April 27-28, 2007 Barnes & Tucker Project€¦ · Barnes-Watkins Refuse Pile, Barnes and Tucker,...

Post on 14-Oct-2020

0 views 0 download

Transcript of April 27-28, 2007 Barnes & Tucker Project€¦ · Barnes-Watkins Refuse Pile, Barnes and Tucker,...

Barnes & Tucker Project

Daniel Sammarco,P.E.Jon Smoyer, P.G.

DEP-Bureau of Abandoned Mine ReclamationCambria Office

Dsammarco@state.pa.usJosmoyer@state.pa.us

Project Team:Art Crossman Darryl AudiaPat Webb Bob OshabenKen Bobak Max Scheeler

West Branch Susquehanna Restoration SymposiumApril 27-28, 2007

OutlineA. Background

B. Project Assessment- inter-basin transfer- Blacklick Creek - West Branch Susquehanna River

C. Project Design

D. Q&A

X Project Location

A. Background – existing plant

Mahaffey, Pa

Curwensville Dam

Barnes & Tucker filed bankruptcy in 2001 – Cleans

Streams Foundation takes over operation of the

Dumans Plant

DEP explores long-term operation alternatives.

…a Win – Win Scenario

www.srbc.netwww.dep.state.pa.us

more efficient treatment needed existing pumping costs are high trust fund is limited mine pool resource recovery

agricultural consumptive use demands approx. 25 miles of stream restored allows for increased low flow releases

from the Curwensville reservoir SRBC, through a PA General Assembly

grant, will contribute $3.9 milliontowards long-term O&M.

Duman Treatment Plant

Proposed New Treatment Area

1970 Blow out Area

Eastern Continental Divide

B. Project Assessment - Inter-basin Transfer

OSM: Hawkins,Perry

x

Inter-basin Transfer (IT)

1. PA law requires projects involving IT to have a NPDES permit.

2. Assessment of watershed basins’ (Susquehanna and Ohio )

West Branch Susquehanna Ohio River Basin

> restore ~25 miles stream > BAMR commitment to treat the Red Mill, Vinton #6,

> addresses water demand issues and Wehrum discharges

> continue AML and AMD remediation projects

Susquehanna River BasinOhio River Basin

pH – 7.3Total Iron: 0.50 mg/lTotal Al: 0.28 mg/lTotal SO4 : 62.6 mg/lAlkalinity: 38 mg/l

pH – 7.9Total Iron: <.30mg/lTotal Al: <.50 mg/lTotal SO4 : 34.3 mg/lAlkalinity: 55 mg/l

pH – 3.7Total Iron: 8.1 mg/lTotal Al: 13.6 mg/lTotal SO4 : 420.0 mg/lAlkalinity: -150 mg/lAvg. Flow: 1450 mg/l

B. B. Project Assessment – Blacklick Creek

Barnes & Tucker Lancashire No. 15pH – 7.4Total Iron: 1.5 mg/lAlkalinity: 194 mg/lAvg. Flow: 4689 gpmTHAT’S AN AVERAGE OF 10934 LBS/DAYALKALINITY LOST FROM THE BLACKLICK WATERSHED!

Eastern Associates Coal Co. – Colver PlantpH: 7.8Total Iron: 1.90Alkalinity: 58 mg/lAvg. Flow: 2430 gpm

North Branch Blacklick Creek above Elk CreekpH – 7.3Alkalinity: 31 mg/lTotal Iron: <0.3 mg/lTotal Al: < 0.3 mg/lVery low (< 200 gpm) flow during dry periods due to groundwater recharge lost to underground mines

Elk Creek Downstream at MouthpH - 8.0Alkalinity: 94 mg/lTotal Iron: 0.93 mg/lTotal Al: 0.55 mg/lTSS: 5.0 mg/l

Without B&T dischargeElk Creek at mouth:pH – 7.2Alkalinity: 10 – 50 mg/lTotal Iron: 0.5 –2.0 mg/lTotal Al: 0.5 mg/l

North Branch Blacklick below Elk CreekpH – 8.0Alkalinity: 95 mg/lTotal Iron: 0.55 mg/lTotal Al: <.5mg/l

Red Mill Discharge – Commercial No. 16 minepH- 3.5Hot Acidity: 172.6 mg/lTotal Iron: 52 mg/lTotal Al: 7.7 mg/lAvg. Flow: 210 gpm

Without B&T discharge, North Branch Blacklick belowRed Mill:pH – 6.9Alkalinity: 18 mg/lTotal Iron: .92 mg/lTotal Al: 0.6 mg/l

North Branch aboveVintondalepH – 7.3Alkalinity: 46 mg/lTotal Iron: 1.7 mg/lTotal Al: 0.5 mg/l

Vintondale BoreholesDischarge from Vinton #6 minepH- 4.9Hot Acidity: 307 mg/lTotal Iron: 136 mg/lTotal Al: 5.0 mg/lAvg. Flow: 2200 gpm

South Branch of Blacklick CreekpH- 6.03Hot Acidity: 24 mg/lTotal Iron: 2.21Total Al: 1.93NO BUFFERING HELP HERE!

Wehrum Shaft DischargepH – 3.4Hot Acidity: 298 mg/lTotal Iron: 68 mg/lTotal Al: 20.1 mg/lAvg. Flow: 609 gpm

Blacklick Creek Above Wehrum ShaftpH- 6.4Hot Acidity: 11.4 mg/lTotal Iron: 2.08 mg/lTotal Al: 1.17 mg/l

Blacklick Creek below Wehrum ShaftpH – 6.4Hot Acidity: 14.0 mg/lTotal Iron: 4.8 mg/lTotal Al: 1.5 mg/l

Blacklick Creek without B&T’s water:pH –6.2Acidity – 20 mg/lTotal Iron – 5.5 mg/lTotal Al – 1.7 mg/l

WHAT’S THE SOLUTION?

• Reclaim and remediate the refuse piles at Colver.

• Continue AMD remediation efforts in the South Branch Blacklick

treatRed Mill Mine

Vinton #6 mine

Wehrum mine

B. Project Assessment – West Branch Susquehanna

Barnes-Watkins Refuse Pile project

West Branch- Net Alkalinity Barnes-Watkins Refuse

Pile, Barnes and Tucker, and Bear Run Projects

-300

-250

-200

-150

-100

-50

0

50

100

150

200

250

185.

0

192.

0

199.

0

206.

0

213.

0

220.

0

227.

0

234.

0

Stream Mile

mg/

l

PrePost

increase in Net AlkalinityWest Branch -Total Al

Barnes-Watkins Refuse Pile, Barnes and Tucker, and Bear Run Projects

0

5

10

15

20

25

30

185.

00

192.

00

199.

00

206.

00

213.

00

220.

00

227.

00

234.

00

Stream Mile

mg/

l PrePost

92% reduction in Al t

West Branch - Total Iron Barnes-Watkins Refuse Pile, Barnes and Tucker, and Bear

Run Projects

0

2

4

6

8

10

12

14

16

18

185.

00

192.

00

199.

00

206.

00

213.

00

220.

00

227.

00

234.

00

Stream Mile

mg/

l

PrePost

82% reduction in Fe t

C. Project Design – Proposed Site Location

C. Project Design – Exploratory Drilling Program

1460

1465

1470

1475

1480

1485

1490

1495

1500

1505

1510

1515

7/2/20060:00

8/21/20060:00

10/10/20060:00

11/29/20060:00

1/18/20070:00

3/9/20070:00

4/28/20070:00

1479

1479.5

1480

1480.5

1481

1481.5

1482

1482.5

1483

1483.5

7/2/2006 0:00 8/21/2006 0:00 10/10/2006 0:00 11/29/2006 0:00 1/18/2007 0:00 3/9/2007 0:00 4/28/2007 0:00

1475.00

1480.00

1485.00

1490.00

1495.00

1500.00

1505.00

1510.00

0 50000 100000 150000 200000 250000 300000 350000

B1 - BOREHOLE (PATTERSON ROAD)

1470

1472

1474

1476

1478

1480

1482

1484

1486

1488

1490

8/23

/200

68/

24/2

006

8/25

/200

68/

26/2

006

8/27

/200

68/

28/2

006

8/29

/200

68/

30/2

006

8/31

/200

6

9/1/

2006

9/2/

2006

9/3/

2006

9/4/

2006

9/5/

2006

9/6/

2006

9/7/

2006

9/8/

2006

9/9/

2006

9/10

/200

6

9/11

/200

69/

12/2

006

9/13

/200

69/

14/2

006

9/15

/200

6

9/16

/200

69/

17/2

006

9/18

/200

69/

19/2

006

9/20

/200

69/

21/2

006

9/22

/200

69/

23/2

006

9/24

/200

69/

25/2

006

9/26

/200

69/

27/2

006

9/28

/200

69/

29/2

006

9/30

/200

6

10/1

/200

610

/2/2

006

10/3

/200

610

/4/2

006

10/5

/200

610

/6/2

006

DATE

AVE

RA

GE

ELEV

ATI

O

Draw Down Rate = -0.259'/Day

Draw Down Rate = -0.527'/Day

Active Treatment - Dense Sludge Technology

Pre-Aeration Basin

Ferrous ReactorBasin

Floc. Clarifier/Thickener

Sludge ConditioningReactor

Hydrated lime

Mine pool

Underflow disposal

Polishing Pond

Polymer

Q design = 10.5 MGD

to WBSR

Project Team: Art Crossman Daryl AudiaPat Webb Bob OshabenKen Bobak Max Scheeler

D. Q&A

existing proposed

Hydrology Analysis-Plant effluent

100 year flow = 2400 cfs

Project flow ~ 16 cfs

Maberry (2002-2003)6.

94

4.68

6.64

9.36

9.36

9.36

6.79

4.68

4.68

6.7 6.94

6.34

9.36

9.36

9.36

7.02

4.68

9.36

9.36

9.36

6.55

9.36

-1.2

-1.2

-2.5

-6.1

-13.

9

-15

-15

-11.

7

-6.2

-1.3

-1.3

-1.2

-2.5

-6.1

-8.8

-13.

9

-15

-15

-11.

7

-6.2

-1.3

-1.3

5.74

3.48 4.

14

3.26

-4.5

4

-5.6

4

-8.2

1 -7.0

2

-1.5

2

5.4 5.64

5.14

6.86

3.26

0.56

-6.8

8

-10.

32

-5.6

4

-2.3

4

3.16

5.25

8.06

7.84

-20

-15

-10

-5

0

5

10

15

Month

Flow

Rat

e (m

gdAve. Maberry Pump Rate (mgd)SRB Consumptive Use Need (mgd)Excess (+) / Deficit (-) Resultant (mgd)

1/02 2/02 3/02 4/02 5/02 6/02 7/02 8/02 9/02 10/02 11/02 12/02 1/03 2/03 3/03 4/03 5/03 6/03 7/03 8/03 9/03 10/03 11/03 12/03 Total

2Year

No

Mon

thly

Dat

a

No

Mon

thly

Dat

a