Load Calculation sheet
Load demand based on proposed built up area:
Residential Load:
Total buildup area: 28689.52 sq meter
Hence (28689.52x75)/(1000)=2152 KVA ------- A
Commercial load:
Total build up area:921.13 sq meter
Hence(921.13x200)/(1000)=185 KVA --------B
Common load:100 KVA-----------C
Total KVA:2437 KVA
Hence 4 nos 630 KVA DTC proposed.