Aggregate planning

Part Available-To-PromiseCapable-To-Promise

Skorkovský

http://higheredbcs.wiley.com/legacy/college/russell/0471692093/ppt/ch13.ppt

Roadmap (taken form Operation Management- Russel and Taylor)

Qua

ntity

Global O

perations

Competitivness

Supply Chain Management

Supply Chain Forecasting

InventoryManagement

Lean Production

AggregatePlanning

ResourcePlanning

MS Dynamics NAV example ATP

It was produced before

MS Dynamics NAV example ATP

MS Dynamics NAV example ATP

-101=-111+10

Continuation of the sales line

MS Dynamics NAV example ATP

Order promising

Calculate->ATP

MS Dynamics NAV example ATP

Instead of 31.12.2009

Accept

End of the sales lineF6

MS Dynamics NAV example ATP

F6

144=45+99

MS Dynamics NAV example CTP

No production orders created so far, part of the sales order header and sales line looks like :

MS Dynamics NAV example CTP

From forecats

MS Dynamics NAV example CTPOrder->Order Promising->Calculate->Capable-To-Promise-> Accept

Planning line was created