Antitermite ITP

Post on 04-Dec-2015

180 views 18 download

description

Antitermite ITP

Transcript of Antitermite ITP

CLIENT : GAIL

CONSULTANT: MECON CONTRACTOR: JAIHIND PROJECTS LTD

INSPECTION TEST PLAN FOR ANTITERMITEDOC NO.: JPL/KKBMPL/CIVIL/ITP/03 REV. 01

ACTIVITY JPL MECON GAIL REMARK

1 Approval of procedure W R R & A

2 Incoming material checking W RW RW

3 Marking of location & preparation for Treatment W RW RW

4 Check for Depth of Hole W W RW

5 Application of Tretment W W RW

6 safety W R R

Legends:W: Witness Point H : HoldpointRW: Random Witness A : ApprovalR : Review of Documents

FOR JPL FOR MECON/GAIL

Sign:

Name

Date:

KOCHI-KOOTTANAD-BANGALORE MANGALORE PIPELINE PROJECT

SR. NO.