910 St. Andrews RdLocal Drainage Project (LDP)

Pre-Construction Community Meeting

WBS NO. M-000291-001A-4Hien Pham, P.E.

January 30, 2018

1 OVERVIEW OF THE PROJECT

2 PROJECT SCOPE AND PHASING

3 WHAT TO EXPECT DURING CONSTRUCTION

4 CONTACT INFORMATION

AGENDA

2

February Construction Begins

2018 May

Anticipated Completion

910 St. Andrews Rd LDP(WBS NO. M-000291-001A-4)

NOTE: EXPECTED DATES ARE ESTIMATES, MAY CHANGE DURING CONSTRUCTION

Project Map

• Replace/upsize existing inlets

910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)

Identified Improvement Needs

• Regrade roadside ditches

• Replace/upsize 24-inch to 36-inch storm sewers and culverts

910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)

What to Expect During Construction

Prepare for Construction• Residents will be notified minimum 72 hours prior to

start of construction activities• Plan for potential service impacts• Be mindful of protective barriers• Remove valuables in close proximity to the roadside

ditches

Potential Service Impacts:• Potential water service impacts, if needed• Potential parking/driveway access impacts, if needed

!

910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)

What to Expect During Construction

Parking and Driveway Access• Short-periods of limited access to your driveway• Contact us immediately if needing handicapped

access• Construction will alternate each side of the street

on different schedules

6P

910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)

What to Expect During Construction

Driveways• Driveway aprons will be reconstructed

910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)

What to Expect During Construction

Restoration• Sodding the sides of ditches will be done when construction is

complete.• City does not approve final payment to contractor until restoration is

complete.• If you have concerns:

• Document (writing, photo, etc.)• Call 3-1-1• Do not make the repairs yourself

910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)

Construction – How to Report a Problem

Contact 311• Report the project number

• Request issue be directed to Public Works Capital Projects

• Be as detailed as possible with your concern.

• Please remember to provide your contact information and address.

9

Contact us at: pwecip@houstontx.gov

910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)

Contact Information

Contact us at pwecip@

houstontx.gov

Shawn Sidhu, Project Manager (713) 991-6685

AJ Kessinger, Project Manager (832) 395-2957

Chuck Uecker, Inspector (832) 596-4376

Reliance Construction Services, Inc. (Contractor)

Houston Public Works (Oversight)

910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)

IMPORTANT LINKS

For a complete listing of Frequently Asked Questions please visit:• https://www.publicworks.houstontx.gov/ecd/faqs.html

Today’s presentation and additional project information can be found at:

https://rebuildhouston.org/community-engagement

i

THANK YOU

Q&A to follow