ANA2017 Conference, Sydney, 6 Oct 2017 11

Presentation 6 – Session 2

APR1400 Program in UAE

Young Hoon KIM

General Manager, KHNP’s UAE Project Office

Biography

Young Hoon Kim is the General Manager of

KHNP’s UAE Project Office. He received his

Bachelor's degree in Mechanical Engineering from

Konkuk University in 1997 and his MBA from

KAIST Graduate School of Management in 2010.

Since joining KEPCO in 1996, he had worked at a

nuclear power plant site for more than 15 years. After

having served as General Manager in Shin Hanul

NPP Project Management Office, he is currently

working on the UAE Barakah Project.

Abstract

This presentation will introduce to you the UAE NPP

Project that KHNP joined as a key partner, providing an overall understanding of project details

including project progress, project structures, construction opportunities and challenges,

construction site factors, time & project management, and project costs, etc.

.

Korea Hydro & Nuclear Power Co., Ltd. (KHNP) is Korea’s largest power generation company producing approximately 31% of the nation’s electricity supply with the mission of “enriching the lives of citizens and providing a foundation for the nation’s economic development through the stable supply of power”

KHNP owns and operates 24 units of nuclear power plants, 35 units of hydro power plants, 16 units of pumped-storage power plants, photovoltaic power plants and so on, having roughly 11,500 employees.

While safely operating nuclear power plants in order to eliminate the nation’s concerns over power supply, KHNP also aims to successfully construct new nuclear power plants.

Introduction of UAE Project 1

Contract Structure2

Site-specific Characteristics4

3

Opportunities and Challenges5

Current Project Status

Time & Project Management

Project Cost

6

7

1/28

Owner/Contractor ENEC / KEPCO

Ref. Plant

Scope

Contract Date Dec. 27, 2009

APR1400 x 4 Unit (5,600MW)

Nuclear Fuel (3 Cycles)

Operating Support Service

Shin-Kori 3&4 in Korea

APR1400 4Units Fuel Supply OSSSimulator

2/28

▪ (EOSA) Early Operating Support Agreement

▪ (OSSA) Operating Support Services Agreement

▪ (EOSA) July 2016 ~ SCD of Unit 4 (to be finished after completion of each unit)

▪ (OSSA) SCD of Unit 1 ~ 10 years after completion of Unit 4 (2030)

▪ Dispatch experienced and qualified personnel to UAE NPP

Operating Support Services

▪ July 20, 2016

3/28

Abu Dhabi

Dubai

Barakah

Doha

Ruwais

270km

390km

4/28

5/28

6/28

Joint PM

Agreement

Prime Contract

Subcontract

EAA : Executive Affairs Authority

EAD : Environment Agency - Abu Dhabi

HAAD : Health Authority – Abu Dhabi

NCEMA : National Crisis and Emergency Management

Authority

CICPA : Critical Infrastructure and Coastal Protection

Authority

FANR : Federal Authority of Nuclear Regulation

ADWEC : Abu Dhabi Water Electricity Company

ENEC : Emirates Nuclear Energy Corporation

KEPCO : Korea Electric Power CorporationCICPASite Protection and Security

FANRNuclear Regulation

EAD, NCEMA,

HAAD etc.,EAA

Nuclear Policy

ENECShare Holding(82%)

KEPCOShare Holding(18%)

Barakah OneProject Co.

Nawah EnergyOperation & Maintenance Company

ADWECPower Purchase

7/28

8/28

9/28

Licensing

Design

Manufacturing

Construction

Commissioning

10/28

11/28

Drilling Investigation

Drilling Machine

Geophysical Prospecting

Trench Investigation

12/28

Low seismicity

Tectonically inactive for nearly

100 million years

No Tsunami activity

“Seismic Design Value : 0.3g (7.0M)”

13/28

Barakah Site

[Over 6.0M, 1900~2005]

14/28

❖ Working time should be modified for improving productivity and efficiency.

Description Site Working Time Office Working Time

Morning 05:30 ~ 12:00 (6.5 hrs) 06:00 ~ 12:00 (6.0 hrs)

Afternoon 15:00 ~ 18:30 (3.5 hrs) 14:00 ~ 18:00 (4.0 hrs)

Night / Overnight

(2 shifts)19:30 ~ 04:30(+1) (If necessary)

UAE Labor Law(Federal Law No. 8 of 1980)

15 June - 15 September 2017

12:00 pm – 3:00 pm

15/28

[Muslim & Non Muslim Labor Status]

Muslim 3,206 MD (23%)

Total 14,003 MD

Description Non Muslim’s Working Time Muslim’s Working Time

Morning05:30 ~ 12:00

(6.5 hrs)

05:30 ~ 12:00

(6.5 hrs)

Afternoon15:00 ~ 18:30

(3.5 hrs)-

Night / Overnight

(2 shifts)

19:30 ~ 04:30(+1)

(If necessary)-

Working Schedule

[27 May ~ 25 June 2017]

16/28

Protection Measures

Moving dust in the air Piled-up sand by sandstorm

Arabian Gulf

UAE

17/28

Transport Route

Transport Schedule

D-25 D D+10 D+45D-40

Shipping

Notification

Shipping

Documents

Distribution

ShippingVessel

Booking

D+48

Unloading

at BNPP site

Discharging

in Abu Dhabi

Barakah

NPPContainer Cargo

Busan Port, NY Port,

Yokohama Port, etc.

Khalifa Port

thru Dubai Port

Oversized/

Heavy Cargo

Masan Port, Portsmouth

Port, etc.

Khalifa port/

Musaffah Port

Air Cargo

Incheon Airport,

NY Airport, Narita

Airport, etc.

Abu Dhabi Airport/

Dubai Airport

Major Shipping

(Air)Port

Discharging

(Air)PortClassification

Approx. 440Km

Khalifa Port

BNPP

Road Map (Khalifa Port to Barakah)

Abu Al Abyad

(Stopover No. 1)

ICAD-3

(Stopover No. 2)

18/28

Global Leadership & Competence

19/28

Global Standards

Global Cooperation

➢ Regulatory Review from Multinational workforce

➢ Cooperation in various fields

➢ Enhancing global competence of employees

20/28

Procedures for Project Management- Project Procedure Manual (PPM)

- Site Internal Procedure (SIP)

- Overseas Office Internal Procedures (NOIP, POIP)

Project Management System (NPCMS, PPMS)

Experienced and dedicated Personnel

21/28

- Materials Lists

- Design Information

- Technical Specifications

Design

- Procurement Schedule

- Contract Change

- Suppliers’ Information

Procurement

- Installation History

- Installation Status

- Turnover Information

Construction/Commissioning

- Receiving / Releasing

- Storage / Inventory

- Maintenance, repair

Materials on site

A/E

- Materials Lists

- Design Information

- Bill of Material

NSSS Supplier

- Materials List- Technical Specification

Work Supervision Team

- Materials Request- Materials Installation- Turnover

Procurement Contract Team

- Invitation to Bid- Suppliers Selection- Contracts Signing- Delivery Information

Procurement Control Team

- Technical Evaluation- Manufacturing Check- Delivery Management

Materials Team on site

- Receiving / Storing- Releasing / Re-receiving- NCRs

Overseas Office

- Overseas materials

Materials Management System

22/28

[Licensing Portal]

Document Control & Information Sharing System

[BOK] [e-Portal(External Portal)]

23/28

Regular Project Meetings

Reference Plant’s Lessons Learned

24/28

Remote Technical Support Center

RTSC(KHNP HQ)

KHNP Eng. Center

SKN3,4Engineers

ExternalVendors

KHNPCRI

Commissioning and Subsequent Operations Interface

Construction Operation

Kick-off C to C T/O F/L

SCDCommissioning

Prime ContractOSS

OSSA

HSJV KHNP NE NE

C to O T/O

25/28

KEPCO

HSJV

Construction

KHNP

Commissioning

OWNER

NE

OperationT/O T/O

Const. Plant

System T/O Mechanism

26/28

Project Cost

EPC Cost

Fuel SupplyDesign & Eng. Procurement ConstructionPM

Owner Cost

Other Services

T/G

BOP

NSSS

Contract ChangeOSS

27/28

Fixed Price

Fixed Rate

Cost Reimbursable

Over 40 years experience in NPP Construction

Project Management

Experienced and Qualified Personnel

Supply Chain Management

The World’s Best !