from former colleagues, clients, or just interesting folk, so feel free to contact him
Contents • Part 1: The Planning Process
• Common planning problems • The planning and scheduling process • The schedule basis • Productivity rates and construction durations • Resource loaded schedules and resource leveling • Some factors impacting the baseline schedule
• Part 2: Schedule Assurance Review
• Schedule quality review • Schedule risk review • Schedule benchmark review • Conclusion
3
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
Schedule Assurance Review • The construction industry performs large investments in very
complex and risky environments
• To increase project success, clients and contractors perform independent reviews at specific project decision “gates”
• This review process is called Project Assurance Reviews and it seeks to assess the ability to meet the project objectives in terms of time, cost, quality, safety, operability performance, etc.
• The reviews are conducted by independent expert teams or Subject Matter Experts (SME) in all disciplines that help to identify weaknesses and shortcomings that may put the project at risk
• The independent expert teams present recommendations and other forms of guidance to ensure that stakeholders can meet their expectations
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
4
Schedule Assurance Review • Key areas of Project Assurance
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
5
PROJECT ASSURANCE
QualityAssurance
Procurement& Subcontracts Assurance
CommunicationAssurance
Risk Assurance
Schedule Assurance
CostAssurance
HSE Assurance
TechnicalAssurance
OrganizationalAssurance
NOTE: Project Assurance members should be independent and objective experts from each discipline or functional department who serve and report to the senior management during project assurance reviews
Applicability: Schedule Assurance • The purpose of this section is
to provide guidelines to assist both the creator of the baseline schedule (scheduler) and the reviewer, who receives the schedule for review and approval
• The focus of schedule assurance reviews is on the overall quality and completeness of the baseline schedule. The schedule review focuses on the following issues
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
6
c
Inclusion of the entire project scope
Sequence and work flow
Constructability Timing and phasing
Adherence to legal and contractual requirements
Unambiguous and clear descriptions of the work
Resource usage and balance
Design and coding of activities(i.e. OBS & WBS)
Level of detail
Highlighting key or critical areas of risk & opportunities
Schedule Assurance Review • Schedule Assurance consists of the following steps:
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
7
Schedule Quality Review
Schedule Risk Review
Schedule Benchmark
Review
ROBUST Baseline Schedule
Schedule Assurance Review • Schedule Assurance consists of the following steps:
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
8
Schedule Quality Review
Schedule Risk Review
Schedule Benchmark
Review
ROBUST Baseline Schedule
Schedule Quality Review • The following is a recommended checklist that allows the
creator of the baseline schedule and reviewers to consistently check baseline schedules – example:
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
9
Project Item Description
1 What is the name of this project? ABC project
2 What type of facility is being constructed (e.g., process, power, infrastructure, or other)?
Industrial process plant
3 Is this a joint venture project? No
4 Where is this project located (city, state, country)? Abu Dhabi, UAE
5 What is the total installed cost of this project (in millions)? 400 MM USD
6 Under what type of contract is this project being executed (e.g., lump sum, cost reimbursable, cost plus percentage, or other)?
Engineering, procurement and construction (EPC)
lump sum
7 What is the scheduled duration of this project in months? 36 months
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
10
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
1 How well do you understand the project scope? e.g. process plant, infrastructure, greenfield, expansion
2 Does the company have previous experience with this client? e.g. similar scope, same location, same technology
3 Do you personally have previous experience with similar project? e.g. same client, similar scope, same location, same technology
4 How well do you understand under what type of contract is this project being executed? e.g. EPC, EPCm, cost reimbursable, cost plus percentage, or others
5 How well do you understand the partnering or joint venture split? e.g. personnel and technology, construction scope
6 How well do you understand the project location (city, state, country)? e.g. site access, local labor productivities, weather conditions, local customs
• Section 1: General Checklist Template General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
11
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
7 How well do you understand the local regulations? e.g. permitting, local approval authorities and processes, local design authorities
8 How well do you understand the schedule requirements and phasing? e.g. contract milestones, temporary construction phase, early production phase, pre-shutdown phase, etc.
9 Is the project being benchmarked against a similar project? e.g. similar plant, industry averages, productivity metrics
10 Is the work breakdown structure (WBS) or work packages being defined? e.g. process area, utility areas, buildings, etc.
• Section 1: General Checklist Template General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
12
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
11 Is the basic information being reviewed? e.g. license, process flow diagram (PFDs), equipment list, process units, utility units
12 How well do you understand the plant layout or general layout? e.g. major equipment location, key layouts
13 Does this project have a complete basic design or FEED package? e.g. incomplete design, outstanding design items, degree of definition, basis of design
14 Does this project have multiple engineering execution locations? e.g. special consultants, architectural design, local designers
15 Does this project have adequate site studies available? e.g. soil investigation, topographic surveys, initial plant surveys
16 Is the list of engineering deliverables defined? e.g. specifications, drawings, supporting documents for permits
• Section 2: Engineering Checklist Template General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
13
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
17 Does the company have previous experience with the selected technology or license? e.g. process design basis, process equipment list, P&IDs
18 Does the company have previous experience with the project specifications and codes? e.g. high end, industry standards, local design codes
19 How well do you understand the engineering approval requirements? e.g. review cycles, third parties, local approval authorities and processes
20 Is the list of design deliverables and engineering activities being defined and identified in the schedule? – refers to the project scope and client requirements
• Section 2: Engineering Checklist Template General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
14
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
21 How well do you understand the procurement policies and procedures of this project? e.g. minimum number of vendors/bidders, approval of alternative vendors, purchase order approvals
22 Is the requirement for local vendors defined? e.g. local content, approval of alternative vendors
23 Is the list of materials or equipment supplied by client defined? e.g. lead times, novated orders, free issues, vendor design interfaces
24 Is the list of long lead items (materials and/or equipment) defined? e.g. completeness of engineering datasheets for early purchasing, licensed equipment, single sources, lead times
25 Are lead times for equipment and material defined? e.g. based on preliminary quotes, previous orders, historical database, required on site dates (ROS)
• Section 3: Equipment & Material Supply Checklist General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
15
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
26 Is the location of vendor(s) for critical purchased items defined? e.g. transport period from vendor shop(s) to site, multimodal transport (by rail, sea and road), border crossing times
27 Are weather windows for transportation of materials or equipment defined? e.g. storms, icy roads, high winds
28 How well do you understand the customs clearance and in-country transport process on this project? e.g. transit times, closure of custom points, port capacity, inland transport and handling
29 Does the company have adequate laydown area defined? e.g. availability of warehouse, storage capacity, distance from/to construction site, alternative sites
30 Is the list of procurement activities being defined and identified in the schedule? e.g. RFQs, technical and commercial evaluation, negotiation and purchase order, vendor design, fabrication, factory acceptance test (FAT), packing and transport, etc…
• Section 3: Equipment & Material Supply Checklist General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
16
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
31 Is the pre-fabrication scope or strategy defined? e.g. rack modules, process modules, pipe spools, pre-cast elements, prefabricated buildings
32 Is the fabricator(s) subcontract plan defined? e.g. single or multiple prefabrication shops
33 Does the company have previous experience with the proposed fabricator(s)? e.g. similar facility, same location
34 Is the material purchasing scope for fabricator(s) defined? e.g. purchasing by company or fabricator(s), interfaces between material deliveries and fabrication schedule
35 Is the location of major fabricator(s) defined? e.g. productivity of workforce, fabrication shop/yard capacity, distance from/to closest port and/or construction site
36 Is the transport and delivery strategy defined? e.g. large deliveries vs multiple small-sized deliveries
• Section 4: Fabrication Checklist Template General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
17
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
37 Are weather windows for transportation of pre-fabricated items defined? e.g. storms, icy roads, high winds
38 How well do you understand the shop inspection and test requirement? e.g. time and test duration, interfaces with client/owner, third-party inspections
39 Is the list of pre-fabrication activities being defined and identified in the schedule? e.g. shop drawings, purchasing of raw materials, fabrication and assembly, inspection and tests, packing and transport
• Section 4: Fabrication Checklist Template General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
18
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
40 Is there any requirement for local subcontractor(s)? e.g. local content, approval of alternative subcontractor(s), necessary local licenses, permits, additional mobilization times, visas
41 Is the construction subcontract plan defined? e.g. scope of works, work packages, single or multiple subcontractors, interface plan
42 How well do you understand under what type of contract is subcontracting executed? e.g. cost-plus, unit rates, guaranteed maximum price, fixed price, incentive
43 How well do you understand the subcontractor(s) capability? e.g. experience in similar work, workforce capabilities, equipment availability, current on-going commitments and pending awards
44 Does the company have previous experience with the proposed subcontractor(s)? e.g. worked together in similar project, similar scope, same location, available historical productivities
• Section 5: Subcontract Checklist Template General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
19
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
45 Is the material purchasing plan for subcontractor(s) agreed? e.g. purchasing by Company or subcontractor(s), interfaces between material deliveries and construction schedules
46 Is the list of subcontract activities being defined and identified in the schedule? e.g. preparation of bid packages, bid evaluation and reviews, bid negotiation and award, subcontractor(s) mobilisation to site
• Section 5: Subcontract Checklist Template General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
20
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
47 Does the company have performed a constructability review? e.g. construction methods, modularisation or pre-assembly designs, standardised design elements, site fabrication vs. shop fabrication
48 Is the construction plan defined? e.g. temporary construction facilities, construction methods and procedures, site access and restrictions, heavy lift and rigging studies, safety requirements, etc.
49 How well do you understand the proposed construction sequence and priorities? e.g. installation sequences, sequence of transport and erection of modules, sequence of installation of heavy lift equipment, sequence of tie-ins, sequence of handover of site areas
50 Does the company have access date(s) to construction site defined and identified in the schedule? e.g. site preparation complete by client, demining complete, shutdown start date, site permit approved
51 Is the list of preparatory works defined and identified in the schedule? e.g. labor camp, temporary facilities, laydown areas, demolition, soil remediation, asbestos removal, etc.
• Section 6: Construction Checklist Template General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
21
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
52 How well do you understand interfaces with other contractors and/or communities? e.g. future or on-going construction site works, works by others, traffic and local roads
53 How well do you understand the working calendars and/or constraints? e.g. max. hours per day, overtime, rosters, non‐work periods, 24x7 coverage, SimOps calendar
54 How well do you understand local customs, practices or traditions? e.g. public holidays, religion celebrations, language barriers, safety culture
55 Are construction labor sources and resources availability known? e.g. union or open shop labor, local content requirements, current labor market conditions
56 Are special construction equipment requirements defined? e.g. heavy cranes, barges, mobilisation time, equipment/plant inspections, road closure and escorts, etc.
• Section 6: Construction Checklist Template General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
22
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
57 Are weather windows for construction defined? e.g. winter, rainy season, sand storms, extreme heat, etc.
58 Are key construction quantities available? e.g. number of piles, m3 of concrete, ton of steel, DiaInch of pipes, meter of cables
59 Is the list of construction activities being defined and identified in the schedule? e.g. site preparation, underground, foundations, major steel structures, large-bore pipes, cable trays, equipment installation, etc.
60 Are estimations of activity durations defined? e.g. based on quantities (BOQs), productivities, etc. (please refers to part 1 for details)
• Section 6: Construction Checklist Template General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Quality Review
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
23
Questions
Ver
y w
ell
So
mew
hat
w
ell
No
t to
o
wel
l
No
t at
all
N/A
61 How well do you understand the scope of project completion? e.g. punch lists, site test requirements, hydrotest, loop checks, solo run test
62 How well do you understand the pre-commissioning sequence and priorities for this project? e.g. storm water, potable water, firewater, power generation, instrument air, DCS and control room, cooling water, water treatment, steam, flare s, process trains, etc.
63 How well do you understand the pre-commissioning support activities for this project? e.g. mobilisation of vendor representatives, notification to third parties or client representatives
64 Is the list of pre-commissioning activities being defined and identified in the schedule? e.g. power energisation, hydrotest, running trials, cleaning and flushing, loop checks, etc.
• Section 7: Pre-commissioning Checklist Template General Engineering Equipment and
material supply Fabrication Subcontract Construction Pre-commissioning
Schedule Assurance Review • Schedule Assurance consists of the following steps:
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
24
Schedule Quality Review
Schedule Risk Review
Schedule Benchmark
Review
ROBUST Baseline Schedule
Schedule Risk Review Once you completed the schedule quality review and the preliminary baseline schedule is ready, the next step consists of:
• Assessing the potential variability in the schedule duration resulting from identified project risks
• Assessing how risks and opportunities may influence the estimated activity durations and overall schedule
• Understanding which activities have the highest probability of impacting the project completion date or key milestones
• Understanding which risks have higher impact on key milestones or overall schedule
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
25
A brief to Schedule Risk Review • Using schedule risk analysis allows you to enter extra
information about the uncertainty of the duration of the schedule activities
• This extra information is used to produce more accurate or realistic schedules. It also help you manage your project more effectively by answering questions such as: • What is the chance of finishing the project on time? • What risks have higher impact on the schedule? • What is the best case? what is the worst case? • What activities are most likely to cause delays?
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
26
Schedule Risk Review • Level 1: Identify the project risks and
opportunities. Typically, this includes the use of a risk checklist and the start of the project risk register
• Level 2: Analyse project risks using a qualitative method based on a probability x impact matrix. It helps to prioritise the list of risks
• Level 3: Analyse project risks using a quantitative method based on Monte Carlo simulations. It helps to estimate the potential impacts of risks and determine the probability of meeting the project target
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
27
Risk Category
Availability of sufficient amount of suitable soils from nearby borrow pits, resulting in increase in transport costs
Cost
Shortage of skilled workers, resulting in longer construction schedule Schedule
Extreme
High
MediumLowLow
Medium
HighMedium
Low
Impact
Likel
ihoo
d
Schedule Risk Review • Example:
• Estimated cost: US$ 420 MM • Target duration: 25 months • Project location: Africa • Project award date: Jan 2011 • Target finish date: Jan 2013 • Contract type: EPC lump sum • Industry: Oil & Gas (offshore)
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
28
E = Engineering; P = Procurement; and C = Construction
Preliminary project schedule
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
29
Project risk register • Example: risks identified during the risk workshop with
project team members
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
30
Risk Pre-mitigation Response Post-mitigation
ID Title Probability Impact Type Probability Impact RBS
001 Decline by qualified subcontractors to bid VL M Reduce VL M Commercial Risk 002 Extended contract sanction period H M Reduce H L Commercial Risk 003 Late comments and/approvals from client or local authorities VL M Reduce VL L Technical Risk 004 Inappropriate selection of subcontractor(s) L H Avoid VL H Commercial Risk 005 Bankruptcy of local subcontractor(s) or supplier(s) VL H Avoid VL H Commercial Risk 006 Late design changes during fabrication L H Reduce L M Technical Risk 007 Late delivery of equipment to fabrication yard L M Reduce L L Fabrication Risk 008 Late material deliveries to fabrication yard L M Reduce L L Fabrication Risk 009 Current workload of preferred fabrication yards in the region M H Reduce M M Fabrication Risk
011 Unavailability of vessels for transport from yard to Africa (missing the window) M H Reduce M M Transport Risk
012 Storms - wind, waves, high currents (Autumn/Winter Period) during transportation of platform from fabrication yard M VL Accept M VL Transport Risk
013 Damages to modules during transport from fabrication yard VL H Reduce VL M Installation Risk 014 Piles failure or damage due to unexpected subsea soil conditions L H Avoid VL M Installation Risk 015 Severe weather conditions during offshore heavy lift (especially in winter) H L Accept H L Installation Risk 016 Shortage of local skilled manpower during installation offshore M M Reduce M L Installation Risk 017 Incorrect selection of the flotel L M Avoid VL M Installation Risk 018 Issues with vendor representatives during installation/test offshore L M Reduce L L Commercial Risk 019 Difficulties to meet high local labor content requirements H L Accept H L Commercial Risk 020 Limited access during demolition and revamp works (SimOps) H L Accept H L Installation Risk
021 Delay during final interfaces with existing systems (e.g. telecomm, electrical) M L Reduce L L Installation Risk
Output of the schedule risk review • Q: What is the
probability of finishing the project on or before 25 months (Jan 2013)?
• A: The probability of completing the project on 25 months (Jan2013) is less than 5% • Most Likely (P50) = 28M • Worst Case (P90) = 31M
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
31 06-Dec-12 25-Jan-13 16-Mar-13 05-May-13 24-Jun-13 13-Aug-13 02-Oct-13 21-Nov-13
Distribution (start of interval)
0
20
40
60
80
100
120
140
160
180
200
220
Hits
0% 04-Dec-12
5% 07-Feb-13
10% 26-Feb-13
15% 12-Mar-13
20% 21-Mar-13
25% 01-Apr-13
30% 09-Apr-13
35% 17-Apr-13
40% 29-Apr-13
45% 03-May-13
50% 10-May-13
55% 16-May-13
60% 23-May-13
65% 30-May-13
70% 06-Jun-13
75% 13-Jun-13
80% 21-Jun-13
85% 02-Jul-13
90% 16-Jul-13
95% 05-Aug-13
100% 07-Nov-13
Cum
ulat
ive
Freq
uenc
y
OFFSHORE EXAMPLESchedule Risk Review
Output of the schedule risk review • What risks are most likely to cause delays?
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
32 16%
18%
19%
20%
22%
25%
27%
28%
41%
48%
Damages to modules during transport from fabrication yard
Delay during final interfaces with existing systems (e.g.telecomm, electrical)
Decline by qualified subcontractors to bid
Issues with vendor representatives during installation/testoffshore
Incorrect selection of the flotel
Unavailability of vessels for transport from yard to Africa(missing the window)
Late design changes during fabrication
Piles failure or damage due to unexpected subsea soil conditions
Current workload of fabrication yards in the region
Shortage of "local" skilled manpower during installation offshore
Schedule Assurance Review • Schedule Assurance consists of the following steps:
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
33
Schedule Quality Review
Schedule Risk Review
Schedule Benchmark
Review
ROBUST Baseline Schedule
Schedule Benchmark Review • Benchmarking has long
been used by clients and contractors to improve the accuracy of project performance
• It is the process of comparing one’s own baseline (or proposal) schedule against the results of similar projects to validate our proposed project schedule
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
34
PREPARE BASELINE SCHEDULE
DEVELOP PRODUCTIVITY
METRICS
SCHEDULE DATA COLLECTION
SYSTEM
COMPANY PROJECTS DATABASE(INTERNAL)
SIMILAR PROJECTS/
NORMS(EXTERNAL)
CONDUCT SCHEDULE
BENCHMARK COMPARISON
VALIDATE SCHEDULE
SPECIFIC FACTORS AFFECTING THIS
PROJECT
YES
ACCEPT BASELINE SCHEDULE
NO
Schedule Benchmark Review • Example: contractor historical data
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
35
Project Project location Duration (Months)
Cost (USD MM)
Project A Europe 27 320 Project B Middle East 28 400 Project C Middle East 30 450 Project D Asia 33 580 Project E North America 35 720 Project F Middle East 36 780 Project in Analysis Africa 25 420
Schedule Benchmark Review • Example: contractor historical data
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
36
320
400 450
580 720
780
420
200
300
400
500
600
700
800
900
24 25 26 27 28 29 30 31 32 33 34 35 36 37
Proj
ect C
ost (
USD
MM
)
Project Duration (Months)
• The expected duration of 25 months is below the benchmark for similar projects
• The expected duration, from historical data, should be in the range of 27 to 28 months
Observations Suggestions/Recommendations
The expected duration of 25 months is shorter than similar projects completed by the company. The benchmark data suggests that the project duration should be between 27 and 28 months. Also, the schedule risk analysis shows that the most likely scenario or P50 should be 28 months (3 extra months)
1. Consider the use of “reusable” engineering or standard design library in some areas to reduce engineering
2. Consider overdesign vs. waiting for detailed information from vendors 3. Simplify the process of cycle time review (e.g. cross-functional team) 4. Assess the time-cost effect of selective overtime, double-shift, or additional
resources during design and fabrication 5. Relocate appropriate engineering resources to fabrication yards to expedite
technical queries 6. Consider “schedule” as major criteria to evaluate fabrication bids 7. Consider the use of incentive/bonus in the contract for early fabrication
completion 8. Consider the use of single source for critical procurement items to reduce
time of vendors selection 9. Assess the time-cost effect of allocating premiums for early supplier
deliveries 10. Confirm capabilities and capacity of proposed fabrication yards, and
perhaps assign the fabrication of jacket and piles to a separate yard 11. Assess the time-cost effect of using international subcontractors instead of
local subcontractors (e.g. penalties for non-compliance with local content) 12. Consider a cost contingency for eventual penalties and/or prolongation
costs in case schedule cannot be compressed 13. Negotiate a 3-month grace period to prevent cost penalties from LDs
Prep
ared
by
A. S
anch
ez
(am
sanc
hezu
@gm
ail.c
om)
37
Conclusion: Project Assurance
38 Contact: amsanchezu@gmail.com
End of Part 2: Schedule Assurance Review