Date: 05.03.2016 To, Secretary Environment & Member Secretary SEIAA, Rajasthan, Department of Environment Secretariat, Jaipur Subject: Regarding Environmental Clearance for our Mining Project “Asan
Quartz and Feldspar Mine, Lease Area: 5.00 Ha (ML No.: 09/1994)” located at N/v: Asan, Tehsil: Raipur, District: Pali, Rajasthan.
Sir,
We are herewith submitting an application for Environmental Clearance for our Mining Project “Asan Quartz and Feldspar Mine, Lease Area: 5.00 Ha. (ML No.: 09/1994) categorized as Category ‘B-2” Project as per As per EIA Notification dated 14.09.2006 and its Subsequent amendments & as per notification no. S.O. 141 (E) dated: 15.01.2016. N/v: Asan, Tehsil: Raipur, District: Pali, Rajasthan for your kind perusal & necessary action.
In regards to above, we are enclosing the following documents:
1. Form-1 M 2. Pre-feasibility Report 3. Approved Mining Plan 4. Annexure 5. Soft copy of the documents
Kindly consider our project in upcoming SEAC Meeting at your earliest. Thanking you Yours Truly,
Amit Kumar Jain (Applicant)
Project Name: Asan Quartz & Feldspar Mine, N/v: Asan, Tehsil: Raipur, Pali
ML No.: 09/1994
ANNEXURE-E
Part-(A) LAND: STAGE WISE LAND USE AND RECLAMATION AREA (Ha.) S.
No. Land use Category Present 5th Year End of life of
mine 1 Top Soil Dump -- -- -- 2 Waste Dump (External) -- 0.5800 -- 3 Excavation (Voids Only) 0.0350 1.3500 1.3500 4 Road -- 0.0200 0.0200 5 Built Up Area -- 0.0100 0.0100 6 Township Area -- -- -- 7 Afforestation -- 1.6500 1.6500 8 Reclamation (Backfilled) -- -- -- 9 Mineral Storage -- 0.0200 -- 10 Processing (Crushing) -- -- -- 11 Undisturbed Area 4.9650 1.3700 1.9700 Total 5.0000 5.0000 5.0000
Post Mining Plan (Conceptual) Land Pattern Of ML Area (Ha.) Part-(B) POST MINING LAND USE OF CORE ZONE WITH ENVIRONMENT
MANAGEMENT S. No.
Description Land Use (In Ha.) Plantation Water
Body Public
Use Undisturbed Total
1 Top Soil Dump -- -- -- -- -- 2 External Waste
Dump -- -- -- -- --
3 (a) Excavation (Voids)
-- 1.3500 -- -- 1.3500
(b) Excavation (backfilled)
-- -- -- -- --
4 Road -- -- 0.0200 -- 0.0200 5 Built Up Area -- -- 0.0100 -- 0.0100 6 Township Area -- -- -- -- -- 7 Afforestation 1.6500 -- -- -- 1.6500 8 Mineral Storage -- -- -- -- -- 9 Undisturbed Area -- -- -- 1.9700 1.9700 Total 1.6500 1.3500 0.0300 1.9700 5.0000
Project Name: Asan Quartz & Feldspar Mine, N/v: Asan, Tehsil: Raipur, Pali
ML No.: 09/1994
Ecology: Stage wise Cumulative Plantation Part-(C) REQUIREMENTS FOR PLANTS FOR AFFORESTATION AND
RECLAMATION Year Un-worked Area Waste Dump
(Outside) Inside Dump (Reclaimed
Area)
Top Soil Dumps
Total
Area (Ha.)
No. of Trees
Area (Ha.)
No. of Trees
Area (Ha.)
No. of Trees
Area (Ha.)
No. of Trees
Area (Ha.)
No. of Trees
Existing -- -- -- -- -- -- -- -- -- -- 1st 0.33 132 -- -- -- -- -- -- 0.33 132 2nd 0.33 132 -- -- -- -- -- -- 0.33 132 3rd 0.33 132 -- -- -- -- -- -- 0.33 132 4th 0.33 132 -- -- -- -- -- -- 0.33 132 5th 0.33 132 -- -- -- -- -- -- 0.33 132
6th Year Onwards
-- -- -- -- -- -- -- -- -- --
Total 1.65 660 -- -- -- -- -- -- 1.65 660
AMIT KUMAR JAIN S/o Shri Ratan Lal Jain
R/o: 5, Vinod Nagar, Beawar, District: Ajmer (Rajasthan) Statement of Commitment with reference to the “Asan Quartz & Feldspar Mine
(ML No.: 09/1994) located at N/v: Asan, Tehsil: Raipur, District: Pali, Rajasthan.
Following are the commitment related to the above mentioned project agreed by
the project proponent during EIA presentation to the SEAC for compliance and
presented for verification during post EC period, to RPCB and MoEF&CC along
with other EC conditions.
S. No.
Commitments under Various Heads
Ref page no in Form-1 M,PFR
etc.
Final Responsibility (Status of
compliance) Total 660 saplings will be
planted along the barrier of 7.5 m along the boundary of mine lease which will cover 1.65 Hectare land i.e. 33% of the total lease area for plantation. Certain Species like Khejri, Pipal, Ker, Sisham, Babool, Neem & Khakhra which are more suitable to local soil are proposed to be planted.
PFR Pg. No. 21
Will be complied
ESR (Entrepreneur Social responsibility) Rs. 50,000/-
PFR Pg. No. 28
Will be complied
Cost proposed for Environmental management Rs. 1,00,000/-
PFR Pg. No. 30
Will be complied
Budget for labour welfare Rs 1,00,000/- (Recurring Cost)
PFR Pg. No. 29
Will be complied
Date: 05.03.2016
Amit Kumar Jain